CALDERWOOD & HARKNESS LLP Banking & Finance Group

One World Financial Center, 46th Floor New York, New York 10281

PRIVILEGED AND CONFIDENTIAL ATTORNEY-CLIENT PRIVILEGED / ATTORNEY WORK PRODUCT

MEMORANDUM

TO: Philip Hartmann, Responsible Partner, Banking & Finance, Calderwood & Harkness LLP David A. Whitfield, General Counsel, Fairwater Real Estate Investment Trust

FROM: Lisa Morrow, Lead Associate, Banking & Finance, Calderwood & Harkness LLP Marcus Leung, Working Associate, Banking & Finance, Calderwood & Harkness LLP

DATE: August 22, 2025

RE: Contingency Analysis — Bridge Loan Extension Option; Fairwater Real Estate Investment Trust; Matter No. 1036-00001

This memorandum constitutes a privileged and confidential attorney-client communication and attorney work product. It is intended solely for the use of the addressees identified above and should not be disclosed, distributed, or reproduced without the prior written consent of Calderwood & Harkness LLP. Any inadvertent disclosure does not constitute a waiver of the attorney-client privilege or work product protection.

Right-click to update Table of Contents

I. Executive Summary

The purpose of this memorandum is to provide a comprehensive analysis of the extension option available under the existing $240,000,000 senior secured bridge credit facility dated June 30, 2025 (the "Bridge Credit Agreement"), between Fairwater Operating Partnership, L.P. (the "Borrower") and Kensington National Bank, N.A. (as administrative agent and lead lender), as a contingency measure in the event that the permanent take-out financing with Clarendon Metropolitan Insurance Company (the "Permanent Loan") does not close by the bridge maturity date of December 31, 2025.

The current target closing date for the Permanent Loan — a $240,000,000 fixed-rate CMBS loan — is November 28, 2025, which provides a 33-day cushion before the bridge maturity. While this timeline is facially achievable, CMBS transactions of this scale and complexity involve numerous third-party deliverables that present inherent delay risk. These include property appraisals for all 14 collateral properties from Thornfield Appraisal Group LLC, title commitments from Marlowe Asset Management Title Insurance Group, Inc., Phase I and Phase II environmental site assessments, ALTA survey updates, and organizational document deliveries across five states. The involvement of multiple third-party vendors, coupled with loan document negotiation between our firm and Ashworth McPhail LLP (counsel to Clarendon Metropolitan), introduces meaningful risk that the target closing date may slip.

The Bridge Credit Agreement provides for one (1) extension of the initial maturity date by six (6) months, from December 31, 2025 to June 30, 2026. However, this extension is not automatic. It is subject to the satisfaction of four conditions precedent at the time of the extension: (a) no Event of Default or incipient Event of Default; (b) portfolio loan-to-value ("LTV") not exceeding 65%; (c) portfolio debt service coverage ratio ("DSCR") of at least 1.20x; and (d) payment of a 25 basis point extension fee on outstanding principal.

The most significant risk to exercising the extension option is the DSCR condition. The extension DSCR threshold of 1.20x is notably higher than the ongoing portfolio DSCR covenant of 1.10x that governs the initial term. The current portfolio DSCR stands at approximately 1.169x, which comfortably satisfies the ongoing 1.10x covenant but falls approximately 0.031x below the 1.20x extension threshold. At current net operating income ("NOI") and interest rate levels, Fairwater cannot satisfy this condition without either (i) achieving approximately $690,400 in additional annual NOI (a 2.64% increase) or (ii) making a voluntary partial prepayment of approximately $6.2 million to reduce the debt service denominator.

The remaining three conditions are expected to be satisfiable. The no-default condition presents low risk given Fairwater's current compliance posture. The LTV condition provides approximately 2.66 percentage points of headroom (current LTV of 62.34% vs. the 65% threshold), and the extension fee of $600,000 at full draw is a manageable financial cost.

Based on our analysis, we recommend the following courses of action:

1. Monitor NOI Growth Trajectory Monthly. Request monthly NOI reports from Fairwater Residential Management LLC and Naomi T. Sinclair (Fairwater's Chief Financial Officer) to track portfolio NOI performance against the $26,870,400 threshold needed to satisfy the 1.20x DSCR at current outstanding principal and interest rate levels.

2. Model Scenarios for Partial Voluntary Prepayment. Develop detailed financial models analyzing the impact of a partial voluntary prepayment of approximately $6.2 million on the DSCR, LTV, and minimum liquidity covenant, and confirm that the Bridge Credit Agreement permits such prepayment without premium or penalty.

3. Begin Early Coordination with Kensington National Bank, N.A. If, by mid-October 2025, the Permanent Loan closing appears likely to be delayed past the bridge maturity date, we recommend proactive outreach to Thomas J. Pagano, Managing Director, Real Estate Finance, at Kensington National Bank, to signal the potential exercise of the extension option and preserve relationship goodwill.

