[sheet: Cover & Summary]
Field | Value
Document Title | Litigation Budget and Staffing Plan
Prepared By | Calderwood & Harkness LLP
Prepared For | Optiwave Semiconductor Corp. / Ridgeline Capital Partners, LP
Date | March 25, 2024
Matter | Optiwave Semiconductor Corp. v. Lumicore Technologies, Inc.
Case No. | 2:24-cv-00319-JRG
Court | United States District Court for the Eastern District of Texas, marshall Division
Presiding Judge | Judge James R. Gilstrap
Client | Optiwave Semiconductor Corp.
Client HQ | 4810 Bayside Technology Parkway, Suite 300, Santa Clara, CA 95054
Client General Counsel | Rebecca Tanaka
Client CFO | David Leitner
PE Sponsor | Ridgeline Capital Partners, LP
PE Sponsor HQ | 200 Clarendon Street, 40th Floor, Boston, MA 02116
PE Sponsor Contact / Board Chair | Franklin Osei, Managing Partner
Board Resolution Authorizing Spend | OWS Board Resolution No. 2024-07
Defendant | Lumicore Technologies, Inc.
Defendant HQ | 9200 Spectrum Boulevard, Building C, Austin, TX 78759
Lead Litigation Counsel | Calderwood & Harkness LLP
C&H Main Office | 350 South Grand Avenue, 48th Floor, Los Angeles, CA 90071
C&H DC Office | 1201 F Street NW, Suite 700, Washington, DC 20004
Responsible Partner | Alan Ngo (IP Litigation)
Billing Partner | Marcus Delgado (IP Litigation)
Lead Associate | Wendy Schultz (IP Litigation)
Working Associate | Omar Siddiqui (IP Litigation)
Local Counsel | Whitmore & Callahan LLP (Jim Callahan), 110 North College Avenue, Suite 800, Tyler, TX 75702
Engagement Letter Date | March 18, 2024
Anticipated Complaint Filing | April 22, 2024
Anticipated Trial Date | February 2, 2026 (estimated 7–10 days)
Total Approved Budget | $18,500,000
Damages Sought | ~$210,000,000
Asserted Patents | U.S. 10,234,847; U.S. 10,891,193; U.S. 9,678,562; U.S. 11,402,015
Accused Products | LumiLink 400G-ZR+; LumiLink 800G-DR8; LumiEdge 1600G-LR
Success Fee Component | 5% of net recovery above $150M (per engagement letter)
Blended Cap Rate | $925/hr (negotiated with Ridgeline Capital Partners)
D&O / Litigation Cost Insurance | Pacific Rim Insurance Group, Policy No. PLI-2023-08812
Approval Requested From | Franklin Osei, Board Chair / Managing Partner, Ridgeline Capital Partners, LP
Approval Signature Line | ____________________________
Approval Date Line | ____________________________
[sheet: Phase Budget Summary]
Phase No. | Phase Name | Description | Approximate Timeframe | C&H Attorney Fees | C&H Paralegal Fees | Local Counsel Fees | Expert Fees | Third-Party / Vendor Costs | Court Costs & Filing Fees | Travel & Miscellaneous | Phase Total | % of Total Budget
1 | Pre-Suit Investigation & Strategy | Retention of Benchmark Semiconductor Analysis for teardown review; infringement analysis; patent portfolio assessment; engagement of FairPoint Licensing Group coordination; pre-suit strategy development; litigation hold implementation; conflict clearance | Mar 2024 | 850000 | 75000 | 25000 | 200000 | 30000 | 0 | 20000 | 1200000 | 6.5%
2 | Pleadings & Initial Motions | Drafting and filing complaint (7 counts: 4 direct infringement, induced, contributory, willful); civil cover sheet; summons; pro hac vice applications (Ngo, Schultz, Siddiqui); opposition to motion to transfer; reply to counterclaims; proposed protective order; Rule 26(f) report; initial disclosures; docket control order | Apr–Aug 2024 | 1250000 | 125000 | 150000 | 0 | 50000 | 25000 | 200000 | 1800000 | 9.7%
