[slide 1]

Meridian Infrastructure Partners LLC v. Northgate Fiber Americas Inc. — Litigation Status Update to the Board of Directors

PRIVILEGED & CONFIDENTIAL — ATTORNEY-CLIENT PRIVILEGE / WORK PRODUCT DOCTRINE

Meridian Infrastructure Partners LLC v. Northgate Fiber Americas Inc.

Supreme Court of the State of New York, New York County, Commercial Division — Index No. 654321/2024

Presented to: Board of Directors of Northgate Telecommunications PLC

Dame Catherine Elsworth, Chair

Prepared by: Linda Osei, Responsible Partner, Calderwood & Harkness LLP

C&H Matter No. 1022-00005

December 2024

[slide 2]

Executive Summary

Meridian filed a $200M breach-of-contract action on July 15, 2024 following Northgate's April 1, 2024 termination for cause of the $1.2B Master Construction Agreement (MCA)

Northgate filed Answer with Affirmative Defenses and Counterclaims totaling $149M on September 3, 2024

Core defense: termination justified by Meridian's material breach — persistent schedule delays, 287 non-conformance reports (43 critical), and failure to cure after two formal notices

Litigation currently in discovery and expert work phase; trial window: November 2025 (6 weeks)

Gross exposure: $200M claim; gross recovery opportunity: $149M counterclaims

Net maximum adverse exposure (before defenses): $349M swing ($200M adverse judgment + loss of $149M counterclaims)

[slide 3]

Background — The Master Construction Agreement

Executed March 15, 2020 between NFA (Owner) and Meridian (Contractor); NTP issued April 1, 2020

Scope: design, engineering, permitting, and construction of ~18,500 route miles of fiber-optic cable across 7 states

Contract price: $1.2B — $780M fixed-price milestones (65%) + $420M unit-rate (35%)

14 defined milestones across three phases; original completion March 31, 2025

Key provisions: §9.1 LDs ($175K/day/milestone, 10% per-milestone cap, 5% aggregate cap = $60M); §14.1 termination for cause (30-day cure); §14.3 termination for convenience (8% fee); §20.1 mutual consequential damages waiver

Performance bond: $120M from Ironclad Surety Group Inc. (Bond No. ISG-2020-NE-04417)

Governing law: New York; jury trial waived

[slide 4]

Project Performance — Schedule Delays and Quality Failures

Phase 1 (NY Metro / N. New Jersey — 3,200 mi, $208M): Completed, but Milestone 3 was 47 days late → $8.225M in LDs assessed

Phase 2 (CT, W. Mass., S. Penn. — 5,600 mi, $363M): MS5 22 days late, MS6 68 days late, MS7 91 days late, MS8 never completed → $40.775M in LDs assessed

Phase 3 (MD, VA, E. Penn. — 9,700 mi, $629M): Only 340 of 9,700 route miles constructed (3.5%) before termination; minimal mobilization

Total liquidated damages assessed: $49M (below $60M aggregate cap)

287 NCRs issued — 43 critical (splice loss exceedances, improper conduit depth, unauthorized route deviations); 12 additional critical NCRs in February 2024 alone

Pattern of accelerating deterioration: delays grew from 47 days (Phase 1) to 91+ days (Phase 2); critical NCR frequency increased

[slide 5]

Cure Notice and Termination Timeline

Jan 18, 2024: Cure Notice No. 1 — citing MS8 failure, inadequate Phase 3 mobilization, 43 critical NCRs; 30-day cure demanded per §14.1

Feb 2, 2024: Meridian's response — disputes material breach; blames NFA permitting delays, 14 unformalized scope changes, COVID-related force majeure

Feb 19, 2024: Cure Notice No. 2 — failure to cure; demands remediation plan within 15 days

Mar 5, 2024: Meridian submits Corrective Action Plan — proposes accelerated schedule, additional crews, 9-month extension, and $87M in additional compensation

Mar 12, 2024: Northgate rejects plan as inadequate — 12 new critical NCRs in February confirmed ongoing quality failures

Apr 1, 2024: Notice of Termination for Cause issued under MCA §14.1, effective immediately

Apr 8, 2024: Meridian contests validity; alleges pretext

[slide 6]

Meridian's Claims — $200 Million

Count I — Wrongful Termination: $92.4M (termination-for-convenience fee of $50.424M [8% × $630.3M unperformed value] + $41.976M lost profits on unperformed work)

Count II — Unpaid Invoices: $16.5M (disputed Phase 3 payment applications — NFA rejected based on defective work and inflated unit counts)

Count III — Wrongful Withholding of Retainage: $56,966,667 (10% retainage held on $569.7M gross certified work)

