1015-00003 · Calloway-Briggs Renewables Inc · Transaction Documents
equipment-supply-agreement-execution.docx DOCUMENT Finance & Banking
10 / 12 ← → ✕
Contract analysis Extract to table

EQUIPMENT SUPPLY AGREEMENT

Execution Version

December 1, 2022

between

LONE STAR STORAGE I, LLC a Texas limited liability company ("Buyer")

and

HARMON-DIETRICH ENERGY SOLUTIONS, LLC a Delaware limited liability company ("Supplier")

Lone Star Battery Storage Project 50 MW / 200 MWh Battery Energy Storage System Ector County, Texas

RECITALS

A. Buyer is a Texas limited liability company and single-purpose project company formed to develop, own, and operate a 50 MW / 200 MWh lithium iron phosphate ("LFP") battery energy storage system (the "Project") located on an approximately 15-acre parcel within Survey No. 42, Block 42, T-1-S, T&P RR Co. Survey, Ector County, Texas (nearest postal address: 4800 West University Boulevard, Odessa, TX 79764) (the "Project Site").

B. Buyer is a wholly owned subsidiary of Calloway-Briggs Renewables Inc., a Texas corporation ("CBR"), which serves as the sole member and manager of Buyer and manages and operates Buyer in connection with the development, construction, and operation of the Project.

C. Buyer has entered into an Engineering, Procurement and Construction Agreement dated as of December 1, 2022 with Meridian Power Construction, Inc., a Texas corporation (the "EPC Contractor"), for the design, engineering, procurement, construction, testing, and commissioning of the Project (the "EPC Agreement"). The equipment to be supplied under this Agreement constitutes a subset of the scope of the EPC Agreement and is included within the EPC Contract Price on a pass-through basis; however, the parties desire to establish a direct contractual relationship between Buyer and Supplier for purposes of warranty privity, direct supply obligations, and the security and collateral assignment requirements of Buyer's lender.

D. Supplier is a Delaware limited liability company engaged in the manufacture and integration of lithium iron phosphate battery modules and power conversion systems for grid-scale energy storage applications, with a North American manufacturing facility located in Pflugerville, Texas.

E. Buyer desires to purchase, and Supplier desires to supply, the Equipment (as defined herein) for use in the Project, on the terms and conditions set forth in this Agreement.

F. The Project is being financed in part by a $26,000,000 construction-to-term loan facility (the "Credit Agreement") provided by Brazos River National Bank, N.A. (the "Lender"), and Buyer's rights under this Agreement will be collaterally assigned to Lender as security for such financing pursuant to the Collateral Assignment of Project Contracts dated as of December 1, 2022.

NOW, THEREFORE, in consideration of the mutual covenants and agreements hereinafter set forth, and for other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the parties agree as follows:

ARTICLE 1 — DEFINITIONS AND INTERPRETATION

Section 1.1 — Definitions

As used in this Agreement, the following terms have the meanings set forth below:

"Acceptance Test" means the test procedures set forth in Exhibit D to be conducted following installation and commissioning of the Equipment at the Project Site to confirm that the Equipment meets the Performance Specifications.

"Agreement" means this Equipment Supply Agreement, including all Exhibits, Schedules, amendments, and Change Orders hereto, as the same may be amended, supplemented, or modified from time to time in accordance with the terms hereof.

"Battery Management System" or "BMS" means the electronic system, including all associated hardware, software, firmware, communication interfaces, and controllers, supplied by Supplier to monitor and manage battery module performance, state of charge, state of health, cell balancing, temperature, current, voltage, and safety functions for all Battery Modules within the Equipment.

"Battery Modules" means the LFP battery cells, modules, and racks comprising the energy storage portion of the Equipment, specifically Supplier's proprietary Model HD-LFP-200E, including all internal wiring, busbars, cell-level fuses, and internal protective devices.

"Buyer" means Lone Star Storage I, LLC, a Texas limited liability company, EIN 88-1623504, and its successors and permitted assigns.

