Contract analysis / chazen-preliminary-findings-memo.docx
chazen-preliminary-findings-memo.docx
High · 3
Medium · 3
Standard · 0
I. Introduction and Engagement Summary
Medium
⚑ Forum / governing law
I. Introduction and Engagement Summary 1.1 Purpose of Memorandum This memorandum presents my preliminary findings from the construction delay and critical path analysis I have conducted in connection with the above-captioned matter. The purpose of this memorandum is to provide counsel with a comprehensive summary of my initial analytical conclusions regarding the causes and allocation of schedule delays on the Northg
1. The Master Construction Agreement ("MCA") dated March 15, 2020, between Northgate Fibe
1. The Master Construction Agreement ("MCA") dated March 15, 2020, between Northgate Fiber Americas Inc. and Meridian Infrastructure Partners LLC ("Meridian"), including all exhibits thereto. I have paid particular attention to Exhibit B (Milestone Values), Exhibit C (Technical Specifications incorporating NS-FIBER-2020), and Exhibit D (Baseline CPM Schedule).
2. The MCA project schedule and the fourteen (14) defined milestones set forth under MCA
2. The MCA project schedule and the fourteen (14) defined milestones set forth under MCA § 8.2, including the contractually specified milestone completion dates and associated milestone payment values.
3. Monthly progress reports and schedule updates submitted by Meridian to NFA's construct
3. Monthly progress reports and schedule updates submitted by Meridian to NFA's construction management team, spanning the period from April 2020 through March 2024. These monthly submissions include narrative progress reports, updated CPM schedules, look-ahead schedules, and earned value data.
4. Two hundred eighty-seven (287) Non-Conformance Reports, of which forty-three (43) were
4. Two hundred eighty-seven (287) Non-Conformance Reports, of which forty-three (43) were classified as "critical" and two hundred forty-four (244) were classified as "non-critical." I have reviewed the full catalog of these NCRs as organized in the spreadsheet prepared by Calderwood & Harkness, which includes dates, phases, milestones, defect types, severity classifications, cure status, and estimated remediation co
5. Cure Notice No. 1, dated January 18, 2024, issued by NFA to Meridian; Meridian's respo
Medium
⚑ Notice / time limit to track
5. Cure Notice No. 1, dated January 18, 2024, issued by NFA to Meridian; Meridian's response thereto, dated February 2, 2024; Cure Notice No. 2, dated February 19, 2024; Meridian's Corrective Action Plan, submitted March 5, 2024; NFA's rejection of the Corrective Action Plan, dated March 12, 2024; and the Notice of Termination for Cause, issued April 1, 2024.
6. Deposition transcripts of the following witnesses:
6. Deposition transcripts of the following witnesses: (a) Renata Voss, deposed November 12–13, 2024; (b) Sean Calloway, deposed November 19, 2024; (c) Marcus Henley, deposed December 3–4, 2024; and (d) Victor Sandoval, deposed December 10–11, 2024.
7. Northgate's internal quality assurance monthly reports documenting quality defects ide
7. Northgate's internal quality assurance monthly reports documenting quality defects identified during Phase 2 construction activities, including field photographs, test data, and corrective action tracking logs.
8. Payment applications and progress certifications for all three phases of the project,
8. Payment applications and progress certifications for all three phases of the project, including NFA's marked-up responses, disputed line items, and correspondence regarding payment withholding.
9. Meridian's Verified Complaint, filed July 15, 2024, and NFA's Answer with Counterclaim
9. Meridian's Verified Complaint, filed July 15, 2024, and NFA's Answer with Counterclaims, filed September 3, 2024.
10. Select documents from Northgate's document production of approximately 1.4 million do
10. Select documents from Northgate's document production of approximately 1.4 million documents (3.2 TB) and Meridian's document production of approximately 890,000 documents (1.8 TB), as identified and provided to me by Calderwood & Harkness. My review has focused on the documents most relevant to schedule, delay causation, quality defects, cure efforts, and the termination decision.
11. Third-party subpoena responses received to date. I note that seven (7) subcontractor
11. Third-party subpoena responses received to date. I note that seven (7) subcontractor subpoenas and three (3) municipal permitting authority subpoenas remain outstanding, and I expect the responses to those subpoenas to provide additional relevant information, particularly regarding the permitting timeline and subcontractor performance issues.
12. Weather data from the National Oceanic and Atmospheric Administration ("NOAA") for th
12. Weather data from the National Oceanic and Atmospheric Administration ("NOAA") for the seven-state project area, covering the period from April 2020 through April 2024.
13. Industry data on construction labor market conditions and fiber cable supply chain le
13. Industry data on construction labor market conditions and fiber cable supply chain lead times for the period 2020–2024. A comprehensive list of all materials reviewed will be finalized and included as Appendix B to my final expert report.