The sections that follow provide a detailed background, condition-by-condition analysis, sensitivity modeling, and a comprehensive set of recommendations for contingency planning.

II. Background

A. The Bridge Credit Facility

On June 30, 2025, Fairwater Operating Partnership, L.P. (the "Borrower"), a Delaware limited partnership, entered into the Bridge Credit Agreement with Kensington National Bank, N.A. ("KNB"), as administrative agent and lead lender, and a syndicate of lenders, providing for a $240,000,000 senior secured bridge credit facility (the "Bridge Facility"). The full recourse guaranty was provided by Fairwater Real Estate Investment Trust, a Maryland real estate investment trust (the "REIT" or "Fairwater").

The key terms and structural features of the Bridge Facility are summarized below:

Facility Amount and Structure. The Bridge Facility has an aggregate commitment of $240,000,000. The facility is structured as a single-draw, interest-only term loan with no scheduled amortization. The full $240,000,000 was drawn on the closing date of June 30, 2025, and the entire outstanding principal balance remains at $240,000,000 as of the date of this memorandum.

Administrative Agent. Kensington National Bank, N.A. serves as the administrative agent under the Bridge Credit Agreement. KNB's offices for purposes of the loan are located at 600 Lexington Avenue, New York, New York 10022. The primary relationship manager is Thomas J. Pagano, Managing Director, Real Estate Finance.

Lender's Counsel. Halcourt Briggs & Devlin LLP serves as counsel to the administrative agent and the lender syndicate. The lead partner on the engagement is Kenneth R. Delacroix, whose offices are located at 1221 Avenue of the Americas, New York, New York 10020.

Syndicate Composition. The $240,000,000 commitment is held by four lenders in the following proportions:

Interest Rate. The Bridge Facility bears interest at a floating rate equal to the Secured Overnight Financing Rate ("SOFR") plus 500 basis points, with a SOFR floor of 3.00%. The applicable SOFR benchmark is 30-day Term SOFR. As of August 11, 2025, 30-day Term SOFR was quoted at 4.33%, resulting in an all-in interest rate of 9.33% (4.33% + 5.00%). At this rate, the monthly interest cost on $240,000,000 of outstanding principal is approximately $1,866,000, and the annualized interest expense is approximately $22,392,000.

Default Rate. Upon the occurrence and during the continuance of an Event of Default, interest accrues at the default rate, which is 200 basis points above the otherwise-applicable rate — i.e., SOFR + 700 basis points. At current SOFR levels, the default rate would be approximately 11.33%, producing annualized interest of approximately $27,192,000 and monthly interest of approximately $2,266,000.

Maturity. The initial maturity date of the Bridge Facility is December 31, 2025, reflecting a six-month term from the June 30, 2025 closing date. The Bridge Credit Agreement provides for one (1) extension option, as described in detail in Section III of this memorandum, which, if exercised and all conditions are satisfied, would extend the maturity date to June 30, 2026.

Collateral. The Bridge Facility is secured by the following collateral:

• First-priority mortgage liens on all 14 properties comprising the Sun Belt Portfolio (described in Section II.B below), recorded in each applicable county in Texas, Georgia, Florida, North Carolina, and Tennessee;

• Pledge of 100% of the equity interests in each of the 14 special-purpose entity subsidiaries that hold the portfolio properties;

• Assignment of all leases, rents, and profits from the portfolio properties; and

• Assignment of all property management agreements, including the master property management agreement with Fairwater Residential Management LLC.

Guaranty. The obligations of the Borrower under the Bridge Credit Agreement are guaranteed on a full recourse basis by Fairwater Real Estate Investment Trust. The guaranty covers all principal, interest, fees, costs, and expenses payable under the Bridge Credit Agreement and related loan documents.

Governing Law. The Bridge Credit Agreement and all related loan documents are governed by and construed in accordance with the laws of the State of New York, without regard to conflicts-of-law principles.

B. The Sun Belt Portfolio

The proceeds of the Bridge Facility were used, together with approximately $145,000,000 of equity capital, to finance Fairwater's acquisition of a portfolio of 14 multifamily residential communities located across the southeastern United States (the "Sun Belt Portfolio") from Meridian Sunstone Holdings LLC. The acquisition closed on June 30, 2025, at an aggregate purchase price of $385,000,000.

Portfolio Composition. The Sun Belt Portfolio comprises approximately 4,200 apartment units across 14 garden-style and mid-rise multifamily communities situated in five states. The geographic distribution is as follows:

Ownership Structure. Each of the 14 properties is held by a separate, single-purpose Delaware limited liability company (Fairwater Sun Belt I LLC through Fairwater Sun Belt XIV LLC), each of which is wholly owned by Fairwater Operating Partnership, L.P. This SPE structure was required by the Bridge Facility and will likewise be required by the Permanent Loan.

