1. We will continue to respond to remaining IDRs as they are issued, maintaining our track
1. We will continue to respond to remaining IDRs as they are issued, maintaining our track record of timely and complete responses.
2. The Whitmore team will finalize the rebuttal framework in anticipation of Dr. Washburne
2. The Whitmore team will finalize the rebuttal framework in anticipation of Dr. Washburne's analysis as more details of his approach emerge.
3. I plan to request a mid-examination conference with Supervisory Revenue Agent Gerald Me
3. I plan to request a mid-examination conference with Supervisory Revenue Agent Gerald Meskill, targeted for May 2023, to discuss the examination's status and attempt to narrow remaining issues.
4. I recommend that we schedule a call in the coming weeks with you, Deborah, and Raj Iyer
4. I recommend that we schedule a call in the coming weeks with you, Deborah, and Raj Iyer to discuss the implications of the IRS economist's involvement and to begin preliminary discussions about PPC's posture in the event a significant NOPA is issued. My office will reach out to coordinate calendars.
5. We will provide prompt updates on any further developments regarding Dr. Washburne's an
5. We will provide prompt updates on any further developments regarding Dr. Washburne's analysis or other material examination developments. Marcus, I am available to discuss any aspect of this update at your convenience. Our next quarterly status report (covering Q1 2023 activity) will be circulated separately on its usual schedule. Please do not hesitate to reach out with any questions in the interim. Best regards,