3 | Fact discovery | Drafting and responding to interrogatories (25 each side), RFPs (85 initial + 30 supplemental), RFAs (40); ESI protocol; document review (~182,000 OWS docs / ~1.4M pages for production); privilege log preparation (est. 1,247+ entries); 30(b)(6) notice (18 topics); fact depositions (~17 total including Huang, Michaud, Bautista, Reeves, Ng, Melissa Chen, and others); third-party subpoenas (Solara records, Melissa Chen at Veridian Photonics); motion to compel opinion-of-counsel letters; meet-and-confer correspondence | Aug 2024–May 2025 | 3200000 | 350000 | 200000 | 375000 | 350000 | 15000 | 110000 | 4600000 | 24.9%
4 | Claim Construction | Joint claim construction statement (14 disputed terms); opening claim construction brief (50 pages); reply brief; declarations of Dr. Caroline Ashford (Northfield Institute of Technology) and Dr. Jian-Wei Huang; intrinsic and extrinsic evidence appendices; claim construction tutorial for Judge Gilstrap; Markman hearing presentation (60+ slides); prosecution history estoppel analyses ('193 and '015 Patents); means-plus-function analysis; claim differentiation analysis; proposed claim construction order | Oct 2024–Mar 2025 | 1600000 | 100000 | 75000 | 225000 | 25000 | 5000 | 70000 | 2100000 | 11.4%
5 | Expert discovery | Retention and coordination of three plaintiff experts: Dr. Caroline Ashford (infringement/validity, $950/hr, budget $1.1M), Dr. Lawrence Keating (damages, $875/hr, budget $950K), Gregory Falk (industry, $650/hr, budget $375K); drafting expert reports (infringement, validity rebuttal, damages with Panduit/Georgia-Pacific/willful enhancement analyses, industry background); expert depositions (preparation and defense of Ashford, Keating, Falk depositions); offensive depositions of defendant experts Dr. Rajesh Sundaram (Pacific Western University) and Dr. Natasha Volkov (Pinnacle Analytics Partners LLP) | Jun–Aug 2025 | 1200000 | 100000 | 50000 | 1850000 | 100000 | 0 | 100000 | 3400000 | 18.4%
6 | Dispositive Motions & Daubert | Partial SJ on infringement of '562 Patent (Claims 1, 4, 6); partial SJ on validity of '015 Patent (prior-conception defense); oppositions to anticipated defense SJ motions on doctrine of equivalents (prosecution history estoppel) and EMVR; Daubert motions against Dr. Sundaram (validity) and Dr. Volkov (damages); opposition to anticipated Daubert motion on Dr. Keating | Sep–Nov 2025 | 1450000 | 75000 | 100000 | 150000 | 50000 | 10000 | 65000 | 1900000 | 10.3%
7 | Trial Preparation | Trial strategy memorandum; proposed jury instructions; proposed verdict form; witness list (13+ witnesses); exhibit list (~340 exhibits organized P-001 through P-340); deposition designation charts; trial demonstratives (infringement and damages modules); motions in limine; pre-trial conference statement; voir dire questions; opening statement outline; witness preparation | Oct 2025–Jan 2026 | 1650000 | 125000 | 100000 | 200000 | 100000 | 10000 | 115000 | 2300000 | 12.4%
8 | Trial | 7–10 day jury trial before Judge Gilstrap; opening statements; direct and cross-examination of live witnesses; presentation of deposition designations; expert testimony; demonstrative presentations; closing arguments; post-trial motions (JMOL, new trial if needed); verdict | Feb 2026 | 750000 | 50000 | 75000 | 100000 | 25000 | 5000 | 195000 | 1200000 | 6.5%
TOTAL | Mar 2024–Feb 2026 | 11950000 | 1000000 | 775000 | 3100000 | 730000 | 70000 | 875000 | 18500000 | 100.0%
Notes | Contingency reserve of $0 allocated from success fee component (5% of net recovery above $150M per engagement letter); success fee is separate from the $18.5M budget. All figures rounded to nearest $5,000 within phases; totals are exact.