Financial Metrics at Acquisition. At the time of acquisition, the Sun Belt Portfolio had a trailing-twelve-month ("TTM") NOI of $26,180,000, resulting in an acquisition capitalization rate of 6.80% ($26,180,000 ÷ $385,000,000). The weighted average occupancy across the portfolio at acquisition was 93.7%. The portfolio was appraised at $385,000,000 as of the acquisition date.

Property Management. Following the acquisition, management of all 14 properties was transitioned to Fairwater Residential Management LLC, a Fairwater affiliate (EIN 52-2953810). The property management agreement became effective on July 1, 2025. Fairwater Residential Management LLC is responsible for leasing, maintenance, capital expenditure coordination, and financial reporting at the property level. The management agreement was assigned to KNB as collateral under the Bridge Facility.

C. The Permanent Take-Out Financing

The Bridge Facility was always intended to serve as interim financing pending the arrangement and closing of a permanent CMBS conduit loan. The permanent take-out financing has now progressed to the application stage and is summarized below.

Proposed Lender. Clarendon Metropolitan Insurance Company, a national CMBS conduit lender (NAIC No. 38921), has been identified as the permanent lender (the "Permanent Lender"). Clarendon Metropolitan's counsel for the transaction is Ashworth McPhail LLP, with lead partner Joanna C. Wexler.

Proposed Loan Terms. The proposed Permanent Loan has the following indicative terms:

• Loan Amount: $240,000,000

• Interest Rate: 6.25% fixed for the full term

• Term: 10 years

• Amortization: 30-year amortization schedule

• Monthly Payment (P&I): Approximately $1,477,846

• Annual Debt Service: Approximately $17,734,152

Transaction Timeline. The Permanent Loan process has reached the following milestones and is tracking to the following projected dates:

• Term sheet received: August 25, 2025

• Board of Trustees authorization: September 8, 2025

• Loan application and rate lock deposit submitted: September 15, 2025 (deposit amount: $2,400,000; reference number CL-CMBS-2025-09-0347)

• Target closing: November 28, 2025

Financial Advisor. Fairwater has engaged Beacon Ridge Capital Advisors LLC as financial advisor for the Permanent Loan process. The lead advisor is Dennis P. Nakamura, Partner.

D. Timeline Risk Assessment

The interval between the target Permanent Loan closing date (November 28, 2025) and the bridge maturity date (December 31, 2025) is 33 days. While this cushion is not insubstantial, it is important to evaluate whether it is sufficient in light of the complexity and scope of the closing deliverables required in a 14-property, five-state CMBS transaction.

Key Milestones. The following table summarizes the critical milestones between now and the target closing date, along with current target dates:

Potential Delay Factors. Based on our experience with multi-property CMBS transactions and the specific circumstances of this portfolio, we have identified the following potential sources of delay:

• Appraisals. Thornfield Appraisal Group LLC must complete independent FIRREA-compliant appraisals for all 14 properties across five states. Scheduling inspections, gathering comparable data, and finalizing reports for 14 properties is a labor-intensive process. Industry norms suggest an 8–12 week timeline for a portfolio of this size, meaning that appraisals initiated in September may not be finalized until late November or early December.

• Title Commitments. Marlowe Asset Management Title Insurance Group, Inc. must issue title commitments for all 14 properties. Title searches in five jurisdictions may reveal exceptions requiring clearance (e.g., mechanic's liens, tax liens, encroachments, easement issues), and the resolution process can be time-consuming.

• ALTA Surveys. Updated ALTA/NSPS land title surveys must be obtained for each property. Survey crews must be dispatched to all 14 locations, and any survey discrepancies must be resolved with the title company and the lender.

• Environmental Reports. Updated Phase I environmental site assessments (and Phase II assessments if recommended) must be completed for all 14 properties. Any recognized environmental conditions ("RECs") identified by the environmental consultant would require additional investigation, potentially delaying closing.

• Organizational Document Delivery. Clarendon Metropolitan will require full organizational document packages for the Borrower, the REIT guarantor, each of the 14 SPEs, and the property manager. Certificates of good standing, formation documents, operating agreements, authorizing resolutions, incumbency certificates, and related materials must be gathered across multiple jurisdictions (Delaware, Maryland, Texas, Georgia, Florida, North Carolina, and Tennessee).

• Lender Internal Credit Approval. Clarendon Metropolitan's internal credit committee must approve the final credit terms following receipt and review of all third-party reports. Committee scheduling delays are not uncommon.

