CONFIDENTIAL — ATTORNEY WORK PRODUCT / PRIVILEGED

CROSS-EXAMINATION OUTLINE

DEPOSITION OF MARCUS HENLEY

Vice President of Field Operations (Northeast Division)

Meridian Infrastructure Partners LLC

CASE CAPTION

SUPREME COURT OF THE STATE OF NEW YORK COUNTY OF NEW YORK — COMMERCIAL DIVISION

MERIDIAN INFRASTRUCTURE PARTNERS LLC,

Plaintiff,

v.

NORTHGATE FIBER AMERICAS INC.,

Defendant-Counterclaimant.

Index No. 654321/2024 Part 49 (Hon. Eleanor M. Ricci)

Deposition Dates: December 3–4, 2024

Location: Offices of Calderwood & Harkness LLP, 425 Park Avenue, 33rd Floor, New York, NY 10022 (or as otherwise agreed with Hargrove, Deluca & Stein LLP)

Prepared by: Jeffrey Park, Lead Associate

Reviewed by: Linda Osei, Responsible Partner

Date Prepared: November 25, 2024

C&H Matter No.: 1022-00005

Classification: Privileged and Confidential — Attorney Work Product. This document was prepared in anticipation of litigation and is protected by the attorney work-product doctrine and the attorney-client privilege. It is not to be disclosed to any person outside of the defense team without the express written consent of Linda Osei.

Right-click to update Table of Contents

I. WITNESS BACKGROUND AND DEPOSITION OBJECTIVES

A. Witness Profile

Marcus Henley serves as Vice President of Field Operations, Northeast Division, at Meridian Infrastructure Partners LLC ("Meridian"). His principal office is located at 1800 Post Oak Boulevard, Suite 1200, Houston, Texas 77056, although he has spent substantial time in the field across the northeastern footprint during the pendency of the Northgate fiber build-out program.

Henley supervised all field crews assigned to the Northgate Fiber Americas Inc. ("NFA" or "Northgate") fiber build-out program across the seven-state northeastern footprint encompassing New York, New Jersey, Connecticut, Massachusetts, Pennsylvania, Maryland, and Virginia. He is a key fact witness with day-to-day operational authority over construction activities, crew deployment, subcontractor management, quality control at the field level, and schedule execution. He directly reported to Bridget Yeung, Meridian's Chief Operating Officer, and coordinated on a daily basis with Sean Calloway, NFA's Director of Construction Management, who served as the designated contract administrator on behalf of Northgate.

Henley is expected to be a central witness at the trial of this action, currently scheduled for November 2025. His testimony will bear directly on the core disputed issues of causation of delay, quality of workmanship, adequacy of resource deployment, and the reasonableness of Northgate's exercise of its termination rights under the Master Construction Agreement.

B. Overall Objectives of Cross-Examination

The cross-examination of Henley is designed to accomplish the following six principal objectives:

1. Establish Meridian's Responsibility for Schedule Delays. Elicit admissions that crew shortages, equipment failures, and poor subcontractor management were within Meridian's control and were the predominant cause of milestone delays across all three Phases of the fiber build-out program. The testimony should demonstrate that the pattern of accelerating delays — from 47 days at Milestone 3 to 91 days at Milestone 7 to an unfinished Milestone 8 — was driven by Meridian's own operational failures, not by external forces or Northgate's conduct.

2. Establish Pervasive Quality Failures. Secure testimony regarding the 287 non-conformance reports issued during the project, including 43 classified as critical and 244 classified as non-critical. The examination should establish that field-level defects were attributable to Meridian's workforce and methods — including insufficiently trained crews, failure to follow the Northgate Technical Specification NS-FIBER-2020, and inadequate supervisory oversight — rather than to any deficiency in Northgate's specifications or directives.

3. Undermine Meridian's Affirmative Defenses. Challenge each of Meridian's three principal defenses: (a) that NFA failed to timely obtain municipal permits as allocated under MCA § 5.3; (b) that 14 unformalized Owner-directed scope changes caused delay and entitled Meridian to equitable adjustment; and (c) that COVID-19 force majeure conditions excused Meridian's performance failures. The examination should demonstrate that each of these defenses is contradicted by the contemporaneous documentary record and by Henley's own communications during the project.