"Buyer's Representative" means the individual designated by Buyer pursuant to Section 3.2 to act as Buyer's authorized representative under this Agreement.

"Capacity Warranty" means the warranty set forth in Section 10.2 with respect to the capacity retention of the Battery Modules over the Capacity Warranty Period.

"Capacity Warranty Period" means the period of ten (10) years from the date of Provisional Acceptance.

"CBR" means Calloway-Briggs Renewables Inc., a Texas corporation, the sole member and manager of Buyer.

"Change Order" means a written amendment to this Agreement modifying the scope of the Equipment, the Contract Price, the Delivery Schedule, the Performance Specifications, or other terms, executed by both Parties in accordance with Article 8 and substantially in the form attached as Exhibit F.

"Commercial Operation Date" or "COD" means August 15, 2023 (expected), or such later date as actual commercial operation of the Project is achieved; the Guaranteed COD under the EPC Agreement is September 1, 2023.

"Confidential Information" has the meaning set forth in Section 16.1.

"Container Enclosures" means the weatherproof, climate-controlled, pre-fabricated container units designed and manufactured by Supplier for housing the Battery Modules and associated electrical components, inclusive of structural framing, access doors, cable entry points, ventilation interfaces, and fire suppression integration points.

"Contract Price" means Eighteen Million Four Hundred Thousand Dollars ($18,400,000), as may be adjusted in accordance with Article 8.

"Credit Agreement" means the $26,000,000 construction-to-term loan facility agreement, dated as of December 1, 2022, between Buyer and Lender.

"Defect" means any failure of the Equipment or any component thereof to conform to the Performance Specifications, the Documentation, or the Warranties, in each case attributable to defective design, defective materials, or defective workmanship on the part of Supplier or its Subcontractors.

"Defect Warranty" means the warranty set forth in Section 10.3.

"Defect Warranty Period" means the period of five (5) years from the date of Provisional Acceptance of the applicable Equipment, subject to extension as provided in Section 10.3.

"Delivery Date" means the date on which any Shipment of Equipment is delivered to the Delivery Point in accordance with Article 5.

"Delivery Point" means the Project Site at 4800 West University Boulevard, Odessa, TX 79764, Ector County, Texas, FOB destination.

"Delivery Schedule" means the schedule of four (4) Shipments set forth in Exhibit C, as may be modified by Change Order or extended by Excusable Delay.

"Documentation" means all manuals, drawings, design specifications, installation guides, commissioning procedures, maintenance instructions, recommended operating parameters, BMS software documentation, training materials, and other technical documentation to be provided by Supplier pursuant to Sections 2.2 and 4.4.

"EPC Agreement" means the Engineering, Procurement and Construction Agreement dated December 1, 2022 between Buyer and Meridian Power Construction, Inc., as the same may be amended, supplemented, or modified from time to time.

"EPC Contractor" means Meridian Power Construction, Inc., a Texas corporation.

"Equipment" means, collectively, the Battery Modules, Power Conversion Systems, Battery Management System, Thermal Management System, Container Enclosures, and all associated components, materials, cables, connectors, switchgear interface equipment, communication hardware, sensors, monitoring software, firmware, accessories, and Documentation to be supplied by Supplier under this Agreement, as more particularly described in Exhibit A.

"Excusable Delay" has the meaning set forth in Section 6.3.

"Final Acceptance" has the meaning set forth in Section 7.3.

"Force Majeure Event" has the meaning set forth in Section 14.1.

"HVAC" means the heating, ventilation, and air conditioning systems constituting the Thermal Management System.

"Intellectual Property" has the meaning set forth in Section 11.1.

"Lender" means Brazos River National Bank, N.A., a national banking association, and its successors and assigns.

"Lender's Engineer" means Norgate Technical Advisors, Inc., or such other independent engineer retained by Lender in connection with the Credit Agreement and the Project.

"Liquidated Damages" or "LDs" means the delay liquidated damages payable by Supplier pursuant to Section 6.2.

