1039-00003 · Torchlight Mining Corp · Remediation Schedules & Work Plans
consolidated-remediation-milestone-matrix.xlsx DOCUMENT Antitrust
60 / 75 ← → ✕
Contract analysis Extract to table

[sheet: Summary]

FieldValue
Document TitleConsolidated Remediation Milestone Matrix — All Four Sites
Prepared ByCalderwood & Harkness LLP (Matter No. 1039-00003)
DateFebruary 20, 2025
ClientTorchlight Mining Corp. (TSX/NYSE: TRC)
Case CaptionUnited States of America and State of Montana v. Torchlight Mining Corp. et al.
Civil Action No.9:24-cv-00087-DWM
CourtU.S. District Court for the District of Montana, Missoula Division
JudgeHon. Donald W. Molloy (Senior Judge)
Consent Decree Execution DateFebruary 19, 2025
Expected Entry DateMay 15, 2025
Effective Date (30 days post-entry)June 14, 2025
Environmental ConsultantPinnacle Creek Environmental, LLC (Dr. Astrid Bergmann, P.E.)
Independent MonitorVerdant Analytics, Inc. (Dr. Kamal Osei)
Financial Assurance Provider — SuretyIronbark Surety of America, Inc. (Bond No. ISA-ENV-2025-08934)
Financial Assurance Provider — TrustLarchfield Trust Company, N.A. (Trust No. LTC-REM-2025-1177)

AGGREGATE FINANCIAL SUMMARY

Ridgecrest Remediation (Nominal)$198,600,000
Gallatin Remediation (Nominal)$42,800,000
Bonanza Creek Remediation (Nominal)$63,200,000
Kanawha Bend Remediation (Nominal)$38,900,000
Total Remediation (Nominal)$343,500,000
Ridgecrest Remediation (NPV @ 3%)$134,900,000
Gallatin Remediation (NPV @ 3%)$34,100,000
Bonanza Creek Remediation (NPV @ 3%)$47,100,000
Kanawha Bend Remediation (NPV @ 3%)$29,000,000
Total Remediation (NPV @ 3%)$245,100,000
Civil Penalties (all sites)$31,500,000
EPA Past-Costs Reimbursement (CERCLA § 107)$18,100,000
Supplemental Environmental Projects (SEPs)$12,000,000
Independent Monitor Costs (5 yr est.)$4,800,000
Grand Total (Nominal)$409,900,000
Grand Total (NPV/Cash Equivalent)$311,500,000
Financial Assurance — Surety Bond$165,000,000
Financial Assurance — Remediation Trust Fund$80,000,000
Financial Assurance — Total$245,000,000
Surety Bond Annual Premium (1.85%)$3,052,500
TMC Environmental Reserve (Q3 2024)C$340.0M (≈ US$251.4M at 0.7394 FX)
Shortfall vs. Nominal ObligationUS$158,500,000

[sheet: Site Overview]