[sheet: Billing Rate Schedule]
Timekeeper / Vendor | Organization | Role | Bar Admissions | Standard Rate ($/hr) | Blended Cap Rate ($/hr) | Effective Rate ($/hr) | Notes
Alan Ngo | Calderwood & Harkness LLP | Responsible Partner (IP Litigation) | CA; TX E.D. (pro hac vice) | 1350 | 925 | 925 | Blended cap applies to all C&H time; cap rate negotiated with Ridgeline Capital Partners
Marcus Delgado | Calderwood & Harkness LLP | Billing Partner (IP Litigation) | TX; CA | 1250 | 925 | 925
Wendy Schultz | Calderwood & Harkness LLP | Lead Associate (IP Litigation) | CA; TX E.D. (pro hac vice) | 825 | 925 | 825 | Standard rate below cap; billed at standard rate
Omar Siddiqui | Calderwood & Harkness LLP | Working Associate (IP Litigation) | CA; TX E.D. (pro hac vice) | 725 | 925 | 725 | Standard rate below cap; billed at standard rate
C&H Paralegal Staff | Calderwood & Harkness LLP | Paralegals | N/A | 375 | 925 | 375 | Standard rate below cap; billed at standard rate
James 'Jim' Callahan | Whitmore & Callahan LLP | Local Counsel Partner (E.D. Tex.) | TX; E.D. Tex. | 575 | N/A | 575 | Local counsel retainer dated April 5, 2024; separate from C&H blended cap
W&C Associate | Whitmore & Callahan LLP | Local Counsel Associate | TX | 400 | N/A | 400
W&C Paralegal | Whitmore & Callahan LLP | Local Counsel Paralegal | N/A | 275 | N/A | 275
Dr. Caroline Ashford | Northfield Institute of Technology | Technical / Infringement Expert | N/A | 950 | N/A | 950 | Expert retention agreement dated August 1, 2024; estimated budget $1,100,000
Dr. Lawrence Keating | Meridian Economic Consulting Group, LLC | Damages Expert | N/A | 875 | N/A | 875 | Expert retention agreement dated August 5, 2024; estimated budget $950,000
Gregory Falk | Independent Consultant (formerly Solara Optics, Inc.) | Industry Expert | N/A | 650 | N/A | 650 | Expert retention agreement dated August 8, 2024; estimated budget $375,000
Benchmark Semiconductor Analysis, LLC (Kevin Ng, Lead Engineer) | Benchmark Semiconductor Analysis, LLC | Reverse-Engineering / Teardown Lab | N/A | Project-based | N/A | Project-based | Estimated budget $375,000; teardown of LumiLink 400G-ZR+, LumiLink 800G-DR8, LumiEdge 1600G-LR
[sheet: Staffing Matrix]
Phase | Alan Ngo — Partner (hrs) | Marcus Delgado — Partner (hrs) | Wendy Schultz — Sr. Associate (hrs) | Omar Siddiqui — Associate (hrs) | C&H Paralegals (hrs) | Jim Callahan — Local Counsel (hrs) | W&C Associate (hrs) | W&C Paralegal (hrs) | Total Phase Hours | C&H Weighted Avg Rate Check ($/hr)
Phase 1: Pre-Suit Investigation & Strategy | 80 | 40 | 200 | 250 | 100 | 20 | 10 | 15 | 715 | $843
Phase 2: Pleadings & Initial Motions | 120 | 80 | 350 | 400 | 200 | 100 | 50 | 40 | 1340 | $848
Phase 3: Fact discovery | 200 | 150 | 800 | 1000 | 600 | 120 | 80 | 80 | 3030 | $800
Phase 4: Claim Construction | 200 | 100 | 450 | 400 | 150 | 50 | 20 | 25 | 1395 | $831
Phase 5: Expert discovery | 150 | 80 | 350 | 300 | 150 | 30 | 15 | 15 | 1090 | $821
Phase 6: Dispositive Motions & Daubert | 200 | 100 | 400 | 350 | 100 | 60 | 30 | 20 | 1260 | $848
Phase 7: Trial Preparation | 250 | 120 | 450 | 350 | 200 | 60 | 30 | 25 | 1485 | $835
Phase 8: Trial | 150 | 80 | 200 | 100 | 50 | 50 | 25 | 15 | 670 | $862
TOTAL HOURS | 1350 | 750 | 3200 | 3150 | 1550 | 490 | 260 | 235 | 10985 | $829
Rate Check: Total C&H Fees ÷ Total C&H Hours | C&H Attorney + Paralegal Fees = $12,950,000 ÷ 10,000 C&H hrs = ~$829/hr (≤ $925 cap)
[sheet: Expert Fee Detail]
Expert / Vendor | Organization | Role | Hourly Rate ($/hr) | Estimated Hours | Report Preparation | Deposition Preparation & Testimony | Trial Testimony & Preparation | Travel & Expenses | Total Estimated Fee | Retention Agreement Date | Notes
Dr. Caroline Ashford | Northfield Institute of Technology | Technical / Infringement & Validity Expert | 950 | 1158 | 550000 | 250000 | 200000 | 100000 | 1100000 | 2024-08-01 | Infringement report (literal + DOE for '193 Claims 3/7 and '015 Claim 12); validity rebuttal report addressing 23 prior-art references; deposition defense; trial testimony