• Loan Document Negotiation. Negotiation of the CMBS loan documents between Calderwood & Harkness LLP (on behalf of Fairwater) and Ashworth McPhail LLP (on behalf of Clarendon Metropolitan) is expected to involve multiple rounds of markup and discussion on issues including transfer restrictions, cash management provisions, reserves, insurance requirements, and special-purpose entity covenants.

Conclusion on Delay Risk. In our judgment, there is a meaningful — though not predominant — risk that one or more of the foregoing delay factors could cause the Permanent Loan closing to slip past December 31, 2025. If such a delay were to occur, the bridge extension would become the sole contractual mechanism available to Fairwater to avoid a maturity default. This is the core reason that a thorough contingency analysis of the extension option is necessary at this stage.

III. Extension Option — Detailed Analysis of Conditions

A. Overview of Extension Mechanics

The Bridge Credit Agreement provides for one (1) extension of the maturity date by six (6) months, from December 31, 2025 to June 30, 2026. This extension is not automatic and is at the election of the Borrower, subject to satisfaction of specified conditions.

To exercise the extension, the Borrower must deliver a written notice of extension to Kensington National Bank, N.A., in its capacity as administrative agent, no later than thirty (30) days prior to the initial maturity date — i.e., by no later than December 1, 2025. The notice must be accompanied by an officer's certificate certifying that all conditions to the extension have been satisfied (or, where applicable, will be satisfied on the effective date of the extension).

The extension is subject to the contemporaneous satisfaction of four conditions precedent at both the time the extension notice is delivered and the time the extension becomes effective (December 31, 2025):

(a) No Event of Default or incipient Event of Default;

(b) Portfolio LTV not exceeding 65%;

(c) Portfolio DSCR of at least 1.20x; and

(d) Payment of the extension fee (25 basis points on outstanding principal).

We analyze each condition in detail below.

B. Condition (a) — No Event of Default

Requirement. No Event of Default, and no event that with the giving of notice or lapse of time (or both) would constitute an Event of Default, may exist at the time the extension notice is delivered or at the time of the extension effective date. This is a standard "clean hands" condition found in virtually all extension provisions.

Current Status. As of the date of this memorandum, no known Events of Default exist under the Bridge Credit Agreement. The Borrower is current on all interest payments, which have been paid monthly since the initial interest payment date. All covenant compliance certificates required under the Bridge Credit Agreement have been delivered in a timely manner, and the most recent compliance certificate confirmed satisfaction of all applicable financial covenants.

Assessment. This condition is expected to be satisfied at the time of extension, assuming Fairwater continues to make timely interest payments and comply with all affirmative and negative covenants in the Bridge Credit Agreement during the intervening period. We note that the ongoing DSCR covenant of 1.10x is satisfied at the current DSCR of 1.169x, providing meaningful headroom against the ongoing (as distinct from the extension) DSCR requirement.

It bears emphasis that if the delay in the Permanent Loan closing is simply a timing delay — rather than a fundamental inability to close — the Bridge Facility would remain performing and this no-default condition should continue to be met. We nonetheless recommend continued monitoring of all covenant metrics through the extension decision date to identify any compliance issues as early as possible.

C. Condition (b) — Portfolio LTV ≤ 65%

Requirement. At the time of extension, the ratio of the aggregate outstanding principal balance of the Bridge Facility to the appraised value of the portfolio properties must not exceed 65%.

Current Calculation.

• Outstanding principal: $240,000,000

• Appraised portfolio value (as of acquisition): $385,000,000

• Current LTV: $240,000,000 ÷ $385,000,000 = 62.34%

Margin of Compliance. The current LTV of 62.34% provides approximately 2.66 percentage points of headroom below the 65% threshold. This translates to a meaningful cushion: the appraised portfolio value would need to decline to approximately $369,230,769 ($240,000,000 ÷ 0.65) — a decline of approximately $15,769,231, or approximately 4.10% from the current $385,000,000 appraised value — before this condition would be breached.

Assessment. Given the relatively recent acquisition date of June 30, 2025, the generally stable multifamily market conditions prevailing in the Sun Belt region, and the absence of any property-level distress indicators, we consider a portfolio value decline of greater than 4% within six months to be unlikely absent a significant and unforeseen macroeconomic or market disruption. Accordingly, this condition is expected to be satisfiable.

Note on Appraisal Methodology. We note that the Bridge Credit Agreement may require, as part of the extension process, either updated independent appraisals or a lender's determination of value (based on broker's price opinions or other methodology). If the Bridge Credit Agreement requires refreshed appraisals, the Borrower should be prepared to engage Thornfield Appraisal Group LLC (or another MAI-designated appraiser acceptable to the administrative agent) on an expedited basis. We recommend confirming the applicable valuation methodology for extension purposes in our review of the relevant Bridge Credit Agreement provisions.