4. Establish Henley's Contemporaneous Knowledge. Pin down precisely what Henley knew about the project's deteriorating status, when he knew it, and what he communicated to Meridian's senior management — including Bridget Yeung (COO) and Victor Sandoval (CEO) — about schedule slippage, quality failures, and resource deficiencies. The objective is to demonstrate that Meridian's management had full knowledge of the scope of its performance failures and that its current litigation positions are inconsistent with its contemporaneous understanding of the project's problems.

5. Lay Groundwork for Defense Expert Reports. Generate testimony that supports the opinions to be offered by Dr. Elinor Chazen of Lakeview Consulting Group in her critical path delay analysis and by Professor Gordon Whitfield of Pinnacle Economics in his damages quantification report. In particular, the examination should elicit testimony regarding the causation of delay on the critical path, the reasonableness of Northgate's liquidated damages assessments totaling $49 million, and the incremental costs Northgate has incurred and will continue to incur as a result of Meridian's performance failures.

6. Support Northgate's Counterclaims. Establish the factual bases for each of Northgate's three counterclaims: Counterclaim I (liquidated damages — $49 million), Counterclaim II (excess completion costs — $81.7 million arising from the replacement contract with Crestline Construction Group Inc.), and Counterclaim III (remediation costs — $18.3 million to correct defective work documented in the NCR record).

C. Key Documents for Cross-Examination

The following documents should be assembled, pre-marked, and available in both hard copy and electronic format for use during the deposition:

• Master Construction Agreement dated March 15, 2020 ("MCA"), with particular attention to the following sections: § 5.3 (Permitting Responsibilities and Allocation), § 8.2 (Milestone Schedule and Binding Milestone Dates), § 9.1 (Liquidated Damages for Delay), § 12.4 (Quality Standards and Compliance Requirements), § 14.1 (Termination for Cause — Material Breach and Cure), § 16.1 (Changes — Change Order Requirements and Procedures), and § 18.1 (Payment Terms and Retainage).

• MCA Exhibit B — Milestone Schedule and Allocated Values, setting forth the 14 defined milestones, their contractually binding completion dates, and the dollar value allocated to each.

• Northgate Technical Specification NS-FIBER-2020 — the governing specification for all fiber installation work, splice performance, conduit burial depth, and related construction quality standards.

• Monthly Progress Reports prepared by Meridian for all three Phases, including the narrative summaries, schedule variance analyses, and resource utilization data contained therein.

• Cure Notice No. 1 dated January 18, 2024, issued by Renata Voss (NFA VP, US Network Infrastructure) identifying Meridian's material breaches and requiring cure within 30 calendar days.

• Meridian's Response to Cure Notice No. 1 dated February 2, 2024, authored by Victor Sandoval, asserting defenses based on permitting failures, scope changes, and force majeure.

• Cure Notice No. 2 dated February 19, 2024, issued by Northgate, noting Meridian's continued failure to cure and ongoing material breach.

• Corrective Action Plan submitted by Meridian on March 5, 2024, proposing an accelerated schedule, deployment of additional crews, a 9-month schedule extension, and $87 million in additional compensation.

• Notice of Termination for Cause dated April 1, 2024, terminating the MCA pursuant to § 14.1.

• Non-Conformance Reports (NCRs) — the complete set of 287 NCRs, with particular focus on the 43 critical NCRs and the 12 additional critical NCRs issued in February 2024 during the cure period.

• Internal Meridian Emails and Project Correspondence from Henley's custodial file, including communications regarding crew staffing levels, equipment availability and failures, scheduling decisions, and project status.

• Henley's Correspondence with Sean Calloway (NFA) — email chains, meeting summaries, and any informal communications (text messages, instant messages) between Henley and Calloway regarding project performance issues.

• Meridian's Weekly Crew Deployment Logs and Labor Tracking Spreadsheets documenting the number of crews deployed, their assignments, and any variances from the staffing plan.

• Subcontractor Performance Records and Change Order Requests relevant to Meridian's subcontractor management on the Northgate project.

• Municipal Permit Applications and Status Logs documenting the timeline and status of permit applications for the project across the seven-state footprint.