Site IDSite NameLocation / AddressStateEPA RegionOperating EntityEIN / State IDSite Area — Mine Footprint (acres)Site Area — Total Controlled (acres)Operational SinceCurrent StatusEPA DesignationPermit / Docket No.Applicable StatutesPrincipal ContaminantsKey Violations SummaryEPA Past Costs (CERCLA § 107) ($M)TMC Estimated Remediation (Nominal $M)EPA Estimated Remediation (Nominal $M)Negotiated/Agreed Remediation (Nominal $M)Remediation Duration (years)NPV discount Rate (%)NPV FactorRemediation NPV ($M)Civil Penalty ($M)SEP Allocation ($M)SEP DescriptionState Co-PlaintiffState Lead CounselTMC Local CounselEPA Project Coordinator
SITE-1Ridgecrest Copper-Molybdenum Mine14200 Ridgecrest Mine Road, Drummond, Granite County, MT 59832MontanaRegion 8Ridgecrest Mine Holdings, LLC (wholly owned by Torchlight Mining (U.S.) Inc.)MT SOS ID: E1042738320087001978Closure/Reclamation (active mining ceased Dec. 31, 2019)Proposed NPL listing (CERCLA); AOC Docket No. CERCLA-08-2022-0039 (executed Sept. 15, 2022)CERCLA-08-2022-0039CWA § 301; RCRA § 3004; CERCLA § 107acid mine drainage — dissolved Cu (47 mg/L vs. 0.0087 mg/L std.); Mo (1.2 mg/L); Se (0.082 mg/L); sulfate (3,400 mg/L); tailings impoundment seepage (425 acres) to Flint CreekUnpermitted discharges; mismanagement of hazardous waste from SX/EW circuit; EPA removal action cost recovery ($14.3M, 2021–2023)14.3187.5224198.63030.6795134.914.25.5Flint Creek Watershed Restoration Project — stream-bank stabilization, riparian replanting, fish-passage improvements along 12 miles of Flint CreekState of Montana, Dept. of Environmental Quality (MT DEQ)Annika Hedstrom, Asst. Attorney General, Montana AG's OfficeHolcroft, Dane & Weiss LLP (Russell Dane)Dr. Samuel Tesfaye (EPA Region 8)
SITE-2Gallatin Chemical Works8800 Industrial Park Lane, Belgrade, Gallatin County, MT 59714MontanaRegion 8Torchlight Specialty Chemicals, Inc. (wholly owned by TM(US))EIN: 47-38192041451451993Active operationsRCRA Corrective Action facilityMTD098712456RCRA §§ 3004, 3005; CWA § 301CS₂ in groundwater (890 µg/L vs. MCL 10 µg/L); xanthate decomposition products; VOCs (toluene, xylene) in subsurface soils; 3 SWMUsUnpermitted hazardous-waste storage; failure to perform corrective action; 14 MPDES permit exceedances (CS₂, TSS) Jan. 2021–June 2024042.842.842.81530.796934.15.80N/A (SEP allocated to Ridgecrest — Flint Creek)State of Montana, Dept. of Environmental Quality (MT DEQ)Annika Hedstrom, Asst. Attorney General, Montana AG's OfficeHolcroft, Dane & Weiss LLP (Russell Dane)N/A
SITE-3Bonanza Creek Gold MineCounty Road 447, Mile Marker 12, Lander County, NV 89820NevadaRegion 9Bonanza Creek Mining, LLC (wholly owned by TM(US))NV SOS Entity No.: E05182947315600124002001Active mining ongoingRCRA Corrective Action / CWA enforcementN/ACWA § 301; RCRA § 3004; Migratory Bird Treaty ActWAD cyanide (0.62 mg/L vs. 0.022 mg/L limit); Hg (12.4 µg/L vs. 0.77 µg/L criterion); Se in pit-lake water3 unpermitted discharges from heap-leach pad via torn liner (Mar. 2022, Aug. 2022, Jan. 2023); spent heap-leach ore as hazardous waste; 17 avian mortalities (2021–2023)063.263.263.22030.745447.17.93.5Battle Mountain Community Drinking Water Improvement Project — upgrade of municipal water treatment facilityState of Nevada, Division of Environmental Protection (NV DEP)Ricardo Fuentes, Deputy Attorney General, Nevada AG's OfficeSagebrush Law Group, PLLC (Denise Quartaro)Jennifer Whitfield (EPA Region 9)
SITE-4Kanawha Bend Chemical Plant2200 Chemical Valley Road, Institute, Kanawha County, WV 25112West VirginiaRegion 3Torchlight Specialty Chemicals, Inc. (wholly owned by TM(US))EIN: 47-381920478781985Active operationsRCRA Corrective Action facilityWVD048823915RCRA §§ 3004, 3005; CERCLA § 107H₂SO₄ residuals (pH 1.8); Pb (4,200 mg/kg); As (890 mg/kg); DNAPL (chlorinated solvents) in fractured bedrock aquiferFailure to close former surface impoundment; unpermitted treatment of listed wastes (K062, D002); EPA emergency response cost recovery ($3.8M, 2020)3.838.938.938.92030.7454293.63Institute Community Air Quality Monitoring Network — 6 monitoring stations, 10-year operationState of West Virginia, Dept. of Environmental Protection (WV DEP)Loretta May Hatcher, Asst. Attorney General, West Virginia AG's OfficeBaxter, Tully & Crane PLLC (Nathan Tully)N/A
TOTALAll Four Sites90232132318.1332.4368.9343.5245.131.512

[sheet: Ridgecrest Milestones]