"Loss" means any and all losses, liabilities, damages, claims, costs, and expenses (including reasonable attorneys' fees, consultant fees, and court costs).

"Nameplate Capacity" means 50 MW of power capacity and 200 MWh of energy capacity, representing the rated capacity of the Equipment at the time of Provisional Acceptance.

"Party" means Buyer or Supplier, individually, and "Parties" means both Buyer and Supplier, collectively.

"Performance Specifications" means the technical performance specifications for the Equipment set forth in Exhibit B, as may be modified by Change Order.

"Power Conversion Systems" or "PCS" means ten (10) 5 MW bidirectional inverters (total aggregate capacity of 50 MW) supplied by Supplier for AC/DC conversion, rated for interconnection at 34.5 kV at the PCS output terminals.

"Project" means the Lone Star Battery Storage Project, a 50 MW / 200 MWh LFP battery energy storage system located in Ector County, Texas, to be developed, owned, and operated by Buyer.

"Project Site" means the approximately 15-acre parcel located at 4800 West University Boulevard, Odessa, TX 79764, Ector County, Texas, being a portion of Survey No. 42, Block 42, T-1-S, T&P RR Co. Survey.

"Provisional Acceptance" has the meaning set forth in Section 7.2.

"Punch List" means a list of minor items identified at the time of Provisional Acceptance that do not materially affect the operation, safety, or performance of the Equipment.

"Scheduled Delivery Date" means, with respect to each Shipment, the date specified in the Delivery Schedule (Exhibit C) by which such Shipment is required to be delivered to the Delivery Point, as may be extended by Change Order or Excusable Delay.

"Shipment" means each of the four (4) deliveries of Equipment as described in the Delivery Schedule attached as Exhibit C.

"Spare Parts" means the recommended and required spare parts as listed in Exhibit E.

"Subcontractor" means any person or entity engaged by Supplier to perform any part of Supplier's obligations under this Agreement, including material suppliers, component manufacturers, and service providers.

"Supplier" means Harmon-Dietrich Energy Solutions, LLC, a Delaware limited liability company, and its successors and permitted assigns.

"Supplier's Representative" means the individual designated by Supplier pursuant to Section 3.3 to act as Supplier's authorized representative under this Agreement.

"Thermal Management System" means the HVAC equipment and controls supplied by Supplier for climate regulation within the Container Enclosures, including compressors, evaporators, condensers, fans, ductwork, sensors, and associated control systems, designed for continuous operation in ambient temperatures up to 115°F (46°C).

"Warranty" means, collectively, the Capacity Warranty and the Defect Warranty as set forth in Article 10.

Section 1.2 — Interpretation

The following rules of construction shall apply to this Agreement unless the context otherwise requires:

(a) The headings and titles of the Articles, Sections, and Exhibits of this Agreement are inserted for convenience of reference only and shall not affect the meaning or interpretation of any provision hereof.

(b) Words in the singular include the plural and vice versa; words in one gender include the other genders; and the use of the word "including" or "includes" shall mean "including without limitation" or "includes without limitation," as applicable.

(c) References to "Articles," "Sections," "Exhibits," and "Schedules" are references to Articles, Sections, Exhibits, and Schedules of or to this Agreement, unless otherwise specified.

(d) All monetary amounts referenced in this Agreement are expressed in, and shall be payable in, United States Dollars.

(e) References to "days" mean calendar days unless otherwise expressly stated as "business days." A "business day" means any day other than a Saturday, Sunday, or a day on which commercial banks in Houston, Texas are authorized or required by law to be closed.

(f) References to any law, statute, regulation, or code include all amendments, re-enactments, replacements, and successor statutes or regulations thereto.

(g) The words "herein," "hereof," "hereunder," "hereto," and words of similar import refer to this Agreement as a whole, including all Exhibits and Schedules, and not to any particular Article, Section, or other subdivision hereof.