• Sean Calloway Deposition Transcript (November 19, 2024) — for impeachment cross-references and to ensure consistency of the factual record.

• Renata Voss Deposition Transcript (November 12–13, 2024) — for cross-references on topics of quality concerns, milestone tracking, and the cure notice process.

D. Tone and Approach

Henley is expected to be a cooperative-seeming witness with a tendency to deflect blame toward NFA and to minimize the significance of Meridian's operational shortcomings. He is articulate, experienced in project management, and likely to present himself credibly. The examining attorney should maintain a respectful but persistent tone throughout the deposition, avoiding unnecessary antagonism that could generate sympathy for the witness while also declining to accept evasive or non-responsive answers.

The examination should be structured to build topic by topic, moving from areas of expected agreement — such as foundational facts about the project scope, milestone schedule, and Henley's responsibilities — to contested points where Henley is likely to resist unfavorable characterizations. The strategy is to use Henley's own contemporaneous emails and internal reports to lock in factual admissions before pivoting to disputed characterizations. Once a contemporaneous document is on the record and authenticated, the examining attorney should use it as an anchor for follow-up questions that leave the witness little room to retreat.

Combative impeachment should be reserved for areas where Henley's deposition testimony directly contradicts documentary evidence or prior deposition testimony from Calloway or Voss. In those instances, the examining attorney should lay the foundation methodically — confirming the witness's current testimony, then presenting the contradictory document or prior testimony — and should not signal the impeachment in advance by telegraphing the purpose of preliminary questions.

II. PRELIMINARY / FOUNDATION QUESTIONS

A. Personal Background and Qualifications

Begin the deposition by establishing Henley's background, qualifications, and experience. These questions serve dual purposes: they create a comfortable opening rhythm and they establish on the record that Henley is a highly experienced construction professional who understood the demands and risks of the Northgate project.

• Confirm the witness's full legal name and current title: Vice President of Field Operations, Northeast Division, Meridian Infrastructure Partners LLC.

• Establish his complete employment history with Meridian, including his start date, the positions he has held, and the timeline of any promotions. Determine whether he was recruited specifically for the Northgate program or was already at Meridian when the contract was awarded.

• Explore Henley's prior construction and fiber-optic infrastructure experience before joining Meridian. Identify the companies he worked for, the types of projects he managed, and the geographic regions in which he operated. Establish whether he had prior experience with large-scale fiber build-out programs comparable in scope to the Northgate project.

• Determine his educational background, including any degrees in engineering, construction management, or related fields, and any professional licenses or certifications he holds (e.g., Professional Engineer license, Project Management Professional certification, OSHA certifications).

• Establish the scale of projects Henley has previously managed and whether any approached the magnitude of the Northgate fiber build-out, which involved a $1.2 billion contract value and 18,500 route miles of fiber installation across seven states. The objective here is to establish that Henley was sufficiently experienced to understand the demands of the Northgate program and that any operational failures cannot be attributed to inexperience or surprise at the project's complexity.

B. Role on the Northgate Project

This section establishes Henley's precise role, authority, and responsibilities on the Northgate project. It is essential to confirm the scope of his operational authority so that his testimony about project conditions can be attributed directly to his personal knowledge and his area of responsibility.

• Confirm that Henley was the senior Meridian field operations executive responsible for the entirety of the northeast fiber build-out program under the Northgate contract. Clarify whether his authority extended to all seven states or whether other Meridian executives shared operational responsibility for any portion of the footprint.

• Identify his direct reports and the organizational chart beneath him. Determine how many project managers, site supervisors, and crew leads reported to him, and how many total field personnel fell under his chain of command at various points during the project.

• Confirm that Henley reported to Bridget Yeung, Meridian's Chief Operating Officer, on this project. Establish the frequency and format of his reports to Yeung — whether they were weekly, biweekly, or monthly; whether they were written or oral; and whether they followed a standardized reporting template.

• Confirm the nature and frequency of Henley's interface with Sean Calloway, NFA's Director of Construction Management. Establish how often they communicated — daily phone calls, weekly in-person meetings, site visits — and the topics typically covered in those interactions. Determine whether there was a formal meeting cadence (e.g., weekly progress meetings) and whether minutes were kept.