D. Condition (c) — Portfolio DSCR ≥ 1.20x (Critical Condition)

Requirement. At the time of extension, the portfolio debt service coverage ratio must be at least 1.20x. This threshold is notably and deliberately higher than the ongoing portfolio DSCR covenant of 1.10x that applies during the initial term of the Bridge Facility. The elevated DSCR requirement for the extension reflects the lenders' desire for additional debt-service cushion in exchange for agreeing to extend the maturity of what is, by its nature, short-term bridge financing.

Current DSCR Calculation.

• Trailing-twelve-month portfolio NOI: $26,180,000

• Annual debt service (interest-only at 9.33%): $22,392,000

• Portfolio DSCR: $26,180,000 ÷ $22,392,000 = 1.169x

The current DSCR of 1.169x satisfies the ongoing 1.10x covenant with meaningful headroom but falls short of the 1.20x extension threshold by approximately 0.031x. This shortfall represents the most significant risk to Fairwater's ability to exercise the extension option.

We address this critical condition through three sub-analyses: (1) the NOI increase that would be required to cure the shortfall at current debt levels, (2) the partial prepayment that could be made to cure the shortfall at current NOI levels, and (3) the sensitivity of the DSCR to movements in SOFR.

D.1. Sensitivity Analysis — NOI Required to Meet 1.20x at Current Outstanding Principal

At the current outstanding principal of $240,000,000 and the current all-in interest rate of 9.33%, the annual debt service is $22,392,000. To achieve a DSCR of exactly 1.20x at this debt service level, the portfolio NOI would need to be:

$22,392,000 × 1.20 = $26,870,400

This represents a required increase from the current TTM NOI of $26,180,000:

• NOI shortfall: $26,870,400 − $26,180,000 = $690,400

• Required percentage NOI growth: $690,400 ÷ $26,180,000 = 2.64%

Discussion. The question is whether a 2.64% increase in portfolio NOI is achievable between now and December 2025. Several factors bear on this analysis:

Favorable factors:

• The portfolio's weighted average occupancy at acquisition was 93.7%. If Fairwater Residential Management LLC succeeds in increasing occupancy to 95–96% through its leasing initiatives, this would contribute incremental rental revenue.

• Post-acquisition rent increases, even modest ones (e.g., 2–3% on lease renewals), could contribute to NOI growth. Fairwater's management team has historically targeted 3–4% annual rent growth across its portfolio, and the Sun Belt markets in which the portfolio is located have demonstrated above-average rent growth in recent years.

• Fairwater Residential Management LLC may also achieve operating expense efficiencies as it integrates the portfolio under its management platform, including renegotiation of vendor contracts and implementation of utility expense pass-through programs.

Unfavorable factors:

• The TTM NOI figure is a trailing calculation. If the Bridge Credit Agreement defines "NOI" as trailing-twelve-month NOI, then the calculation period for purposes of the December 2025 extension would include months under the prior owner's (Meridian Sunstone Holdings LLC's) management, before Fairwater's operational improvements took effect. Post-acquisition improvements to occupancy, rents, and operating efficiencies that begin in July 2025 would not be fully reflected in a trailing-twelve-month calculation until July 2026.

• Seasonal factors may also play a role. Multifamily NOI in the Sun Belt can be influenced by seasonal leasing patterns, with typically stronger leasing activity in spring and summer months and softer activity in winter months.

Definitional Issue. A critical threshold question is how "NOI" is defined under the Bridge Credit Agreement for purposes of the DSCR calculation. The calculation methodology could be any of the following:

(i) Trailing twelve months of actual NOI;

(ii) Annualized most-recent-quarter NOI (i.e., last quarter's NOI × 4);

(iii) Annualized most-recent-month NOI (i.e., last month's NOI × 12); or

(iv) Some other methodology, potentially including addbacks for non-recurring expenses, capital expenditure reserves, or management fee adjustments.

If the Bridge Credit Agreement uses an annualized current-quarter or current-month methodology, post-acquisition operational improvements could be recognized more quickly, potentially enabling Fairwater to satisfy the 1.20x threshold by December 2025. If, however, the definition is strictly trailing twelve months, the path to achieving a 2.64% NOI increase by December 2025 is more challenging.

This definitional question is a high-priority action item for our team and is addressed further in Section V.B.2 below.

D.2. Sensitivity Analysis — Partial Prepayment to Achieve 1.20x DSCR at Current NOI

An alternative approach to satisfying the 1.20x DSCR condition is to reduce the outstanding principal of the Bridge Facility through a voluntary partial prepayment. By reducing the outstanding principal, the annual debt service (the denominator in the DSCR calculation) is reduced, thereby increasing the DSCR ratio without any change in NOI.

Required Calculations.