(h) References to any agreement, contract, or document mean such agreement, contract, or document as amended, modified, supplemented, or restated from time to time in accordance with its terms.

(i) The Parties have participated jointly in the negotiation and drafting of this Agreement, and no rule of construction based on authorship shall apply.

Section 1.3 — Order of Precedence

In the event of any conflict, inconsistency, or ambiguity among or between the provisions of this Agreement, the following order of precedence shall apply, with the document listed first taking priority:

(1) Change Orders (in reverse chronological order, with the most recent Change Order taking priority);

(2) The body of this Agreement (Articles 1 through 22);

(3) Exhibit B (Performance Specifications);

(4) Exhibit A (Equipment Description and Scope);

(5) All other Exhibits and Schedules (in alphabetical order by Exhibit letter).

The foregoing order of precedence shall not be construed to diminish Supplier's obligation to furnish Equipment that meets all Performance Specifications and complies with all provisions of this Agreement. Where a provision in a lower-priority document imposes a more stringent requirement than a higher-priority document, the more stringent requirement shall apply unless the higher-priority document expressly states that it supersedes the lower-priority provision.

Section 1.4 — Exhibits and Schedules

The following Exhibits and Schedules are attached to and incorporated into this Agreement by this reference:

• Exhibit A — Equipment Description and Scope

• Exhibit B — Performance Specifications

• Exhibit C — Delivery Schedule

• Exhibit D — Acceptance Test Procedures

• Exhibit E — Spare Parts List

• Exhibit F — Form of Change Order

• Exhibit G — Insurance Requirements

• Exhibit H — Form of Lien Waiver

ARTICLE 2 — SCOPE OF SUPPLY

Section 2.1 — Equipment Scope

Supplier shall design, manufacture, factory-test, package, transport, and deliver to the Project Site the following Equipment, all as more particularly described in Exhibit A:

(a) Battery Modules. Fifty megawatts / Two hundred megawatt-hours (50 MW / 200 MWh) of four-hour duration lithium iron phosphate (LFP) battery modules, Supplier's proprietary Model HD-LFP-200E, including all cells, modules, racks, internal wiring, busbars, cell-level fuses, and internal protective devices, configured for a system with a minimum round-trip efficiency of eighty-seven percent (87%). The Battery Modules shall be designed for bidirectional charge and discharge operation and shall be optimized for the ancillary services and energy arbitrage applications contemplated by the Project within the Electric Reliability Council of Texas ("ERCOT") market.

(b) Power Conversion Systems. Ten (10) bidirectional 5 MW PCS inverters (total aggregate capacity of 50 MW) for AC/DC conversion, rated for interconnection at 34.5 kV at the PCS output terminals, with grid-forming and grid-following capability as further specified in Exhibit B. The PCS units shall be designed for integration with the on-site step-up transformer (34.5 kV to 138 kV), which is to be provided by the EPC Contractor under the EPC Agreement.

(c) Battery Management System. A complete Battery Management System consisting of all hardware controllers, communication architecture, and software functionality necessary for monitoring, control, protection, state-of-charge management, state-of-health assessment, cell balancing, diagnostics, alarm management, data logging, and SCADA integration for all Battery Modules within the Equipment.

(d) Thermal Management System. Integrated HVAC systems for each Container Enclosure, designed for continuous operation in Ector County, Texas ambient conditions, including extreme heat conditions of up to one hundred fifteen degrees Fahrenheit (115°F / 46°C), and capable of maintaining Battery Module operating temperatures within the range specified in the Performance Specifications.

(e) Container Enclosures. Pre-fabricated, weatherproof container units housing Battery Modules, PCS inverters, BMS hardware, and HVAC systems, designed and constructed for outdoor installation at the Project Site, including structural framing, access doors, cable entry points, ventilation interfaces, and fire suppression integration points.

(f) Associated Components. All associated cables, connectors, DC switchgear, switchgear interface equipment, communication hardware, sensors, monitoring terminals, monitoring software, firmware, and accessories as specified in Exhibit A, together with all items reasonably necessary for the Equipment to function as an integrated system in accordance with the Performance Specifications.