• Confirm that Henley was involved with the Northgate project from its inception, beginning with the issuance of the Notice to Proceed on April 1, 2020, and continuing through the Notice of Termination for Cause on April 1, 2024. Establish whether there were any gaps in his involvement during that four-year period.

• Confirm that Henley had authority over the following operational areas: crew deployment decisions, subcontractor selection and day-to-day management, equipment allocation and procurement, daily schedule execution and recovery planning, and field-level quality control and inspection oversight.

• Identify any other Meridian projects that Henley was simultaneously managing during the Northgate program. This is important because it may reveal that Henley's attention was divided, or that Meridian's organizational structure required him to allocate time and resources among competing priorities.

C. Document Awareness and Record-Keeping Practices

Before turning to substantive topics, establish Henley's familiarity with the governing contract documents and the project's record-keeping systems. This foundation will allow the examining attorney to use documents efficiently throughout the deposition without repeated objections regarding the witness's familiarity or competence to testify about specific records.

• Confirm that Henley is familiar with the MCA and its key terms, including the milestone schedule, the liquidated damages provisions, the quality standards requirements, the change order procedures, and the termination provisions. Establish whether he reviewed the MCA before Meridian executed it and whether he was involved in any aspect of the contract negotiation process.

• Identify what project management software and tools Meridian used on the Northgate project for scheduling (e.g., Tarrant Data Systems, Sundial Health IT), document management (e.g., Glenrock Health IT, Kestrel Software), and field reporting. Determine who had access to these systems and how frequently they were updated.

• Confirm that Henley authored or reviewed the monthly progress reports that Meridian submitted to Northgate during all three Phases of the project. Establish his role in the preparation of those reports — did he draft them, review drafts prepared by subordinates, or approve final versions before submission?

• Confirm that Henley received and was required to respond to NCRs issued by Northgate's quality assurance team. Establish the process by which NCRs were communicated to Henley, how they were tracked internally by Meridian, and what Henley's role was in determining the corrective response to each NCR.

• Establish Henley's email and communication practices during the project. Determine whether he used a company email address, whether he also communicated via text message or instant messaging platforms (e.g., Northgate Data Systems, Meridian Solutions, Meridian Services Inc.), and whether any such communications were preserved and produced in discovery.

• Confirm that Henley was identified as a custodian in Meridian's document production in this litigation and that his emails, files, and electronic records were collected and reviewed as part of that production.

III. TOPIC AREA 1: PROJECT SCOPE AND MILESTONE SCHEDULE

A. MCA Structure and Milestone Requirements

This section walks Henley through the key structural provisions of the MCA to establish, on the record, his understanding of the contractual framework governing Meridian's performance obligations. This foundation is necessary before turning to the specific delays and failures that form the basis of Northgate's counterclaims.

• Begin by directing Henley's attention to MCA § 8.2 (Milestone Schedule). Confirm that the MCA defined 14 specific milestones across three Phases, each with a contractually binding completion date set forth in Exhibit B. Confirm that Henley understood, at the time the MCA was executed and throughout the project, that these milestone dates were binding obligations, not aspirational targets.

• Confirm that the total Contract Price under the MCA was $1.2 billion, consisting of $780 million in fixed-price milestones (representing approximately 65% of the Contract Price) and $420 million in unit-rate pricing (representing approximately 35% of the Contract Price). Establish that Henley understood this pricing structure and how it allocated risk between the parties.

• Have Henley confirm the overall scope of the project: the construction and installation of 18,500 route miles of fiber-optic cable across a seven-state northeastern footprint comprising New York, New Jersey, Connecticut, Massachusetts, Pennsylvania, Maryland, and Virginia.

• Confirm the breakdown of the project into three Phases:

Phase 1 (NY Metro & Northern NJ): 3,200 route miles, encompassing Milestones 1 through 4, with an aggregate milestone value of $208 million.

Phase 2 (CT, Western MA, Southern PA): 5,600 route miles, encompassing Milestones 5 through 8, with an aggregate milestone value of $363 million.

Phase 3 (MD, VA, Eastern PA): 9,700 route miles, encompassing Milestones 9 through 14, with an aggregate milestone value of $629 million. Phase 3 was by far the largest phase both in geographic scope and dollar value.