Milestone IDPhaseMilestone DescriptionConsent Decree Section ReferenceDeadline / Target DateResponsible PartyResponsible TMC ContactRegulatory OversightEstimated Cost Allocation ($M)Deliverable / SubmissionPredecessor MilestoneStatusNotes
RC-001Pre-Construction / PlanningConsent Decree Effective Date§ IVJune 14, 2025All PartiesMiriam Soo-Hwan ParkEPA Region 8 / Dr. Samuel Tesfaye0N/AN/APending30 days after entry (target entry May 15, 2025)
RC-002Financial AssuranceEstablish Remediation Trust Fund and post financial assurance ($245.0M total — Ridgecrest allocated portion)§ XIISeptember 12, 2025TMC / Ironbark Surety / Larchfield TrustCarolyn Bracebridge (CFO)EPA OECA / Margaret Coulson0Surety Bond (ISA-ENV-2025-08934); Trust Agreement (LTC-REM-2025-1177)RC-001PendingSurety bond $165.0M + Trust $80.0M = $245.0M total for all sites
RC-003Pre-Construction / PlanningSubmit Ridgecrest Remedial Action Work Plan§ VII.ADecember 14, 2025TMC / Pinnacle Creek EnvironmentalGareth Linford (VP EHS)EPA Region 8 / Dr. Samuel Tesfaye2.5Final Remedial Action Work PlanRC-001PendingFramework and outline prepared Feb. 10, 2025; negotiated remediation cost: $198.6M over 30 years
RC-004Pre-Construction / PlanningEPA review and approval of Remedial Action Work Plan§ VII.AMarch 14, 2026EPA Region 8N/AEPA Region 8 / Dr. Samuel Tesfaye0EPA approval letterRC-003Pending90-day review period assumed
RC-005Pre-Construction / PlanningComplete remedial design (30% design submission)§ VII.BSeptember 14, 2026Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8530% Design PackageRC-004PendingAcid mine drainage treatment system, tailings impoundment stabilization
RC-006Pre-Construction / PlanningComplete remedial design (90% design submission)§ VII.BMarch 14, 2027Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8590% Design PackageRC-005Pending
RC-007Pre-Construction / PlanningComplete remedial design (100% final design)§ VII.BMay 14, 2027Pinnacle Creek EnvironmentalGareth LinfordEPA Region 82100% Final Design PackageRC-006PendingEPA final approval required prior to construction
RC-008ConstructionCommence Ridgecrest remedy construction§ VII.CJune 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics (monitor)15Notice of CommencementRC-007Pending
RC-009ConstructionComplete acid mine drainage treatment system installation — Phase 1§ VII.C.1June 14, 2029TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics35Construction completion report — Phase 1RC-008PendingActive water treatment for dissolved Cu, Mo, Se
RC-010ConstructionComplete tailings impoundment cap and cover system§ VII.C.2June 14, 2031TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics40Construction completion report — tailingsRC-008Pending425-acre tailings impoundment
RC-011ConstructionComplete Flint Creek seepage interception system§ VII.C.3June 14, 2032TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics20Construction completion report — seepageRC-009Pending
RC-012ConstructionComplete acid mine drainage treatment system — Phase 2 (passive treatment)§ VII.C.4June 14, 2033TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics8Construction completion report — Phase 2 acid mine drainageRC-009PendingTransition from active to semi-passive treatment