Dr. Lawrence Keating | Meridian Economic Consulting Group, LLC | Damages Expert | 875 | 1086 | 475000 | 200000 | 175000 | 100000 | 950000 | 2024-08-05 | Lost profits (Panduit, $128.9M est.); reasonable royalty (Georgia-Pacific, 8.5% rate, $37.5M est.); willful/enhanced damages analysis ($109.2M post-notice); total demand ~$210M
Gregory Falk | Independent Consultant (formerly Solara Optics, Inc.) | Industry Expert | 650 | 577 | 175000 | 75000 | 75000 | 50000 | 375000 | 2024-08-08 | Silicon-photonics transceiver market background; competitive landscape; commercial significance of patented innovations; supports secondary considerations of non-obviousness
Benchmark Semiconductor Analysis, LLC (Kevin Ng) | Benchmark Semiconductor Analysis, LLC | Reverse-Engineering / Teardown Lab | Project | N/A | 250000 | 50000 | 50000 | 25000 | 375000 | 2022-11 (initial retention) | Teardowns of LumiLink 400G-ZR+ (Dec 2022), LumiLink 800G-DR8 (Jun 2023), LumiEdge 1600G-LR (Feb 2024); chain-of-custody documentation; trial testimony support
TOTAL | 1450000 | 575000 | 500000 | 275000 | 2800000 | Expert/vendor subtotal $2,800,000. Additional $300K for other third-party/vendor costs (e-discovery platforms, demonstrative graphics, court reporting, etc.) allocated across phases brings total expert/vendor line to $3,100,000.
Notes | Expert fees are estimated and subject to adjustment based on case developments. Hourly experts' estimated hours are approximate (Total Fee ÷ Hourly Rate). Benchmark is project-based. All expert retention agreements include indemnification provisions.
[sheet: Phase Detail — Milestones]
Phase | Task / Milestone | Responsible Timekeeper(s) | Target Start Date | Target Completion / Filing Date | Estimated Hours | Estimated Cost | Status | Notes / Dependencies
Phase 1: Pre-Suit | Conflict clearance memorandum | Wendy Schultz | 2024-03-14 | 2024-03-14 | 5 | 4125 | Complete | Cleared prior unrelated C&H work for Silverstone Capital Markets LLC
Phase 1: Pre-Suit | Engagement letter execution | Alan Ngo / Marcus Delgado | 2024-03-15 | 2024-03-18 | 10 | 9250 | Complete | Includes blended cap rate $925/hr, success fee 5% above $150M
Phase 1: Pre-Suit | Litigation hold memorandum to OWS | Alan Ngo / Wendy Schultz | 2024-03-20 | 2024-03-22 | 15 | 12750 | Complete | 14 custodians identified; directed to Rebecca Tanaka and OWS IT
Phase 1: Pre-Suit | Document preservation protocol — internal C&H | Wendy Schultz | 2024-03-22 | 2024-03-22 | 8 | 6600 | Complete
Phase 1: Pre-Suit | Review Benchmark teardown reports (3 products) | Omar Siddiqui / Wendy Schultz | 2024-03-18 | 2024-03-25 | 80 | 60000 | Complete | LumiLink 400G-ZR+ (Dec 2022), 800G-DR8 (Jun 2023), LumiEdge 1600G-LR (Feb 2024)
Phase 1: Pre-Suit | Pre-suit infringement analysis | Wendy Schultz / Omar Siddiqui | 2024-03-18 | 2024-03-28 | 120 | 93000 | Complete | All 4 patents against all 3 accused products
Phase 1: Pre-Suit | Patent portfolio assessment and selection | Alan Ngo / Omar Siddiqui | 2024-03-18 | 2024-03-25 | 50 | 40000 | Complete | Selected 4 of 142 OWS patents for assertion
Phase 1: Pre-Suit | FairPoint Licensing Group coordination — pre-suit notice history | Alan Ngo / Wendy Schultz | 2024-03-19 | 2024-03-25 | 25 | 21875 | Complete | Reviewed Jan 15, 2023 and May 15, 2023 licensing letters; April 20, 2023 meeting notes
Phase 1: Pre-Suit | Benchmark Semiconductor Analysis — additional teardown coordination | Omar Siddiqui | 2024-03-20 | 2024-03-28 | 30 | 21750 | Complete | Confirmation of chain-of-custody protocols for LumiEdge 1600G-LR (Feb 2024 teardown)
Phase 1: Pre-Suit | Pre-suit strategy memorandum to OWS Board / Ridgeline Capital | Alan Ngo / Marcus Delgado | 2024-03-22 | 2024-03-25 | 20 | 18500 | Complete | Risk/benefit analysis; recommended filing in E.D. Tex.