II. Project Overview and Contractual Framework
High
⚑ Penalty / liquidated damages
II. Project Overview and Contractual Framework 2.1 The Master Construction Agreement The Master Construction Agreement between NFA and Meridian was executed on March 15, 2020. NFA issued its Notice to Proceed ("NTP") on April 1, 2020, establishing the commencement date for the project schedule. The scope of work under the MCA encompasses the design, engineering, permitting, and construction of approximately 18,500 ro
III. Critical Path Analysis Methodology
III. Critical Path Analysis Methodology 3.1 Methodology Overview My analysis employs a contemporaneous schedule analysis approach, utilizing an as-planned versus as-built methodology supplemented by a "windows analysis" technique. This methodology is widely recognized and accepted in the construction industry and in construction litigation as a reliable method for identifying, quantifying, and allocating delays on co
1. Meridian's Baseline CPM Schedule. The baseline CPM schedule submitted with the MCA as
1. Meridian's Baseline CPM Schedule. The baseline CPM schedule submitted with the MCA as Exhibit D serves as the starting point for the as-planned analysis. This schedule was developed by Meridian's project controls team and was accepted by NFA at the time of contract execution. It contains approximately 4,200 activities, including design, permitting, mobilization, construction (boring, trenching, cable placement, sp
2. Monthly Schedule Updates. Meridian submitted monthly schedule updates to NFA's constru
2. Monthly Schedule Updates. Meridian submitted monthly schedule updates to NFA's construction management team, led by Sean Calloway, throughout the project's duration from April 2020 through March 2024. These updates include revised activity durations, actual start and finish dates for completed activities, percentage complete for in-progress activities, and narrative explanations for schedule variances.
3. Daily Field Reports and Crew Mobilization Logs. Meridian's field operations team, unde
3. Daily Field Reports and Crew Mobilization Logs. Meridian's field operations team, under the direction of Marcus Henley (VP of Field Operations), maintained daily field reports documenting crew counts, equipment utilization, weather conditions, work activities performed, and any issues or incidents encountered. These reports provide granular data on actual work progress and resource deployment.
4. NFA's Internal Project Tracking Database and QA Monitoring Reports. NFA maintained its
4. NFA's Internal Project Tracking Database and QA Monitoring Reports. NFA maintained its own internal project tracking system, which includes records of inspections, test results, NCR issuances and dispositions, and progress assessments. The QA monitoring reports provide an independent record of work quality and progress that can be compared against Meridian's self-reported data.
5. Weather Data. I obtained historical weather data from the National Oceanic and Atmosph
5. Weather Data. I obtained historical weather data from the National Oceanic and Atmospheric Administration ("NOAA") for each geographic corridor within the seven-state project area. This data includes daily temperature, precipitation, snowfall, and wind speed records, which I have used to assess whether any delays were attributable to unusually severe weather conditions qualifying as force majeure events under MCA
6. Municipal Permitting Records. I have reviewed the municipal permitting records obtaine
6. Municipal Permitting Records. I have reviewed the municipal permitting records obtained to date through third-party subpoenas. As noted, responses from several municipal authorities remain outstanding, and this is an area where my analysis may be refined upon receipt of additional data.
7. Change Request Correspondence. I have reviewed the correspondence between the parties
High
⚑ Penalty / liquidated damages
7. Change Request Correspondence. I have reviewed the correspondence between the parties relating to Change Order Requests, alleged scope changes, and Requests for Information ("RFIs"), to the extent such correspondence has been produced in discovery and identified by Calderwood & Harkness as relevant to my analysis. 3.3 Analysis Windows I have organized my analysis into three primary windows corresponding to the thr
IV. Phase-by-Phase Delay Analysis and Findings
High
⚑ Penalty / liquidated damages
IV. Phase-by-Phase Delay Analysis and Findings 4.1 Phase 1: New York Metro & Northern New Jersey (Milestones 1–4) 4.1.1 Milestones 1, 2, and 4 Milestones 1, 2, and 4 were completed either on time or within the contractual tolerances established in the MCA. My analysis has not identified any significant critical path delays for these milestones. Meridian's initial mobilization during Phase 1 was generally smooth, and
V. Analysis of Meridian's Asserted Delay Excuses
Medium
⚑ Liability cap to check against exposure
V. Analysis of Meridian's Asserted Delay Excuses Meridian has advanced several arguments in its pleadings and through its discovery positions to explain and justify the project delays. In this section, I address each of Meridian's principal delay defenses and provide my preliminary assessment of their validity and their impact — or lack thereof — on the critical path and overall delay allocation. 5.1 Owner Permitting