RC-013ConstructionComplete waste-rock repository re-grading and cover§ VII.C.5June 14, 2034TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics6.5Construction completion report — waste rockRC-008Pending
RC-014Long-Term O&MCommence long-term operation and maintenance (O&M)§ VII.DJune 14, 2032TMCGareth LinfordEPA Region 8 / Verdant Analytics5O&M Plan implementationRC-011PendingAnnual O&M costs estimated at ~$3.5M/yr for 23 years
RC-015Long-Term O&MAnnual O&M reporting — Year 1§ VII.DJune 14, 2033TMCGareth LinfordEPA Region 83.5Annual O&M ReportRC-014Pending
RC-016Long-Term O&MAnnual O&M reporting — Year 5§ VII.DJune 14, 2037TMCGareth LinfordEPA Region 83.5Annual O&M ReportRC-015Pending
RC-017Long-Term O&MAnnual O&M reporting — Year 10§ VII.DJune 14, 2042TMCGareth LinfordEPA Region 83.5Annual O&M ReportRC-016Pending
RC-018Long-Term O&MAnnual O&M reporting — Year 15§ VII.DJune 14, 2047TMCGareth LinfordEPA Region 83.5Annual O&M ReportRC-017Pending
RC-019Long-Term O&MAnnual O&M reporting — Year 20§ VII.DJune 14, 2052TMCGareth LinfordEPA Region 83.5Annual O&M ReportRC-018Pending
RC-020Long-Term O&MAnnual O&M reporting — Year 23 (final O&M year)§ VII.DJune 14, 2055TMCGareth LinfordEPA Region 83.5Annual O&M ReportRC-019PendingFinal year of O&M obligation
RC-021Monitoring5-Year Performance Review #1§ VII.EJune 14, 2037TMC / Verdant AnalyticsGareth LinfordEPA Region 80.55-Year Review ReportRC-014PendingEvaluate remedy effectiveness against performance standards
RC-022Monitoring5-Year Performance Review #2§ VII.EJune 14, 2042TMC / Verdant AnalyticsGareth LinfordEPA Region 80.55-Year Review ReportRC-021Pending
RC-023Monitoring5-Year Performance Review #3§ VII.EJune 14, 2047TMC / Verdant AnalyticsGareth LinfordEPA Region 80.55-Year Review ReportRC-022Pending
RC-024Monitoring5-Year Performance Review #4§ VII.EJune 14, 2052TMC / Verdant AnalyticsGareth LinfordEPA Region 80.55-Year Review ReportRC-023Pending
RC-025SEPFlint Creek Watershed Restoration Project — commence§ XI.ADecember 14, 2025TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / MT DEQ5.5SEP Commencement NoticeRC-001Pending12 miles of Flint Creek stream-bank stabilization, riparian replanting, fish-passage improvements
RC-026SEPFlint Creek Watershed Restoration Project — 50% completion§ XI.AJune 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / MT DEQ0SEP Progress ReportRC-025Pending
RC-027SEPFlint Creek Watershed Restoration Project — final completion and certification§ XI.AJune 14, 2029TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / MT DEQ0SEP Completion CertificationRC-026Pending
RC-028Completion / TerminationFinal remediation completion — submit certification of completion§ VII.FJune 14, 2055TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics0Certification of Completion reportRC-024PendingEnd of 30-year remediation obligation; termination no sooner than 5 years after completion of remedial construction
RC-029Completion / TerminationEarliest possible decree termination (Ridgecrest)§ XXIIJune 14, 2039TMCMiriam Soo-Hwan ParkEPA / Court0Motion for terminationRC-013 (+ 5 years)Pending5 years after completion of all remedial construction at Ridgecrest; subject to EPA and monitor certification
TOTAL172.1Remaining ~$26.5M allocated across annual O&M years not individually listed (23 yrs × ~$3.5M less amounts shown = balance to $198.6M)