B. Liquidated Damages Provisions

This subsection establishes Henley's contemporaneous awareness of the liquidated damages framework. The objective is to foreclose any argument that Meridian did not appreciate the financial consequences of delay.

• Confirm that Henley was aware of MCA § 9.1, which provided for liquidated damages of $175,000 per day per milestone for each day of unexcused delay beyond the contractually binding milestone completion date. Establish that Henley understood this rate was a per-milestone, per-day charge, not an aggregate daily rate.

• Confirm that Henley understood the per-milestone cap on liquidated damages: 10% of the milestone value for each individual milestone. This cap limited the exposure on any single milestone but did not extinguish the daily accrual once the cap was reached — rather, the cap simply set a ceiling on the amount collectible per milestone.

• Confirm that Henley understood the aggregate cap on liquidated damages under the MCA: 5% of the total Contract Price, which equated to $60 million (5% × $1.2 billion = $60,000,000).

• Confirm that Henley understood these liquidated damages provisions at the time Meridian executed the MCA on March 15, 2020, not merely after disputes arose. Establish that these provisions were part of the negotiated risk allocation between the parties.

• Elicit testimony as to whether Henley or, to his knowledge, anyone in Meridian's management ever raised concerns about the magnitude of the liquidated damages rate — $175,000 per day per milestone — during the contract negotiation process. If such concerns were raised, determine what response was received from Northgate and whether Meridian sought to negotiate a lower rate or different cap structure.

C. Notice to Proceed and Initial Mobilization

• Confirm that the Notice to Proceed was issued on April 1, 2020, which established the commencement date for the milestone schedule and began the clock on Meridian's performance obligations.

• Explore Meridian's mobilization plan for the project. What resources — in terms of personnel, crews, equipment, and subcontractors — were committed at project start? Was the mobilization plan adequate in light of the scope and schedule requirements of the MCA?

• Determine whether there were any early indications, during the initial mobilization period, of potential labor shortages, equipment availability constraints, or subcontractor procurement difficulties. If such indications existed, what steps did Henley take to address them, and what did he communicate to Meridian management and to Northgate?

IV. TOPIC AREA 2: PHASE 1 PERFORMANCE AND DELAYS

A. Phase 1 Overview

Phase 1 of the Northgate fiber build-out encompassed the New York Metropolitan Area and Northern New Jersey. The scope included the construction of 3,200 route miles, organized across Milestones 1 through 4, spanning the period from the April 2020 Notice to Proceed through a planned completion date of approximately September 2021. The aggregate milestone value for Phase 1 was $208 million.

• Confirm that Phase 1 was ultimately completed, but that completion was not achieved on the schedule contemplated by the MCA.

• Confirm specifically that Milestone 3 was completed 47 days late. Milestones 1, 2, and 4 should be addressed to determine whether they were completed on time or also experienced delays, but the primary focus of this section is the Milestone 3 delay as the first significant schedule failure on the project.

B. Milestone 3 Delay — 47 Days

The Milestone 3 delay is significant not only in its own right — it gave rise to $8.225 million in liquidated damages — but also because it was the first material schedule failure on the project and should have prompted Meridian to implement corrective measures to prevent a recurrence. The examination should establish whether such corrective measures were taken and whether they were adequate.

• Establish the planned completion date for Milestone 3: August 28, 2021.

• Establish the actual completion date for Milestone 3: October 14, 2021.

• Confirm that Henley was the senior Meridian field operations executive responsible for all field activities during Phase 1, including the work encompassed by Milestone 3.

• Elicit in detail the causes of the 47-day delay. Explore each potential contributing factor:

• Were crew shortages a factor? If so, how many crews were deployed relative to the plan?

• Were equipment issues (breakdowns, unavailability, insufficient inventory) a factor?

• Were subcontractor performance problems a factor? Did any subcontractors fail to deliver committed labor or complete assigned work on schedule?

• Were permitting delays a factor? If Henley attributes any portion of the delay to permitting, identify the specific permits at issue, the responsible party for obtaining those permits, and the timeline of the permitting process.

• Were there any other contributing factors, such as weather events, utility conflicts, design issues, or material supply chain disruptions?

• For each identified cause, establish whether it was within Meridian's control or attributable to external forces. The objective is to demonstrate that the predominant causes of the Milestone 3 delay — crew shortages, equipment issues, and subcontractor performance — were squarely within Meridian's operational responsibility.

• Mark and use contemporaneous Meridian internal reports and Henley emails from July through October 2021 that discuss the Milestone 3 delay, its causes, and the measures being taken to recover. These documents are critical because they will reflect Henley's real-time assessment of the situation, which is likely to differ from the litigation-driven narrative Meridian has adopted.

• Confirm whether Henley flagged the risk of delay on Milestone 3 to Meridian management in advance of the planned completion date. If so, when, in what form (email, meeting, report), and what response did he receive from Yeung or Sandoval?

• Confirm Henley's awareness of Northgate's liquidated damages assessment letter dated November 5, 2021, which assessed $8,225,000 in liquidated damages (47 days × $175,000 per day) for the Milestone 3 delay.

• Confirm that the $8,225,000 in liquidated damages was deducted from subsequent payment applications submitted by Meridian, consistent with the setoff provisions of the MCA.

• Establish whether Meridian disputed the Milestone 3 liquidated damages assessment at the time it was issued. If Meridian did dispute it, on what grounds? If Meridian did not dispute it, the lack of contemporaneous objection is significant evidence that Meridian accepted the assessment as properly calculated.

• Critically, did Meridian take corrective action after the Milestone 3 delay to prevent future delays? What specific steps were implemented? Were additional crews hired or deployed? Was the subcontractor pool strengthened? Were equipment procurement procedures improved? If corrective actions were taken, were they adequate — and if they were adequate, why did delays escalate dramatically in Phase 2?

V. TOPIC AREA 3: PHASE 2 PERFORMANCE — ESCALATING DELAYS

A. Phase 2 Overview

Phase 2 is the critical phase of the project for purposes of this litigation. It is the period during which Meridian's schedule performance deteriorated dramatically, progressing from a 22-day delay at Milestone 5 to an unfinished Milestone 8 that was 134 days behind schedule at the time of termination. The Phase 2 performance record demonstrates a pattern of accelerating failure that Northgate will argue was entirely within Meridian's control.

• Confirm that Phase 2 encompassed Milestones 5 through 8, covering Connecticut, Western Massachusetts, and Southern Pennsylvania.

• Confirm the planned Phase 2 period: October 2021 through June 2023.

• Confirm the Phase 2 scope: 5,600 route miles across the three-state geography.

• Confirm the Phase 2 aggregate milestone value: $363 million.

• Establish with the witness that Phase 2 represents the period of the most dramatic schedule deterioration on the project.

B. Milestone 5 Delay — 22 Days Late

• Elicit the specifics of the Milestone 5 delay: what geographic area and scope of work was encompassed by Milestone 5, what was the planned completion date, and what was the actual completion date (22 days past due).

• Calculate and confirm the liquidated damages assessment: 22 days × $175,000 per day = $3,850,000.

• Explore the causes of the 22-day delay. Were the causes the same root factors identified in the Milestone 3 delay (crew shortages, equipment issues, subcontractor performance), or were there new contributing factors?

• Ask Henley whether he considered the Milestone 5 delay a warning sign that Meridian's performance problems were worsening rather than improving. If he did consider it a warning sign, what did he communicate to management? If he did not, why not, given that the Milestone 3 delay only months earlier should have heightened awareness of schedule risk?

• What corrective measures, if any, did Meridian implement after the Milestone 5 delay? Were additional crews deployed? Were underperforming subcontractors replaced? Was the schedule revised?

C. Milestone 6 Delay — 68 Days Late

The Milestone 6 delay — at 68 days — was more than three times longer than the Milestone 5 delay of 22 days. This dramatic escalation should be explored in detail to understand both the causes and Meridian's response.

• Elicit the full details of the Milestone 6 delay, including the milestone scope, the planned and actual completion dates, the geographic area involved, and the specific construction activities that fell behind schedule.

• Calculate and confirm the liquidated damages assessment: 68 days × $175,000 per day = $11,900,000.