Phase 1: Pre-Suit | Budget and staffing plan preparation (this document) | Alan Ngo / Marcus Delgado | 2024-03-20 | 2024-03-25 | 20 | 18500 | Complete | Submitted to Ridgeline Capital Partners for approval
Phase 1: Pre-Suit | Validity assessment — prior art search and analysis | Omar Siddiqui / Wendy Schultz | 2024-03-20 | 2024-03-28 | 60 | 46500 | Complete | Identified 23 potential prior art references; assessed strength of each patent
Phase 2: Pleadings | Drafting original complaint (7 counts) | Wendy Schultz / Omar Siddiqui / Alan Ngo | 2024-03-25 | 2024-04-22 | 200 | 162500 | Complete | Counts: 4 direct infringement, induced, contributory, willful; literal + DOE allegations
Phase 2: Pleadings | Civil cover sheet and summons | Omar Siddiqui | 2024-04-18 | 2024-04-22 | 5 | 3625 | Complete
Phase 2: Pleadings | Pro hac vice applications (Ngo, Schultz, Siddiqui) | Omar Siddiqui | 2024-04-15 | 2024-04-18 | 10 | 7250 | Complete | Local counsel designation: Jim Callahan, Whitmore & Callahan LLP
Phase 2: Pleadings | Local counsel retainer agreement | Alan Ngo | 2024-04-01 | 2024-04-05 | 5 | 4625 | Complete | Jim Callahan $575/hr; associate $400/hr; paralegal $275/hr
Phase 2: Pleadings | Insurance coverage notification to Pacific Rim Insurance Group | Alan Ngo | 2024-04-23 | 2024-04-24 | 3 | 2775 | Complete | Policy No. PLI-2023-08812
Phase 2: Pleadings | Rule 26(f) conference and joint report | Wendy Schultz / Jim Callahan | 2024-05-20 | 2024-06-03 | 25 | 20625 | Complete | ESI protocol negotiation included
Phase 2: Pleadings | Initial disclosures (P.R. 3-1) | Wendy Schultz / Omar Siddiqui | 2024-06-01 | 2024-06-10 | 30 | 23250 | Complete | Infringement contentions, witness list, document list
Phase 2: Pleadings | Opposition to motion to transfer venue | Wendy Schultz / Jim Callahan | 2024-06-20 | 2024-07-08 | 80 | 65000 | Complete | Lumicore Tyler office, E.D. Tex. customers (Pinnacle Data Systems, Frontier Cloud Services, CrossPoint Networking)
Phase 2: Pleadings | Reply to counterclaims (non-infringement, invalidity, inequitable conduct, DJ) | Alan Ngo / Wendy Schultz | 2024-07-10 | 2024-07-22 | 40 | 35500 | Complete | Affirmative defenses: prosecution history estoppel, waiver
Phase 2: Pleadings | Proposed stipulated protective order (three-tier) | Wendy Schultz | 2024-08-10 | 2024-08-19 | 15 | 12375 | Complete | Confidential / AEO / Source Code
Phase 2: Pleadings | Docket control order review and compliance memo | Omar Siddiqui | 2024-08-12 | 2024-08-14 | 8 | 5800 | Complete | Scheduling Order entered D.E. 27, August 12, 2024
Phase 3: Fact discovery | First set of interrogatories to Lumicore (25) | Omar Siddiqui | 2024-08-15 | 2024-08-26 | 40 | 29000 | Complete
Phase 3: Fact discovery | First set of RFPs to Lumicore (85) | Omar Siddiqui / Wendy Schultz | 2024-08-15 | 2024-08-26 | 60 | 46500 | Complete
Phase 3: Fact discovery | ESI protocol negotiation and agreement | Wendy Schultz / Omar Siddiqui | 2024-08-20 | 2024-09-05 | 25 | 19375 | Complete | Crestline Technologies platform; agreed search-term methodology
Phase 3: Fact discovery | First set of RFAs to Lumicore (40) | Omar Siddiqui | 2024-09-10 | 2024-09-23 | 25 | 18125 | Complete
Phase 3: Fact discovery | Responses to Lumicore interrogatories and RFPs | Wendy Schultz / Omar Siddiqui | 2024-09-01 | 2024-09-30 | 120 | 93000 | Complete
Phase 3: Fact discovery | Third-party subpoena — Solara Optics records custodian | Omar Siddiqui | 2024-09-01 | 2024-09-09 | 10 | 7250 | Complete | Directed to Gregory Falk; '562 Patent records