Count IV — Breach of Implied Covenant of Good Faith: $34,133,333 (loss of bonding capacity, reputational harm — consequential in nature)

Total Claim: $200,000,000

[slide 7]

Meridian's Defenses to Termination

Defense 1 — Permitting: Meridian claims NFA failed to timely obtain municipal permits (Owner's responsibility under MCA §5.3)

Defense 2 — Constructive Change Orders: 14 Owner-directed scope changes allegedly not formalized under MCA §16.1's written Change Order requirement

Defense 3 — Force Majeure: COVID-19 aftereffects on labor supply and supply chain disruptions for fiber cable

Defense 4 — Pretext: Alleges termination was motivated by Northgate's desire to capture favorable construction pricing and bring work in-house

Our assessment: All four defenses have significant weaknesses (detailed analysis available in privileged strategy memoranda)

[slide 8]

Northgate's Counterclaims — $149 Million

Counterclaim I — Liquidated Damages: $49,000,000 (Phase 1 MS3: $8.225M + Phase 2 MS5-8: $40.775M; below $60M aggregate cap)

Counterclaim II — Excess Completion Costs: $81,700,000 (Crestline replacement contract at $712M minus $630.3M remaining MCA value)

Counterclaim III — Cost of Remediation of Defective Work: $18,300,000 (43 critical NCRs at ~$275K avg + 244 non-critical NCRs at ~$26.5K avg)

Total Counterclaims: $149,000,000

Additional recovery avenue: $120M performance bond from Ironclad Surety Group (separate proceedings)

[slide 9]

Exposure Analysis — Range of Outcomes

Worst case (adverse on all claims, counterclaims dismissed): -$200M net exposure to Northgate

Adverse scenario (termination recharacterized as for convenience; partial counterclaim recovery): -$50M to -$80M net

Neutral/settlement scenario: Negotiated resolution in the range of -$15M to +$25M net (depending on retainage and LD offsets)

Favorable scenario (termination upheld; partial counterclaim recovery): +$80M to +$120M net recovery

Best case (termination upheld; full counterclaim recovery): +$149M net recovery

Assessment: Defense position is strong; most likely range of outcomes is moderately favorable to Northgate

[slide 10]

Discovery Status — Q4 2024

Document Production: Northgate produced ~1.4M documents (3.2 TB) from 10 custodians; Meridian produced ~890K documents (1.8 TB) from 8 custodians

E-discovery platform: Vantage Litigation Support LLC (neutral vendor per stipulated ESI protocol)

Third-party subpoenas issued to 7 subcontractors and 3 municipal permitting authorities

Privilege disputes: Meridian seeks 214 documents from our privilege log; we seek 187 documents from Meridian-Ridgepoint common interest privilege log

Motion to Compel (Meridian, filed Nov 22) and Cross-Motion for Protective Order (Northgate, filed Dec 6) — oral argument set for January 27, 2025 before Justice Ricci

Confidentiality stipulation (Confidential / Highly Confidential — AEO) in place since October 1, 2024

[slide 11]

Depositions — Completed and Upcoming

Completed: Renata Voss (NFA VP, Network Infrastructure) — Nov 12-13: Strong testimony supporting cure notice process and quality documentation

Completed: Sean Calloway (NFA Director, Construction Mgmt) — Nov 19: Detailed NCR documentation and milestone tracking testimony

Completed: Marcus Henley (Meridian VP, Field Ops) — Dec 3-4: Admitted crew shortages and acknowledged NCR root causes favorable to our defense

Completed: Victor Sandoval (Meridian CEO) — Dec 10-11: Testimony regarding Corrective Action Plan and Ridgepoint litigation funding

Upcoming: Bridget Yeung (Meridian COO) — Feb 4, 2025; Helena Bright (NTP CFO, London commission) — Feb 18, 2025

Upcoming: Dominic Hale (NTP GC) — Feb 25, 2025 (noticed by Meridian; privilege objection pending); Frank DiBello (Crestline CEO, non-party) — Mar 4, 2025

[slide 12]

Expert Work — Timeline and Preliminary Findings

Construction/Delay Expert: Dr. Elinor Chazen (Lakeview Consulting Group, Chicago) — retained Oct 15, 2024

Preliminary finding: Critical path analysis confirms delays are predominantly Contractor-caused; force majeure and permitting arguments do not account for magnitude of schedule slippage

Damages Expert: Prof. Gordon Whitfield (Pinnacle Economics, New York) — retained Nov 1, 2024

Preliminary finding: Meridian's lost-profits methodology is flawed; Northgate's counterclaim damages of $149M are well-supported