Section 2.2 — Documentation

Supplier shall deliver to Buyer all Documentation relating to the Equipment, including:

(a) Factory acceptance test reports for each Shipment;

(b) Installation manuals and guides providing detailed instructions for the installation, interconnection, and integration of all Equipment components;

(c) Operation and maintenance manuals, including recommended maintenance schedules, inspection protocols, and troubleshooting guides;

(d) As-built drawings reflecting the final, as-manufactured configuration of all Equipment;

(e) BMS software documentation, including user manuals, configuration guides, communication protocol specifications, and firmware revision histories;

(f) Training materials sufficient to enable Buyer's operations and maintenance personnel to operate the Equipment safely and in accordance with Supplier's recommended practices; and

(g) All applicable certificates of compliance, material certifications, and test results for Equipment components subject to industry standards referenced in Section 4.2.

Section 2.3 — Exclusions

The following items and activities are expressly excluded from Supplier's scope of supply under this Agreement and are the responsibility of Buyer or the EPC Contractor under the EPC Agreement:

(a) All civil and structural works, including site preparation, grading, drainage, fencing, and access road construction;

(b) Equipment foundations, including concrete pads and structural supports for Container Enclosures;

(c) The step-up transformer (34.5 kV to 138 kV);

(d) The gen-tie line, consisting of approximately 1.2 miles of 138 kV overhead transmission line from the Project Site to the Western Permian 138 kV Substation;

(e) The Project switchyard and associated protection and metering equipment;

(f) Revenue metering equipment, except to the extent such metering is integral to the PCS units;

(g) Installation and erection labor at the Project Site, except for Supplier's supervisory and commissioning support personnel as provided in Section 2.4;

(h) Network upgrades at the Western Permian 138 kV Substation required by ERCOT or the applicable transmission service provider;

(i) Site security, temporary facilities, and construction utilities; and

(j) All permits and approvals related to the Project Site, construction, and operation of the Project.

Section 2.4 — Commissioning Support

Supplier shall provide qualified technical personnel on-site at the Project Site during the installation and commissioning phases of the Project to supervise Equipment integration, BMS configuration, Acceptance Testing, and initial start-up of the Equipment, at no additional cost to Buyer. Supplier's commissioning support personnel shall be available for a period of up to sixty (60) days from the date of delivery of the final Shipment (Shipment 4). Supplier's commissioning support obligations include:

(a) Technical supervision and direction of Equipment interconnection, integration, and energization activities performed by the EPC Contractor;

(b) Configuration, calibration, and optimization of the BMS, including communication interface setup with Buyer's SCADA system;

(c) Supervision and support of all Acceptance Tests in accordance with Exhibit D;

(d) Coordination with the EPC Contractor's commissioning team for integrated system testing; and

(e) Training of Buyer's designated operations and maintenance personnel (minimum three (3) days of on-site training).

Should Buyer require commissioning support beyond the sixty (60) day period, Supplier shall provide additional support at Supplier's then-current standard service rates, provided that Supplier shall not charge for additional support necessitated by Defects in the Equipment.

Section 2.5 — Spare Parts

Supplier shall provide to Buyer a list of recommended and required spare parts for the Equipment, as set forth in Exhibit E, together with unit pricing for each spare part. Buyer shall have the option, but not the obligation, to purchase the initial recommended spare parts inventory from Supplier at the unit prices specified in Exhibit E. The unit prices set forth in Exhibit E shall remain valid and available to Buyer for a period of ten (10) years from the date of this Agreement, subject to adjustment only for documented changes in raw material costs exceeding ten percent (10%) in any single calendar year, in which case the adjustment shall be limited to the actual documented increase in raw material costs.