At current NOI of $26,180,000, the maximum annual debt service that would produce a 1.20x DSCR is:

$26,180,000 ÷ 1.20 = $21,816,667

At the current all-in interest rate of 9.33% (interest-only), the outstanding principal balance that would produce annual debt service of $21,816,667 is:

$21,816,667 ÷ 0.0933 = $233,832,975 (approximately)

The required partial prepayment to reduce the outstanding principal from $240,000,000 to $233,832,975 is therefore:

$240,000,000 − $233,832,975 = approximately $6,167,025

Prepayment Mechanics. We need to confirm that the Bridge Credit Agreement permits voluntary partial prepayment without premium or penalty. Bridge credit facilities typically permit voluntary prepayment, but there may be minimum prepayment increment requirements (e.g., minimum prepayment of $1,000,000 or in $500,000 increments) and advance notice requirements (e.g., 3–5 business days' prior written notice). We also need to confirm that prepaid amounts cannot be reborrowed (i.e., that the facility is not a revolving facility — which we understand to be the case, as the facility is structured as a term loan).

Source of Prepayment Funds. A partial prepayment of approximately $6.2 million could be funded from Fairwater's unrestricted cash or, if available, draws under Fairwater's existing revolving credit facility. However, we note that the Bridge Credit Agreement includes a minimum liquidity covenant requiring Fairwater to maintain at least $50,000,000 in unrestricted cash and cash equivalents (or available capacity under its revolving credit facility, to the extent included in the definition of "liquidity" under the Bridge Credit Agreement). Any prepayment must be sized and sourced to ensure continued compliance with this minimum liquidity requirement.

Impact on LTV. A reduction in the outstanding principal to approximately $233,833,000 would have a favorable secondary effect on the LTV condition: LTV would decline from 62.34% to approximately 60.74% ($233,833,000 ÷ $385,000,000), providing additional cushion below the 65% LTV extension threshold.

Combined Approach. We note that a combined approach — modest NOI growth plus a smaller partial prepayment — may also achieve the desired result. For example, if NOI grows by 1.3% (to approximately $26,520,000), the required prepayment to reach 1.20x would be reduced to approximately $3.1 million. This combined approach may be the most realistic path if NOI growth materializes but is insufficient on its own.

D.3. SOFR Movement Risk

The DSCR is sensitive to changes in the SOFR rate because the Bridge Facility bears interest at a floating rate (SOFR + 500 bps). An increase in SOFR increases the all-in interest rate, which increases annual debt service, which in turn decreases the DSCR. Conversely, a decline in SOFR has a favorable impact on DSCR.

SOFR Sensitivity. Each 25 basis point movement in SOFR translates to the following impact on the Bridge Facility:

• Change in annual debt service: $240,000,000 × 0.0025 = $600,000

• At current NOI of $26,180,000, a 25 bps increase in SOFR reduces DSCR by approximately 0.030x

Illustrative Scenarios:

The table above demonstrates the significant sensitivity of the DSCR to SOFR movements. Notably, a 50 basis point decline in SOFR — to 3.83% — would bring the DSCR to 1.235x, above the 1.20x extension threshold, without any NOI improvement or prepayment. Conversely, a 50 basis point increase in SOFR would bring the DSCR dangerously close to the 1.10x ongoing covenant level.

We further note that the SOFR floor of 3.00% in the Bridge Credit Agreement means that if SOFR declines below 3.00%, the floor rate would apply, and no further DSCR benefit would accrue from additional SOFR declines. At the SOFR floor, the all-in rate would be 8.00% (3.00% + 5.00%), annual debt service would be $19,200,000, and the DSCR would be 1.364x — well above the 1.20x extension threshold. However, a decline in SOFR from 4.33% to 3.00% (133 basis points) within four months is not a base-case expectation under current monetary policy conditions.

Recommendation. We recommend close monitoring of the SOFR trajectory as an integral component of extension contingency planning. If the Federal Reserve signals or implements rate cuts before December 2025, this would directly benefit the DSCR calculation and may partially or wholly resolve the DSCR shortfall. Conversely, any indications of further rate increases would exacerbate the shortfall and increase the urgency of the partial prepayment strategy.

E. Condition (d) — Payment of Extension Fee

Requirement. The Borrower must pay a non-refundable extension fee equal to 25 basis points (0.25%) on the outstanding principal balance of the Bridge Facility at the time of extension.

Current Calculation.

• At full outstanding balance of $240,000,000: $240,000,000 × 0.0025 = $600,000

• If a partial prepayment of approximately $6.2 million is made prior to extension (reducing the outstanding balance to approximately $233,833,000): $233,833,000 × 0.0025 = approximately $584,583

The extension fee is payable to the administrative agent for the ratable benefit of the syndicate lenders. It is non-refundable upon payment and is earned by the lenders upon the effectiveness of the extension.

Assessment. This is a financial cost that Fairwater can absorb within its operating budget. It does not present a compliance or structural risk to the exercise of the extension option. We recommend that the fee be budgeted as a contingent liability and that Naomi T. Sinclair's finance team be advised of the amount.