Phase 3: Fact discovery | Document review and production (~182,000 docs, ~1.4M pages) | Full team + paralegals | 2024-08-15 | 2025-03-31 | 1200 | 600000 | In Progress | Crestline Technologies platform; search-term methodology; TAR 2.0 workflow
Phase 3: Fact discovery | Privilege log — initial (1,247 entries) | Paralegals / Omar Siddiqui | 2024-09-15 | 2024-10-31 | 150 | 80000 | Complete
Phase 3: Fact discovery | 30(b)(6) deposition notice — Lumicore (18 topics) | Wendy Schultz | 2024-09-25 | 2024-10-01 | 15 | 12375 | Complete
Phase 3: Fact discovery | Motion to compel opinion-of-counsel letters | Wendy Schultz / Alan Ngo | 2024-10-10 | 2024-10-21 | 50 | 41500 | Filed; Pending | Privilege waiver argument (Seagate/Halo); Lumicore's July 10, 2023 declination letter
Phase 3: Fact discovery | Deposition of Dr. Jian-Wei Huang (OWS CTO) | Alan Ngo (defense) | 2024-10-20 | 2024-11-05 | 40 | 37000 | Complete | Preparation and defense of client witness
Phase 3: Fact discovery | Second set of RFPs to Lumicore (30 supplemental) | Omar Siddiqui | 2024-10-25 | 2024-11-04 | 20 | 14500 | Complete | Source code repos, mask files, fabrication data
Phase 3: Fact discovery | Deposition of Dr. Sandra Michaud (Lumicore CTO) | Alan Ngo / Wendy Schultz | 2024-11-10 | 2024-11-19 | 50 | 44250 | Complete | Key admission: reviewed OWS Published App. No. 2018/0123456 during design phase
Phase 3: Fact discovery | Privilege log — supplemental (318 entries) | Paralegals / Omar Siddiqui | 2024-11-15 | 2024-12-15 | 40 | 22000 | Complete
Phase 3: Fact discovery | Deposition of Raymond Bautista (Lumicore GC) | Alan Ngo | 2024-11-25 | 2024-12-03 | 40 | 37000 | Complete | Limited; privilege issues re: opinion letters
Phase 3: Fact discovery | Deposition of Angela Reeves (FairPoint) | Wendy Schultz | 2024-12-05 | 2024-12-10 | 30 | 24750 | Complete | Confirmed licensing letters Jan 15, 2023 and May 15, 2023; described Apr 20, 2023 meeting
Phase 3: Fact discovery | Deposition of Kevin Ng (Benchmark) | Wendy Schultz | 2025-01-02 | 2025-01-07 | 25 | 20625 | Complete | Confirmed teardown methodology and chain of custody
Phase 3: Fact discovery | Third-party subpoena — Melissa Chen (Veridian Photonics) | Omar Siddiqui | 2025-01-15 | 2025-01-22 | 15 | 10875 | Issued | Former Lumicore engineer; OWS patent awareness evidence
Phase 3: Fact discovery | Meet-and-confer correspondence — Discovery disputes | Wendy Schultz / Omar Siddiqui | 2024-09-01 | 2025-03-31 | 60 | 46500 | Ongoing | Multiple letters re: ESI completeness, privilege log sufficiency, source code access
Phase 3: Fact discovery | Remaining fact depositions (~12) | Full team | 2025-01-15 | 2025-05-01 | 300 | 240000 | Planned | Fact discovery closes May 1, 2025
Phase 4: Claim Construction | Infringement contentions (P.R. 3-1) | Wendy Schultz / Omar Siddiqui | 2024-08-20 | 2024-09-16 | 120 | 93000 | Complete | Claim-by-claim, limitation-by-limitation; includes DOE contentions
Phase 4: Claim Construction | Analysis of Lumicore invalidity contentions (P.R. 3-3, 23 prior-art references) | Omar Siddiqui / Wendy Schultz | 2024-10-15 | 2024-11-07 | 100 | 77500 | Complete | Memos for each of 4 patents
Phase 4: Claim Construction | Joint claim construction statement (14 disputed terms) | Wendy Schultz | 2024-10-15 | 2024-10-28 | 30 | 24750 | Complete | 2 terms agreed; 12 remain in dispute