[sheet: Gallatin Milestones]

Milestone IDPhaseMilestone DescriptionConsent Decree Section ReferenceDeadline / Target DateResponsible PartyResponsible TMC ContactRegulatory OversightEstimated Cost Allocation ($M)Deliverable / SubmissionPredecessor MilestoneStatusNotes
GL-001Pre-Construction / PlanningConsent Decree Effective Date§ IVJune 14, 2025All PartiesMiriam Soo-Hwan ParkEPA Region 80N/AN/APending
GL-002Investigation / StudySubmit Gallatin Corrective Measures Study§ VIII.AJune 14, 2026TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 82Corrective Measures Study ReportGL-001PendingAddresses 3 SWMUs, CS₂ groundwater contamination, VOC soil contamination; RCRA Permit No. MTD098712456
GL-003Investigation / StudyEPA review and selection of corrective measures§ VIII.ADecember 14, 2026EPA Region 8N/AEPA Region 80Statement of Basis / Final DecisionGL-002Pending
GL-004DesignSubmit corrective measures implementation work plan§ VIII.BJune 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 83CMS Implementation Work PlanGL-003Pending
GL-005DesignEPA approval of corrective measures implementation work plan§ VIII.BSeptember 14, 2027EPA Region 8N/AEPA Region 80EPA Approval LetterGL-004Pending90-day review period
GL-006ConstructionCommence corrective measures construction§ VIII.CDecember 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics8Notice of CommencementGL-005PendingCS₂ groundwater treatment, SWMU remediation
GL-007ConstructionComplete SWMU-1 and SWMU-2 soil remediation§ VIII.C.1June 14, 2029TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics6Construction completion report — SWMUs 1 & 2GL-006PendingExcavation and off-site disposal of contaminated soils
GL-008ConstructionComplete CS₂ groundwater treatment system installation§ VIII.C.2December 14, 2029TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics9Construction completion report — GW treatmentGL-006PendingAir stripping and activated carbon treatment
GL-009ConstructionComplete SWMU-3 remediation (former waste storage area)§ VIII.C.3June 14, 2030TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics3Construction completion report — SWMU-3GL-006Pending
GL-010Long-Term O&M / MonitoringCommence long-term groundwater monitoring and O&M§ VIII.DJanuary 14, 2030TMCGareth LinfordEPA Region 8 / Verdant Analytics2O&M Plan implementationGL-008PendingAnnual O&M ~$0.8M/yr for 10 years
GL-011Long-Term O&M / MonitoringAnnual O&M and groundwater monitoring report — Year 1§ VIII.DJanuary 14, 2031TMCGareth LinfordEPA Region 80.8Annual O&M/GW Monitoring ReportGL-010Pending
GL-012Long-Term O&M / MonitoringAnnual O&M and groundwater monitoring report — Year 3§ VIII.DJanuary 14, 2033TMCGareth LinfordEPA Region 80.8Annual O&M/GW Monitoring ReportGL-011Pending
GL-013Monitoring5-Year Performance Review #1§ VIII.EDecember 14, 2034TMC / Verdant AnalyticsGareth LinfordEPA Region 80.55-Year Review ReportGL-010Pending
GL-014Long-Term O&M / MonitoringAnnual O&M and groundwater monitoring report — Year 8§ VIII.DJanuary 14, 2038TMCGareth LinfordEPA Region 80.8Annual O&M/GW Monitoring ReportGL-013Pending
GL-015Monitoring5-Year Performance Review #2 (if required)§ VIII.EDecember 14, 2039TMC / Verdant AnalyticsGareth LinfordEPA Region 80.55-Year Review ReportGL-013PendingSubject to remedy performance
GL-016Completion / TerminationFinal remediation completion — submit certification of completion§ VIII.FJune 14, 2040TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 8 / Verdant Analytics0Certification of Completion reportGL-015PendingEnd of 15-year remediation obligation
GL-017Completion / TerminationEarliest possible decree termination (Gallatin)§ XXIIDecember 14, 2034TMCMiriam Soo-Hwan ParkEPA / Court0Motion for terminationGL-009 (+ 5 years)Pending5 years after completion of all remedial construction
TOTAL36.4Remaining ~$6.4M allocated across annual O&M years not individually listed (balance to $42.8M)

[sheet: Bonanza Creek Milestones]