IV. Additional Considerations

A. Interaction with Bridge Exit Fee

The Bridge Credit Agreement provides for an exit fee of 0.50% of the outstanding principal balance, payable upon repayment of the Bridge Facility. At the full $240,000,000 outstanding balance, this fee equals $1,200,000.

Importantly, however, the exit fee is subject to a waiver provision: the exit fee is waived if the Bridge Facility is repaid in full from the proceeds of a permanent CMBS financing within nine (9) months of the bridge closing date — i.e., by March 31, 2026 (nine months after June 30, 2025).

The interplay between the exit fee waiver and the extension timeline creates the following scenarios:

Scenario 1 — Permanent Loan closes on or before December 31, 2025 (no extension needed). The bridge is repaid within six months of closing. The exit fee is waived. Total incremental cost attributable to extension contingency: $0.

Scenario 2 — Extension exercised; Permanent Loan closes on or before March 31, 2026. The bridge is repaid within nine months of closing. The exit fee is waived. Total incremental cost attributable to extension: $600,000 (extension fee) + incremental interest carry during the extension period (approximately $388,154/month of delay × number of months).

Scenario 3 — Extension exercised; Permanent Loan closes between April 1, 2026 and June 30, 2026. The bridge is repaid after the nine-month exit fee waiver period. The exit fee of $1,200,000 (or proportionally less if partial prepayment reduces the outstanding balance) is payable. Total incremental cost attributable to extension: $600,000 (extension fee) + $1,200,000 (exit fee) + incremental interest carry for the full extension period.

The maximum incremental fee exposure in the extension scenario is therefore $600,000 + $1,200,000 = $1,800,000 in extension and exit fees, plus interest carry differential as discussed in the following section.

B. Continued Accrual of Bridge Interest vs. Permanent Loan Economics

Each month of delay in transitioning from the Bridge Facility to the Permanent Loan imposes a quantifiable economic cost on Fairwater, measured as the differential between the bridge interest cost and the permanent loan debt service.

Monthly Cost Comparison.

Monthly Cost of Delay. Each month of delayed closing costs Fairwater approximately $388,154 in excess interest expense relative to what would be payable under the Permanent Loan.

It should be noted that this comparison slightly understates the true economic cost of delay because the Permanent Loan includes amortization (i.e., a portion of each monthly payment reduces principal), whereas the Bridge Facility is interest-only. Thus, each month on the bridge not only costs more in absolute terms but also foregoes the principal reduction that would be occurring under the Permanent Loan's 30-year amortization schedule. The foregone monthly principal reduction under the Permanent Loan at inception would be approximately $228,154 per month (the difference between the $1,477,846 total P&I payment and approximately $1,250,000 in monthly interest at 6.25% on $240,000,000).

Aggregate Cost Over Full Extension Period. Over a potential six-month extension period (January through June 2026), the aggregate interest cost differential would total approximately $2,328,924 ($388,154 × 6 months). When combined with the extension fee and potential exit fee, the maximum total incremental cost of a full six-month extension is substantial, as quantified in Appendix D.

C. Impact on Financial Covenants During Extension Period

During any extension period, the Bridge Credit Agreement's entity-level financial covenants would continue to apply in full. Based on our review, these covenants include:

• Consolidated Leverage Ratio: Not to exceed 65%

• Fixed Charge Coverage Ratio ("FCCR"): Not less than 1.50x

• Tangible Net Worth: Not less than $750,000,000

• Minimum Liquidity: Not less than $50,000,000 in unrestricted cash and cash equivalents

Several interactions between the extension contingency and these covenants merit attention:

Minimum Liquidity. If Fairwater elects to make a partial voluntary prepayment of approximately $6.2 million to cure the DSCR shortfall, this payment would reduce Fairwater's unrestricted cash position. We need to verify that, after giving effect to any such prepayment, Fairwater would continue to maintain at least $50,000,000 in unrestricted cash and cash equivalents (or such other liquidity metric as may be defined in the Bridge Credit Agreement). This requires coordination with Naomi T. Sinclair to confirm Fairwater's projected unrestricted cash balance at the time of any contemplated prepayment.

Fixed Charge Coverage Ratio. Continued carrying of bridge-rate debt (at 9.33% rather than 6.25%) increases Fairwater's consolidated interest expense, which could impact the FCCR over time. If the extension period extends through the first half of 2026, the incremental interest expense of approximately $2.3 million could have a modestly adverse effect on the FCCR. We recommend that the finance team model the FCCR impact under extension scenarios.

Consolidated Leverage Ratio. To the extent that the continued carrying of bridge debt at higher interest rates reduces Fairwater's net income and retained earnings, there could be a secondary effect on Fairwater's equity base and thus its leverage ratio. However, this effect is expected to be modest in the context of Fairwater's overall balance sheet.