Phase 4: Claim Construction | Opening claim construction brief (50 pages) | Alan Ngo / Wendy Schultz / Omar Siddiqui | 2024-10-29 | 2024-11-15 | 200 | 170000 | Complete | All 12 disputed terms; intrinsic + extrinsic evidence
Phase 4: Claim Construction | Declarations of Dr. Ashford and Dr. Huang | Wendy Schultz / Omar Siddiqui | 2024-11-01 | 2024-11-15 | 40 | 31000 | Complete | POSITA definition: M.S./Ph.D. EE or photonics + 3 yrs silicon-photonic IC design
Phase 4: Claim Construction | Prosecution history estoppel analyses ('193 and '015 Patents) | Omar Siddiqui / Wendy Schultz | 2024-11-10 | 2024-12-01 | 50 | 38750 | Complete | Takahashi rejection ('193); Bergmann/Simonsen rejection ('015)
Phase 4: Claim Construction | Reply claim construction brief | Alan Ngo / Wendy Schultz | 2024-12-08 | 2024-12-20 | 80 | 69500 | Complete | Rebuts narrow constructions; supplemental Ashford declaration
Phase 4: Claim Construction | Joint claim construction chart — final | Wendy Schultz | 2025-01-10 | 2025-01-15 | 15 | 12375 | Complete
Phase 4: Claim Construction | Claim construction tutorial submission | Wendy Schultz / Omar Siddiqui | 2025-01-20 | 2025-02-28 | 60 | 46500 | In Progress | Due February 2025; diagrams/animations with Dr. Ashford
Phase 4: Claim Construction | Markman hearing slides and preparation | Alan Ngo / Wendy Schultz | 2025-02-01 | 2025-03-14 | 80 | 71500 | In Progress | 60+ slides; hearing March 14, 2025
Phase 4: Claim Construction | Means-plus-function and claim differentiation analysis | Omar Siddiqui | 2024-11-15 | 2024-12-05 | 35 | 25375 | Complete | Claims 7 and 12 of '015 Patent; §112(f) structure identification
Phase 5: Expert discovery | Coordinate and draft Dr. Ashford infringement report | Wendy Schultz / Omar Siddiqui | 2025-04-01 | 2025-06-15 | 200 | 155000 | Planned | Due June 15, 2025
Phase 5: Expert discovery | Coordinate and draft Dr. Ashford validity rebuttal report | Omar Siddiqui / Wendy Schultz | 2025-04-01 | 2025-06-15 | 150 | 116250 | Planned | Addresses 23 prior-art references
Phase 5: Expert discovery | Coordinate and draft Dr. Keating damages report | Alan Ngo / Wendy Schultz | 2025-04-01 | 2025-06-15 | 180 | 153000 | Planned | Three theories: lost profits $128.9M, royalty $37.5M, willful enhancement
Phase 5: Expert discovery | Coordinate and draft Gregory Falk industry report | Omar Siddiqui | 2025-04-15 | 2025-06-15 | 60 | 43500 | Planned | Silicon-photonics market, competitive landscape, secondary considerations
Phase 5: Expert discovery | Review and analyze defendant expert reports | Alan Ngo / Wendy Schultz / Omar Siddiqui | 2025-07-01 | 2025-07-15 | 80 | 65500 | Planned | Dr. Sundaram (validity) and Dr. Volkov (damages) rebuttal analysis
Phase 5: Expert discovery | Prepare experts for depositions | Alan Ngo / Wendy Schultz | 2025-07-01 | 2025-08-15 | 120 | 105000 | Planned | Defense of Ashford, Keating, Falk depositions
Phase 5: Expert discovery | Depose Dr. Sundaram and Dr. Volkov | Alan Ngo / Wendy Schultz | 2025-07-15 | 2025-08-15 | 80 | 71250 | Planned | Expert discovery closes August 15, 2025
Phase 6: Dispositive Motions | Partial SJ — infringement of '562 Patent | Alan Ngo / Wendy Schultz | 2025-08-15 | 2025-09-15 | 120 | 105000 | Planned | Claims 1, 4, 6; Benchmark data + Michaud admissions
Phase 6: Dispositive Motions | Partial SJ — validity of '015 Patent | Wendy Schultz / Omar Siddiqui | 2025-08-15 | 2025-09-15 | 100 | 77500 | Planned | Prior-conception defense lacks corroboration