Milestone IDPhaseMilestone DescriptionConsent Decree Section ReferenceDeadline / Target DateResponsible PartyResponsible TMC ContactRegulatory OversightEstimated Cost Allocation ($M)Deliverable / SubmissionPredecessor MilestoneStatusNotes
BC-001Pre-Construction / PlanningConsent Decree Effective Date§ IVJune 14, 2025All PartiesMiriam Soo-Hwan ParkEPA Region 9 / Jennifer Whitfield0N/AN/APending
BC-002Emergency / InterimCommence heap-leach pad liner repair and containment§ IX.AJune 14, 2026TMC / Bonanza Creek Mining, LLC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 9 / Jennifer Whitfield10Liner Repair and Containment Plan (SOW prepared Feb. 14, 2025)BC-001PendingAddresses 3 documented process-solution releases (Mar. 2022, Aug. 2022, Jan. 2023); torn liner; cyanide and mercury contamination
BC-003Emergency / InterimComplete emergency liner repair and process solution containment§ IX.ADecember 14, 2026TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 9 / Verdant Analytics8Completion report — emergency liner repairBC-002PendingWAD cyanide 0.62 mg/L vs. 0.022 mg/L limit
BC-004DesignSubmit Bonanza Creek Corrective Action Plan§ IX.BJune 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 93Corrective Action PlanBC-003PendingIncludes heap-leach pad long-term solution management, pit-lake selenium, avian mortality prevention (netting/hazing)
BC-005DesignEPA approval of Corrective Action Plan§ IX.BSeptember 14, 2027EPA Region 9N/AEPA Region 90EPA Approval LetterBC-004Pending90-day review period
BC-006ConstructionCommence full-scale remedy construction§ IX.CDecember 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 9 / Verdant Analytics12Notice of CommencementBC-005Pending
BC-007ConstructionComplete solution pond bird deterrent system§ IX.C.1June 14, 2028TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 92Installation completion reportBC-006PendingMBTA — 17 avian mortalities documented 2021–2023
BC-008ConstructionComplete pit-lake selenium treatment system§ IX.C.2December 14, 2029TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 9 / Verdant Analytics5Construction completion report — pit lakeBC-006Pending
BC-009ConstructionComplete heap-leach pad permanent liner replacement and containment upgrade§ IX.C.3June 14, 2030TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 9 / Verdant Analytics15Construction completion report — linerBC-006Pending
BC-010Long-Term O&M / MonitoringCommence long-term monitoring and O&M§ IX.DJuly 14, 2030TMCGareth LinfordEPA Region 9 / Verdant Analytics2O&M Plan implementationBC-009PendingAnnual O&M ~$0.4M/yr for 15 years
BC-011Long-Term O&M / MonitoringAnnual O&M and monitoring report — Year 1§ IX.DJuly 14, 2031TMCGareth LinfordEPA Region 90.4Annual O&M ReportBC-010Pending
BC-012Long-Term O&M / MonitoringAnnual O&M and monitoring report — Year 3§ IX.DJuly 14, 2033TMCGareth LinfordEPA Region 90.4Annual O&M ReportBC-011Pending
BC-013Monitoring5-Year Performance Review #1§ IX.EJune 14, 2035TMC / Verdant AnalyticsGareth LinfordEPA Region 90.55-Year Review ReportBC-010Pending
BC-014Long-Term O&M / MonitoringAnnual O&M and monitoring report — Year 8§ IX.DJuly 14, 2038TMCGareth LinfordEPA Region 90.4Annual O&M ReportBC-013Pending
BC-015Monitoring5-Year Performance Review #2§ IX.EJune 14, 2040TMC / Verdant AnalyticsGareth LinfordEPA Region 90.55-Year Review ReportBC-013Pending
BC-016Long-Term O&M / MonitoringAnnual O&M and monitoring report — Year 13§ IX.DJuly 14, 2043TMCGareth LinfordEPA Region 90.4Annual O&M ReportBC-015Pending
BC-017SEPBattle Mountain Drinking Water Project — commence§ XI.BMarch 14, 2026TMCGareth LinfordEPA Region 9 / NV DEP3.5SEP Commencement NoticeBC-001PendingUpgrade of municipal water treatment facility in Battle Mountain, Lander County, NV
BC-018SEPBattle Mountain Drinking Water Project — construction completion§ XI.BDecember 14, 2028TMCGareth LinfordEPA Region 9 / NV DEP0SEP Completion CertificationBC-017Pending
BC-019Completion / TerminationFinal remediation completion — submit certification of completion§ IX.FJune 14, 2045TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 9 / Verdant Analytics0Certification of Completion reportBC-015PendingEnd of 20-year remediation obligation
BC-020Completion / TerminationEarliest possible decree termination (Bonanza Creek)§ XXIIJune 14, 2035TMCMiriam Soo-Hwan ParkEPA / Court0Motion for terminationBC-009 (+ 5 years)Pending5 years after completion of all remedial construction
TOTAL63.1Allocations approximate $63.2M nominal total for Bonanza Creek

[sheet: Kanawha Bend Milestones]