Section 2.6 — Relationship with EPC Agreement

The Equipment supplied hereunder is included within the EPC Contract Price of Thirty-One Million Two Hundred Thousand Dollars ($31,200,000) under the EPC Agreement on a pass-through basis, with the Contract Price under this Agreement constituting a component of the EPC Contract Price. This Agreement is intended to establish a direct contractual relationship between Buyer and Supplier for the purpose of providing Buyer with direct warranty privity, direct performance obligations by Supplier, and the security and collateral assignment rights required by Lender under the Credit Agreement. In the event of any conflict between this Agreement and the EPC Agreement with respect to Supplier's obligations regarding the design, manufacture, testing, delivery, or warranty of the Equipment, this Agreement shall govern as between Buyer and Supplier. Nothing in this Agreement is intended to modify or diminish the obligations of the EPC Contractor to Buyer under the EPC Agreement.

ARTICLE 3 — REPRESENTATIVES AND COORDINATION

Section 3.1 — Cooperation

The Parties shall cooperate in good faith with each other, with the EPC Contractor (Meridian Power Construction, Inc.), and with the Lender's Engineer (Norgate Technical Advisors, Inc., attention: Dr. Phillip S. Reardon, P.E.) in connection with all matters relating to the delivery, installation, testing, and commissioning of the Equipment. Such cooperation shall include, without limitation, timely sharing of technical information, coordination of schedules, prompt responses to requests for information, and reasonable accommodation of site access and inspection requirements.

Section 3.2 — Buyer's Representative

Buyer shall designate an authorized representative in writing within ten (10) business days after execution of this Agreement. Buyer's Representative shall have authority to act on Buyer's behalf with respect to day-to-day administration of this Agreement, including approval of Documentation, coordination of delivery logistics, participation in factory and site acceptance testing, and issuance of certificates of Provisional Acceptance and Final Acceptance. All communications and notices regarding technical matters under this Agreement shall be directed to Buyer's Representative. The designation or replacement of Buyer's Representative shall be communicated to Supplier in writing and shall not require a Change Order.

Section 3.3 — Supplier's Representative

Supplier shall designate an authorized representative with full authority to act on Supplier's behalf in day-to-day matters relating to this Agreement. Supplier's Representative shall serve as the primary point of contact for all technical and logistical communications and shall have authority to make day-to-day decisions regarding Supplier's performance, subject to any limitations communicated by Supplier to Buyer in writing. Ingrid N. Harmon, Chief Executive Officer of Harmon-Dietrich Energy Solutions, LLC, shall serve as Supplier's executive contact for escalation of matters that cannot be resolved at the Representative level. The designation or replacement of Supplier's Representative shall be communicated to Buyer in writing and shall not require a Change Order.

Section 3.4 — Coordination with EPC Contractor

Supplier shall coordinate delivery logistics, on-site receiving requirements, unloading procedures, storage and staging, and commissioning activities with Meridian Power Construction, Inc. (EPC Contractor). Supplier shall participate in project coordination meetings as reasonably requested by Buyer or the EPC Contractor. Supplier acknowledges that the EPC Contractor is responsible for installation and erection of the Equipment and agrees to cooperate with the EPC Contractor to facilitate efficient and timely installation, including by providing technical guidance and supervision during installation activities as part of the commissioning support described in Section 2.4.

Section 3.5 — Lender's Engineer Access

Supplier shall provide Norgate Technical Advisors, Inc. (Lender's Engineer) and its authorized representatives with reasonable access to Supplier's manufacturing facility in Pflugerville, Texas, and to factory test data, production records, and quality assurance documentation, for purposes of Lender due diligence, ongoing construction monitoring, and independent assessment of Equipment quality and compliance with the Performance Specifications. Such access shall be provided during normal business hours upon not less than five (5) business days' prior written notice from Buyer or Lender's Engineer. Supplier shall cooperate with Lender's Engineer in responding to technical inquiries and providing requested information in a timely manner. The Lender's Engineer shall comply with Supplier's reasonable safety, security, and confidentiality requirements while on site at the manufacturing facility.