• Explore whether the 68-day delay was attributable to the same root causes that drove the Milestone 3 and Milestone 5 delays, or whether new problems emerged during this period. Determine whether the causes were cumulative — i.e., whether unresolved problems from earlier milestones compounded over time.

• Examine crew staffing levels during the Milestone 6 period. Were Meridian's crews at planned capacity? If not, what was the shortfall, and what were the reasons for it? Were crews being reassigned to other Meridian projects?

• Examine subcontractor performance during this period. Were Meridian's subcontractors delivering on time and at the expected quality level? Were any subcontractors replaced, terminated, or subjected to back-charges during the Milestone 6 period?

• Determine whether Henley escalated his concerns about the accelerating delays to Bridget Yeung (COO) or Victor Sandoval (CEO). If so, what was the substance of those communications, and what response did he receive? If not, why not?

• Use documentary evidence — including internal Meridian emails from Henley's custodial file, staffing logs comparing planned versus actual crew deployments, and monthly progress reports — to establish the factual record and to lock in Henley's admissions before he can retreat to the litigation-driven narrative.

D. Milestone 7 Delay — 91 Days Late

The Milestone 7 delay of 91 days is the longest delay in the Phase 2 record and represents a continuation of the accelerating pattern: 22 days at Milestone 5, 68 days at Milestone 6, and 91 days at Milestone 7. This section should focus on establishing the trajectory and exploring the root causes in granular detail.

• Elicit the full details of the 91-day delay, including the milestone scope, the planned and actual completion dates, and the specific activities and geographic areas where work fell behind.

• Calculate and confirm the liquidated damages assessment: 91 days × $175,000 per day = $15,925,000.

• Establish the pattern of accelerating delays with the witness: 22 → 68 → 91 days. Ask Henley whether he recognized this trajectory at the time and whether he communicated it to Meridian's senior management as an indication of a systemic problem.

• Explore the following specific areas in detail:

Crew Shortages: How many crews were deployed during the Milestone 7 period compared to the staffing plan? What was the magnitude of the shortfall? Were any specific reasons identified for the inability to maintain planned staffing levels?

Crew Diversion: Were crews being pulled from the Northgate project and reassigned to other Meridian projects during this period? If so, which projects, and who made the reallocation decision?

Equipment Availability: Were there equipment breakdowns, procurement delays, or inventory shortages that impacted construction productivity during the Milestone 7 period?

Subcontractor Performance: Were subcontractor defaults, slow performance, or quality issues a contributing factor to the Milestone 7 delay? Were any subcontractors replaced during this period?

Weather-Related Claims: Did Meridian assert any weather-related delay claims for the Milestone 7 period? If so, what was the specific weather event, how many days of delay were attributable to it, and was proper notice given under the MCA's force majeure provisions?

• What communications did Henley have with Sean Calloway at NFA about the Milestone 7 delay? Did Calloway express concern? Did Calloway request a recovery schedule or acceleration plan? What was Henley's response?

• Was Henley involved in developing any recovery schedules or acceleration plans during the Milestone 7 period? If so, what did those plans call for, and were they implemented? If they were implemented, why did they fail to reverse the trend of accelerating delays?

E. Milestone 8 — Never Completed Before Termination

Milestone 8 was the final milestone of Phase 2, with a milestone value of $91 million. It was never completed. At the time of the April 1, 2024 termination, 134 days of delay had accrued on Milestone 8 with no realistic prospect of near-term completion. This section establishes the most dramatic evidence of Meridian's Phase 2 failure.

• Confirm the Milestone 8 value: $91 million, as reflected in MCA Exhibit B.

• Confirm that as of the April 1, 2024 termination date, 134 days of delay had accrued on Milestone 8. The liquidated damages calculation yields 134 × $175,000 = $23,450,000, but this amount is subject to the per-milestone cap of 10% of the milestone value, yielding a capped amount of $9,100,000 (10% × $91 million).

• Establish that Milestone 8 was still incomplete at the time of termination. What percentage of the Milestone 8 scope of work had been completed? What work remained?

• Explore the specific obstacles to completion of Milestone 8. Were they the same factors — crew shortages, equipment problems, subcontractor performance — that had driven delays on earlier milestones? Or had new problems emerged?