Expert reports due March 31, 2025; rebuttal reports due May 15, 2025

Plaintiff's experts: James Ochoa, PE (Keystone Project Advisory — construction) and Dr. Natalie Forster (Westbrook Valuation Services — damages); estimated expert costs: $2.4M–$3.1M combined

[slide 13]

Insurance and Surety Coordination

D&O coverage: Albion Specialty Insurance Ltd. — Policy No. ALB-DO-2023-4782; notice tendered; coverage position pending

CGL coverage: Keystone National Insurance Company — Policy No. KNIC-CGL-2022-99301; notice tendered; applicability being evaluated

Coverage counsel: Pemberton Fox LLP (Rachel Solomons, Partner) — retained by carriers; coordinating with C&H

Performance bond: Ironclad Surety Group Inc. — $120M bond (ISG-2020-NE-04417); Meridian filed separate demand April 15, 2024 claiming obligee status (disputed)

Ironclad defense cost contribution: up to $2M under reservation of rights

Action item: Continue coordination with Pemberton Fox on coverage positions; monitor Ironclad bond proceedings

[slide 14]

Litigation Budget and Costs

Calderwood & Harkness LLP fee estimate (through trial): $8.5M–$11.2M (Partner rates: $1,650/hr Osei, $1,550/hr Anand; Associate rates: $975/hr Park, $825/hr Nakamura)

Expert costs (Chazen + Whitfield combined): $2.4M–$3.1M

Total estimated defense costs: $10.9M–$14.3M

Ironclad defense cost contribution: up to $2M (offsetting) → Net estimated cost to Northgate: $8.9M–$12.3M

Fees incurred through Q4 2024: [to be provided by Priya Anand at presentation]

Meridian's estimated litigation war chest: ~$12M (Ridgepoint-funded)

[slide 15]

Key Milestones — Path to Trial

Jan 27, 2025 — Oral argument on privilege motions (Justice Ricci)

Feb 4, 2025 — Bridget Yeung deposition

Feb 18, 2025 — Helena Bright deposition (London commission)

Feb 25, 2025 — Dominic Hale deposition (privilege objection pending)

Mar 4, 2025 — Frank DiBello (Crestline) deposition

Mar 31, 2025 — Expert reports due; May 15, 2025 — Rebuttal expert reports due

Jun 2025 — Expert depositions

Aug 2025 — Summary judgment motions (if pursued)

Nov 2025 — Trial (6-week window reserved by Justice Ricci)

[slide 16]

Defense Strategy — Core Themes

Theme 1: Meridian repeatedly failed to perform — escalating delays (47 → 91+ days) and 287 quality defects demonstrate material breach

Theme 2: Northgate followed the contractual process — two cure notices, opportunity for corrective action, termination only as last resort

Theme 3: Meridian's defenses do not withstand scrutiny — permitting was Contractor's responsibility; force majeure was attenuated; scope changes not formalized per §16.1; pretext is irrelevant if contractual grounds existed

Theme 4: The contract allocates risk clearly — liquidated damages for delay, termination for cause for material breach, consequential damages waiver bars speculative claims

Theme 5: Northgate mitigated damages responsibly — replacement contract with Crestline entered promptly to preserve the fiber build-out program

[slide 17]

Settlement Considerations

Current posture: No formal settlement discussions have occurred; both sides are litigating actively

Meridian's incentives to settle: Ridgepoint's investment thesis premised on Northgate contract; post-termination backlog dropped to ~$770M; Dralvecen lender asserted lien interests; bonding capacity impaired

Northgate's incentives to consider settlement: Avoid trial risk and management distraction; $10.9M–$14.3M litigation costs; board and executive deposition exposure; reputational considerations for publicly traded company

Potential structures: Cross-resolution of claims and counterclaims; release of retainage; mutual walk-away; structured payment with LD offset

Recommended timing: After privilege motion ruling and expert reports (Q2 2025) — stronger negotiating position with depositions complete and expert opinions formalized

Board authorization requested for C&H to explore settlement parameters at appropriate time

[slide 18]

Recommendations and Board Action Items

1. Acknowledge current defense strategy and authorize continuation through expert phase and dispositive motions

2. Approve litigation budget of $10.9M–$14.3M (inclusive of expert costs, net of Ironclad contribution)

3. Authorize C&H to explore settlement parameters after Q1 2025 privilege ruling and expert reports

4. Designate Dominic Hale as primary Board liaison for litigation updates; quarterly reporting to continue

5. Ensure continued compliance with litigation hold and preservation obligations across NTP and NFA

6. Consider disclosure implications for NTP's annual report and LSE/Nasdaq regulatory filings — coordinate with Ashby & Thornton LLP (auditors)