ARTICLE 4 — DESIGN AND MANUFACTURING

Section 4.1 — Design Responsibility

Supplier has sole responsibility for the design and engineering of the Equipment to meet the Performance Specifications set forth in Exhibit B. Supplier warrants that the Equipment design is fit for its intended purpose as a grid-scale battery energy storage system operating within the ERCOT market, located in Ector County, Texas, and subject to the ambient environmental conditions at the Project Site, including extreme heat conditions of up to 115°F (46°C). Supplier shall ensure that the design of the Equipment is compatible with the balance-of-plant systems to be provided by the EPC Contractor, including the step-up transformer and switchyard equipment, based on interface specifications to be exchanged between Supplier and the EPC Contractor within thirty (30) days of execution of this Agreement. Any design changes required after the exchange of interface specifications shall be subject to the Change Order process set forth in Article 8.

Section 4.2 — Manufacturing Standards

All Equipment shall be manufactured in accordance with applicable industry standards, including the following:

(a) UL 9540 — Standard for Energy Storage Systems and Equipment;

(b) UL 9540A — Test Method for Evaluating Thermal Runaway Fire Propagation in Battery Energy Storage Systems;

(c) NFPA 855 — Standard for the Installation of Stationary Energy Storage Systems;

(d) IEEE 1547 — Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces;

(e) IEEE 2800 — Standard for Interconnection and Interoperability of Inverter-Based Resources Interconnecting with Associated Transmission Electric Power Systems;

(f) NEC Article 706 — Energy Storage Systems;

(g) IEC 62619 — Secondary lithium cells and batteries for industrial applications — Safety requirements; and

(h) All other applicable federal, state, and local codes and standards, including those required by the Authority Having Jurisdiction for Ector County, Texas.

Supplier shall maintain current certifications and listings for all Equipment components requiring third-party certification and shall provide copies of all certificates and listing reports to Buyer as part of the Documentation.

Section 4.3 — Factory Acceptance Testing

Supplier shall conduct factory acceptance tests ("FATs") at its manufacturing facility in Pflugerville, Texas, prior to shipment of each Shipment. Factory acceptance tests shall include, at a minimum:

(a) Cell and module capacity testing to verify nameplate energy capacity and voltage specifications;

(b) PCS inverter efficiency testing to verify rated efficiency at partial and full load conditions;

(c) BMS functional testing to verify monitoring, protection, communication, and control functions;

(d) Thermal Management System performance testing to verify cooling and heating capacity under simulated load conditions; and

(e) Integrated system functional testing to verify interoperability of Battery Modules, PCS, BMS, and Thermal Management System within each Container Enclosure.

Buyer and Buyer's representatives, including Norgate Technical Advisors, Inc. (Lender's Engineer), shall have the right to witness factory acceptance tests upon at least ten (10) business days' prior written notice to Supplier. Supplier shall provide FAT procedures to Buyer for review at least fifteen (15) business days prior to the scheduled FAT date. Supplier shall promptly provide FAT reports to Buyer following completion of each FAT.

Section 4.4 — Documentation Deliverables

Supplier shall deliver Documentation in accordance with the following schedule:

(a) Preliminary Design Documentation: Within thirty (30) days of execution of this Agreement, Supplier shall deliver preliminary design documentation, including system architecture drawings, single-line diagrams, equipment layout drawings, interface specifications, and BMS functional descriptions;

(b) Final Design Documentation: At least thirty (30) days prior to the Scheduled Delivery Date for the first Shipment, Supplier shall deliver final design documentation, including detailed engineering drawings, wiring diagrams, BMS configuration specifications, and installation instructions; and

(c) As-Built Documentation: Within sixty (60) days after Final Acceptance, Supplier shall deliver complete as-built documentation reflecting the final, as-manufactured and as-installed configuration of all Equipment, including any modifications made during installation and commissioning.

All Documentation shall be delivered in electronic format (PDF and, where applicable, native CAD or engineering software format) and in two (2) complete sets of hard copies.