Phase 6: Dispositive Motions | Opposition to anticipated defense SJ on DOE | Wendy Schultz / Omar Siddiqui | 2025-09-15 | 2025-10-15 | 80 | 62000 | Planned | Festo tangential-relation exception
Phase 6: Dispositive Motions | Opposition to anticipated defense SJ on EMVR | Alan Ngo / Wendy Schultz | 2025-09-15 | 2025-10-15 | 80 | 69500 | Planned | Patented features drive demand for accused modules
Phase 6: Dispositive Motions | Daubert motions against Dr. Sundaram and Dr. Volkov | Alan Ngo / Wendy Schultz / Omar Siddiqui | 2025-10-01 | 2025-11-01 | 120 | 99000 | Planned | Sundaram: uncorroborated docs; Volkov: disaggregated base, non-comparable licenses
Phase 6: Dispositive Motions | Opposition to anticipated Daubert on Dr. Keating | Alan Ngo / Wendy Schultz | 2025-10-15 | 2025-11-15 | 60 | 52500 | Planned
Phase 7: Trial Prep | Trial strategy memorandum | Alan Ngo / Marcus Delgado | 2025-10-01 | 2025-10-31 | 40 | 37000 | Planned | Themes, witness order, exhibit strategy, verdict form
Phase 7: Trial Prep | Proposed jury instructions | Wendy Schultz / Omar Siddiqui | 2025-11-01 | 2025-12-15 | 60 | 46500 | Planned | Claim construction, infringement (literal + DOE), validity, willfulness, damages
Phase 7: Trial Prep | Proposed verdict form | Wendy Schultz | 2025-11-15 | 2025-12-15 | 20 | 16500 | Planned | Special verdict: per patent, per claim, per product; willfulness, validity, damages
Phase 7: Trial Prep | Witness list (13+ witnesses) | Omar Siddiqui | 2025-11-15 | 2025-12-15 | 10 | 7250 | Planned | Live: Huang, Petrov, Tanaka, Reeves, Ng, Ashford, Keating, Falk, Chen, Whitfield; adverse: Michaud, Bautista, Dalmqvist
Phase 7: Trial Prep | Exhibit list (~340 exhibits, P-001 to P-340) | Omar Siddiqui / Paralegals | 2025-11-15 | 2025-12-15 | 80 | 42500 | Planned | 9 categories: patents, teardowns, design docs, licensing, financials, licenses, depositions, demonstratives, miscellaneous
Phase 7: Trial Prep | Deposition designation charts | Omar Siddiqui / Paralegals | 2025-11-15 | 2025-12-31 | 50 | 27500 | Planned | All 17 depositions; counter-designations expected
Phase 7: Trial Prep | Trial demonstratives — infringement and damages modules | Wendy Schultz / Dr. Ashford / Dr. Keating | 2025-12-01 | 2026-01-15 | 100 | 82500 | Planned | Annotated teardowns, 3D models, revenue timelines, GP factor summaries
Phase 7: Trial Prep | Motions in limine | Alan Ngo / Wendy Schultz | 2025-12-15 | 2026-01-10 | 50 | 44250 | Planned | Exclude PE-sponsor evidence, patent-troll references, undisclosed opinions/prior art
Phase 7: Trial Prep | Pre-trial conference statement | Wendy Schultz | 2025-12-15 | 2026-01-05 | 20 | 16500 | Planned | OWS requests 4 of 5 allocated trial days
Phase 7: Trial Prep | Voir dire questions | Alan Ngo | 2026-01-01 | 2026-01-15 | 10 | 9250 | Planned | Patent familiarity, tech industry, IP attitudes
Phase 7: Trial Prep | Opening statement outline | Alan Ngo / Marcus Delgado | 2026-01-01 | 2026-01-25 | 30 | 27750 | Planned | Five acts: innovation, copying, willfulness, technology, remedy ($210M)
Phase 7: Trial Prep | Witness preparation sessions | Alan Ngo / Wendy Schultz | 2026-01-10 | 2026-01-31 | 200 | 175000 | Planned | All live witnesses
Phase 8: Trial | Trial — 7 to 10 days | Full trial team | 2026-02-02 | 2026-02-13 | 500 | 400000 | Planned | Jury trial before Judge Gilstrap, E.D. Tex.
Phase 8: Trial | Post-trial motions (JMOL, new trial if needed) | Alan Ngo / Wendy Schultz | 2026-02-14 | 2026-03-15 | 80 | 69500 | Planned | Contingency