Milestone IDPhaseMilestone DescriptionConsent Decree Section ReferenceDeadline / Target DateResponsible PartyResponsible TMC ContactRegulatory OversightEstimated Cost Allocation ($M)Deliverable / SubmissionPredecessor MilestoneStatusNotes
KB-001Pre-Construction / PlanningConsent Decree Effective Date§ IVJune 14, 2025All PartiesMiriam Soo-Hwan ParkEPA Region 30N/AN/APendingRCRA Permit No. WVD048823915
KB-002Interim StabilizationSubmit interim stabilization measures work plan§ X.ASeptember 14, 2025TMC / Torchlight Specialty Chemicals, Inc. / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 31Interim Stabilization Work Plan (SOW prepared Feb. 18, 2025)KB-001PendingAddresses H₂SO₄ residuals, heavy metals, DNAPL in fractured bedrock
KB-003Interim StabilizationCommence Kanawha Bend interim stabilization construction§ X.AMarch 14, 2026TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 3 / Verdant Analytics3Notice of Commencement — Interim MeasuresKB-002Pending
KB-004Interim StabilizationComplete Kanawha Bend interim stabilization measures§ X.ADecember 14, 2026TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 3 / Verdant Analytics5Interim Stabilization Completion ReportKB-003PendingSoil pH as low as 1.8; Pb max 4,200 mg/kg; As max 890 mg/kg
KB-005Investigation / StudySubmit RCRA Facility Investigation (RFI) report§ X.BJune 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 33RFI ReportKB-004PendingDNAPL characterization in fractured bedrock aquifer
KB-006Investigation / StudySubmit Corrective Measures Study (CMS)§ X.BDecember 14, 2027TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 32CMS ReportKB-005Pending
KB-007DesignEPA selection of remedy and issuance of Statement of Basis§ X.CJune 14, 2028EPA Region 3N/AEPA Region 30Statement of Basis / Final DecisionKB-006Pending
KB-008DesignSubmit Corrective Measures Implementation Work Plan§ X.CDecember 14, 2028TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 32CMI Work PlanKB-007PendingAddresses former waste lagoon closure, listed wastes K062, D002
KB-009ConstructionCommence corrective measures construction§ X.DJune 14, 2029TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 3 / Verdant Analytics10Notice of CommencementKB-008Pending
KB-010ConstructionComplete former surface impoundment closure§ X.D.1December 14, 2030TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 3 / Verdant Analytics5Closure certification reportKB-009Pending
KB-011ConstructionComplete DNAPL source-zone treatment§ X.D.2June 14, 2032TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 3 / Verdant Analytics4Treatment completion reportKB-009PendingFractured bedrock aquifer remediation
KB-012Long-Term O&M / MonitoringCommence long-term groundwater monitoring and O&M§ X.EJuly 14, 2032TMCGareth LinfordEPA Region 3 / Verdant Analytics1.5O&M Plan implementationKB-011PendingAnnual O&M ~$0.2M/yr for 13 years
KB-013Long-Term O&M / MonitoringAnnual O&M and groundwater monitoring report — Year 1§ X.EJuly 14, 2033TMCGareth LinfordEPA Region 30.2Annual O&M/GW Monitoring ReportKB-012Pending
KB-014Long-Term O&M / MonitoringAnnual O&M and groundwater monitoring report — Year 3§ X.EJuly 14, 2035TMCGareth LinfordEPA Region 30.2Annual O&M/GW Monitoring ReportKB-013Pending
KB-015Monitoring5-Year Performance Review #1§ X.FJune 14, 2037TMC / Verdant AnalyticsGareth LinfordEPA Region 30.55-Year Review ReportKB-012Pending
KB-016Long-Term O&M / MonitoringAnnual O&M and groundwater monitoring report — Year 8§ X.EJuly 14, 2040TMCGareth LinfordEPA Region 30.2Annual O&M/GW Monitoring ReportKB-015Pending
KB-017Monitoring5-Year Performance Review #2§ X.FJune 14, 2042TMC / Verdant AnalyticsGareth LinfordEPA Region 30.55-Year Review ReportKB-015Pending
KB-018SEPInstitute Community Air Quality Monitoring Network — station installation complete§ XI.CDecember 14, 2026TMCGareth LinfordEPA Region 3 / WV DEP3SEP Installation Completion ReportKB-001Pending6 ambient air quality monitoring stations in Institute/South Charleston area
KB-019SEPInstitute Community Air Quality Monitoring Network — end of 10-year monitoring period§ XI.CDecember 14, 2036TMCGareth LinfordEPA Region 3 / WV DEP0SEP Final ReportKB-018PendingQuarterly reporting throughout 10-year period
KB-020Completion / TerminationFinal remediation completion — submit certification of completion§ X.GJune 14, 2045TMC / Pinnacle Creek EnvironmentalGareth LinfordEPA Region 3 / Verdant Analytics0Certification of Completion reportKB-017PendingEnd of 20-year remediation obligation
KB-021Completion / TerminationEarliest possible decree termination (Kanawha Bend)§ XXIIJune 14, 2037TMCMiriam Soo-Hwan ParkEPA / Court0Motion for terminationKB-011 (+ 5 years)Pending5 years after completion of all remedial construction
TOTAL41.1Allocations approximate $38.9M nominal total for Kanawha Bend (SEP $3.0M accounted separately in SEP Schedule; balance reflects rounding across annual O&M)