Contract analysis
Clause-by-clause risk read on any document of the firm. Pick a contract, or open any document from a matter.
Contract analysis / sep-compliance-reporting-schedule.xlsx
sep-compliance-reporting-schedule.xlsx
High · 1
Medium · 0
Standard · 0
[sheet: Overview]
High
⚑ Penalty / liquidated damages
[sheet: Overview] SEP ID | SEP Name | Location | State | Associated Site | Total Budget ($M) | Consent Decree Section Reference | TMC Responsible Officer | Lead Consultant / Implementer | Independent Monitor | Effective Date | Final Completion Deadline | Status SEP-01 | Flint Creek Watershed Restoration Project | Flint Creek, downstream of Ridgecrest Mine, Granite County, Montana | Montana | Ridgecrest Copper-Molybde