Section 4.5 — Quality Assurance / Quality Control

Supplier shall maintain a documented quality assurance and quality control ("QA/QC") program consistent with ISO 9001:2015 (or equivalent) throughout the design, manufacturing, testing, and delivery phases. Supplier shall make its QA/QC program documentation available to Buyer upon request. Buyer shall have audit rights to inspect Supplier's manufacturing processes, quality records, and testing activities at Supplier's Pflugerville, Texas facility upon reasonable advance notice (not less than five (5) business days). Supplier shall promptly address any non-conformances identified during such audits and shall maintain records of corrective and preventive actions taken.

ARTICLE 5 — DELIVERY

Section 5.1 — Delivery Terms

All Equipment shall be delivered FOB Project Site (4800 West University Boulevard, Odessa, TX 79764, Ector County, Texas). Supplier shall be responsible for all costs and risks of transportation from Supplier's manufacturing facility in Pflugerville, Texas to the Delivery Point, including freight, insurance during transit, and any permits required for overland transport. Risk of loss of, and title to, the Equipment shall pass from Supplier to Buyer upon delivery of the Equipment to the Project Site and completion of the receiving inspection described in Section 5.3, provided that passage of risk and title shall not relieve Supplier of its warranty, indemnification, or other obligations under this Agreement. In the event of damage to Equipment during transit, Supplier shall, at its sole cost and expense, promptly repair or replace the damaged Equipment.

Section 5.2 — Delivery Schedule

Equipment shall be delivered to the Delivery Point in four (4) Shipments in accordance with the Delivery Schedule set forth in Exhibit C, as summarized below:

(a) Shipment 1: On or before March 15, 2023 — Battery Modules (first tranche) and Container Enclosures (first tranche).

(b) Shipment 2: On or before April 15, 2023 — Battery Modules (second tranche) and PCS inverters (five (5) of ten (10) units).

(c) Shipment 3: On or before May 15, 2023 — Battery Modules (third tranche), PCS inverters (remaining five (5) of ten (10) units), and BMS hardware.

(d) Shipment 4: On or before June 1, 2023 — Remaining Battery Modules, Container Enclosures, Thermal Management Systems (HVAC), and all remaining components and accessories.

The Delivery Schedule has been developed in coordination with the EPC Contractor's construction schedule to enable achievement of the Guaranteed COD of September 1, 2023 under the EPC Agreement. Supplier acknowledges that the Delivery Schedule is critical to the overall Project schedule and that delays in any Shipment may cause cascading delays in installation, testing, commissioning, and achievement of COD.

Section 5.3 — Receiving Inspection

Upon delivery of each Shipment to the Delivery Point, Buyer (or the EPC Contractor on Buyer's behalf) shall conduct a visual and documentary receiving inspection within five (5) business days of delivery. The receiving inspection shall include visual examination of Equipment for external damage, verification of Equipment quantities and components against the packing list and bill of lading, and review of applicable factory test reports and certificates. Buyer shall notify Supplier in writing of any apparent damage, shortage, or non-conformity identified during the receiving inspection promptly upon discovery. Acceptance of delivery and completion of receiving inspection shall not constitute a waiver of Buyer's right to assert claims for latent Defects or non-conformities not reasonably discoverable during a visual inspection.

Section 5.4 — Packaging and Shipping

Supplier shall be responsible for all packaging, crating, and shipping of the Equipment in a manner suitable for overland transport to the Project Site, taking into account the nature of the Equipment, road conditions, and ambient environmental conditions during transit. All packaging shall provide adequate protection against damage from handling, vibration, moisture, and temperature extremes. All shipments shall be clearly marked with the following identification:

(a) Project name: "Lone Star Battery Storage Project";

(b) Shipment number (1, 2, 3, or 4);

(c) Contents manifest identifying each container, crate, or package; and

(d) Handling instructions, including orientation indicators and hazardous materials markings as required by applicable Department of Transportation regulations.

Section 5.5 — Shipping Notices