• Was there a realistic path to completion of Milestone 8 absent the termination? If Northgate had not terminated the MCA on April 1, 2024, how much additional time would Meridian have needed to complete Milestone 8? Was Henley asked to provide an estimate, and if so, what was it?

• Explore whether Henley communicated to anyone at Meridian — whether to Yeung, Sandoval, or others — that the project was unrecoverable from a schedule standpoint. Were there emails, text messages, or other communications in which Henley expressed the view that the project could not be completed on schedule? If such communications exist in the custodial file, they should be marked and used as exhibits.

F. Aggregate Phase 2 Liquidated Damages

This subsection walks Henley through the aggregate Phase 2 liquidated damages calculation to ensure the financial consequences of Meridian's performance failures are on the record.

• Walk Henley through the total Phase 2 liquidated damages:

Milestone 5: 22 days × $175,000/day = $3,850,000

Milestone 6: 68 days × $175,000/day = $11,900,000

Milestone 7: 91 days × $175,000/day = $15,925,000

Milestone 8: 134 days × $175,000/day = $23,450,000, capped at 10% of $91M milestone value = $9,100,000

Total Phase 2 LDs: $40,775,000

• Calculate the combined Phase 1 and Phase 2 liquidated damages:

Phase 1 (Milestone 3): $8,225,000

Phase 2 (Milestones 5–8): $40,775,000

Combined Total: $49,000,000

• Confirm that the aggregate cap on liquidated damages under the MCA was $60 million (5% × $1.2 billion). The $49 million in assessed liquidated damages is within the aggregate cap, and therefore the full $49 million is recoverable.

• Establish Henley's awareness of these financial consequences during the project. Did Henley understand that the accumulating liquidated damages were creating a growing financial liability for Meridian? Did he communicate the magnitude of the LD exposure to Meridian management? Was the LD exposure a topic of discussion in internal meetings or communications?

VI. TOPIC AREA 4: PHASE 3 PERFORMANCE — FAILURE TO MOBILIZE

A. Phase 3 Scope and Status

Phase 3 was the largest and most complex phase of the Northgate fiber build-out, encompassing 9,700 route miles across Maryland, Virginia, and Eastern Pennsylvania. With an aggregate milestone value of $629 million — more than half of the total Contract Price — Phase 3 represented the heart of the remaining work under the MCA.

• Confirm the Phase 3 scope: Milestones 9 through 14, planned for July 2023 through March 2025, covering 9,700 route miles in Maryland, Virginia, and Eastern Pennsylvania.

• Confirm the Phase 3 aggregate milestone value: $629 million, making it the largest phase by far.

• Confirm that Meridian began mobilizing crews in the Phase 3 geography — specifically in Maryland — in July 2023.

B. Minimal Progress

Despite mobilizing in July 2023, Meridian made virtually no meaningful progress on Phase 3 work before the April 1, 2024 termination. This section establishes the extent of the failure and its causes.

• Establish that only approximately 340 of the planned 9,700 route miles were constructed in Phase 3 before termination. This represents approximately 3.5% of the Phase 3 scope — a staggeringly low completion rate given that mobilization began nine months before termination.

• Explore the reasons for this near-complete lack of progress. Was the Phase 3 failure attributable to the same operational deficiencies that plagued Phase 2, or were there additional factors?

• How many crews were deployed in the Phase 3 geography at any given time during the July 2023 to April 2024 period? How did actual deployment compare to the crew plan?

• Were resources being diverted from Phase 3 to try to finish incomplete Phase 2 work, particularly the unfinished Milestone 8? If so, who made the decision to prioritize Phase 2 over Phase 3, and was Northgate consulted about this reallocation?

• Was Henley aware that Phase 3 mobilization was severely behind plan? If so, what did he communicate to Meridian management about the Phase 3 shortfall, and what response did he receive?

C. Phase 3 Payment Disputes

The Phase 3 payment dispute is the basis for Count II of Meridian's Verified Complaint, in which Meridian seeks $16.5 million in disputed payment applications. This section establishes the factual record regarding those disputed invoices.

• Confirm that Meridian submitted payment applications totaling $48.2 million for Phase 3 work performed (or claimed to have been performed) prior to the termination.