D. Lender Relationship and Consent Considerations

Kensington National Bank, through Thomas J. Pagano, and the syndicate lenders (Pinnacle Trust Company, Greystone Commerce Bank, and Redfield Capital Markets, LLC) have an existing and constructive relationship with Fairwater. Early and transparent communication about any delay risk is strongly recommended to preserve this relationship and to facilitate a smooth extension process if one becomes necessary.

We emphasize that the extension is a contractual right of the Borrower under the Bridge Credit Agreement. Assuming all four conditions are satisfied, the extension does not require the consent, approval, or vote of any lender. The administrative agent's role is ministerial — to confirm that the conditions have been met and to give effect to the extension upon receipt of a compliant extension notice.

However, if one or more conditions cannot be satisfied — most notably the 1.20x DSCR condition — the Borrower would need to negotiate a waiver of the unsatisfied condition or an amendment to the Bridge Credit Agreement modifying the condition. Any such waiver or amendment would require the consent of the "Requisite Lenders" under the Bridge Credit Agreement, which we expect to be defined as lenders holding a majority (more than 50%) or possibly two-thirds of the outstanding commitments. Given KNB's 40% share, the consent of at least one additional lender would be required in all cases.

Negotiating a waiver or amendment would involve additional legal fees, potential modification fees to the lenders, and the risk that the lenders may impose additional conditions or modified terms (e.g., a higher extension fee, a principal paydown requirement, or a tighter covenant package). The timeline for negotiating and documenting a waiver or amendment is also a consideration, particularly given the December 1, 2025 extension notice deadline.

For these reasons, it is far preferable to satisfy the extension conditions as stated rather than to rely on lender consent for a waiver or amendment.

E. Coordination with Fairwater's Other Indebtedness

Fairwater carries approximately $1,480,000,000 in consolidated indebtedness exclusive of the Bridge Facility. This indebtedness includes Fairwater's unsecured revolving credit facility, one or more unsecured term loans, and secured mortgage indebtedness on other portfolio properties. Virtually all of Fairwater's credit facilities contain cross-default provisions that provide for an Event of Default under each such facility upon the occurrence of an uncured Event of Default under any other material indebtedness of Fairwater or its subsidiaries.

If Fairwater were unable to repay or extend the Bridge Facility by December 31, 2025, a maturity default would occur. The $240,000,000 Bridge Facility would almost certainly constitute "material indebtedness" under Fairwater's other credit facilities, triggering cross-default provisions across Fairwater's approximately $1.48 billion in other debt. The cascading effect of such cross-defaults could be catastrophic, potentially resulting in acceleration of multiple facilities, enforcement of remedies by multiple lender groups, and severe disruption to Fairwater's operations, credit standing, and access to capital markets.

This cascading-default risk underscores the critical importance of either (i) closing the Permanent Loan or (ii) successfully exercising the bridge extension before December 31, 2025. A maturity default on the Bridge Facility must be avoided.

V. Recommendations

A. Primary Strategy — Expedite Permanent Loan Closing

The primary strategy remains — and should remain — to close the Permanent Loan with Clarendon Metropolitan Insurance Company on or before November 28, 2025, well in advance of the December 31, 2025 bridge maturity date. The extension option is and should be treated as a contingency measure, not a preferred outcome.

To maximize the likelihood of a timely closing, we recommend the following:

• Proactive management of third-party deliverable timelines. Fairwater's internal team and Beacon Ridge Capital Advisors LLC (Dennis P. Nakamura) should maintain a detailed tracking schedule for all third-party deliverables, including appraisals (Thornfield Appraisal Group LLC), title commitments (Marlowe Asset Management Title Insurance Group, Inc.), ALTA surveys, environmental reports, and organizational documents. Weekly status calls with all vendors should be instituted no later than September 15, 2025.

• Aggressive document negotiation schedule. We recommend circulating Fairwater's initial comments on the Clarendon Metropolitan loan documents within five business days of receipt from Ashworth McPhail LLP, and pressing for weekly negotiation calls thereafter to resolve open issues on an expedited basis. Early identification and resolution of "hot button" issues (transfer restrictions, cash management triggers, reserve requirements) will be essential to avoiding last-minute delays.

• Escalation protocol. Any emerging delay risk — whether attributable to third-party deliverables, lender credit committee timing, or document negotiation — should be escalated immediately to Philip Hartmann, David A. Whitfield, and Dennis P. Nakamura for assessment and remediation.

• Weekly monitoring. The deal team should assess the probability of a timely closing on a weekly basis beginning in October 2025, with the assessment communicated to all stakeholders.

B. Extension Contingency Preparations

In parallel with the primary strategy of expediting the Permanent Loan closing, we recommend the following extension contingency preparations: