Document TitleRidgecrest Copper-Molybdenum Mine — 30-Year Remediation Milestone Schedule
Date PreparedFebruary 10, 2025
Prepared ByCalderwood & Harkness LLP (Matter No. 1039-00003)
In Coordination WithPinnacle Creek Environmental, LLC (Dr. Astrid Bergmann, P.E.)
ClientTorchlight Mining Corp. (TSX: TRC / NYSE: TRC)
Operating EntityTorchlight Mining (U.S.) Inc. / Ridgecrest Mine Holdings, LLC (MT SOS ID: E1042738)
Site Address14200 Ridgecrest Mine Road, Drummond, Granite County, Montana 59832
Site Area~3,200 acres (mine footprint); ~8,700 acres (total controlled property)
Consent Decree ReferenceUnited States of America et al. v. Torchlight Mining Corp. et al., Civil Action No. 9:24-cv-00087-DWM, U.S. District Court for the District of Montana, Missoula Division
JudgeHon. Donald W. Molloy (Senior Judge)
Ridgecrest AOC Docket No.CERCLA-08-2022-0039
Negotiated Remediation Cost (Nominal)$198,600,000 over 30 years
NPV (3% discount Rate)$134,900,000 (NPV factor 0.6795)
TMC Estimate$187,500,000
EPA Estimate$224,000,000
Remedy Construction CommencementJune 14, 2027
End of Remediation ObligationJune 14, 2055 (30 years from Effective Date)
Effective Date of Consent DecreeJune 14, 2025 (30 days after expected entry date of May 15, 2025)
Financial Assurance (Total)$245,000,000 (Surety Bond $165.0M, Bond No. ISA-ENV-2025-08934, Ironbark Surety of America, Inc. + Remediation Trust $80.0M, Trust No. LTC-REM-2025-1177, Larchfield Trust Company, N.A.)
Independent MonitorVerdant Analytics, Inc. (Dr. Kamal Osei)
EPA Project CoordinatorDr. Samuel Tesfaye, EPA Region 8
Government Technical ExpertDr. Patricia Voss, Cascade Geosciences, Inc.
StatusDRAFT — Subject to final consent decree entry

[sheet: Key Dates Summary]

Milestone IDDateDescriptionConsent Decree SectionResponsible PartyStatus
PRE-011978-01-01Ridgecrest Mine begins operationsBackgroundTMCHistorical
PRE-022019-12-31Active mining ceases at RidgecrestBackgroundTMCComplete
PRE-032021-01-15EPA commences removal action at RidgecrestBackgroundEPAComplete
PRE-042022-09-15Ridgecrest AOC executed (Docket No. CERCLA-08-2022-0039)BackgroundTMC / EPAComplete
PRE-052023-05-30EPA completes Ridgecrest removal action ($14.3M total cost)BackgroundEPAComplete
PRE-062023-09-12EPA issues Notice of Violation (NOV) to TMCBackgroundEPAComplete
PRE-072024-01-18DOJ files complaint (Civil Action No. 9:24-cv-00087-DWM)BackgroundDOJComplete
PRE-082025-02-19Consent decree lodged with Court; 30-day public comment period begins§ IIIDOJ / TMCComplete
PRE-092025-03-21Public comment period closes§ IIICourtComplete
PRE-102025-04-28Court hearing on motion for entry of consent decree§ IIICourtPending
PRE-112025-05-15Expected entry of consent decree§ IIICourtPending
PRE-122025-06-14Effective Date (30 days after entry, per § IV)§ IV—Pending
PRE-132025-07-14First civil penalty installment due ($7.875M — Ridgecrest share: $3.55M)§ V.ATMCPending
PRE-142025-09-12Deadline to establish Remediation Trust Fund and post financial assurance ($245.0M total)§ VIIITMC / Ironbark / LarchfieldPending
PRE-152025-12-14Deadline to submit Ridgecrest Remedial Action Work Plan (final)§ VI.A.1TMC / Pinnacle CreekPending
PRE-162027-06-14Commencement of Ridgecrest remedy construction§ VI.A.3TMCPending
PRE-172055-06-14End of 30-year remediation obligation§ VI.A.12TMCPending

[sheet: 30-Year Milestone Schedule]

YearPeriod StartPeriod EndPhaseMilestone DescriptionConsent Decree SectionDeliverable / ActionResponsible PartyAnnual Cost Estimate ($M)Cumulative Cost Estimate ($M)5-Year BenchmarkVerification / Reporting
12027-06-142028-06-14Phase 1 — Construction & Active RemediationCommence remedy construction; mobilize AMD treatment system; begin tailings impoundment stabilization grading; install monitoring well network expansion§ VI.A.3Construction mobilization report; initial AMD treatment system design-build contract executionTMC / Pinnacle Creek18.518.55-Year Benchmark 1 (Years 1–5): Complete AMD treatment plant construction, tailings cap Phase 1, initial Flint Creek water quality improvement targetsQuarterly progress reports to EPA (Dr. Samuel Tesfaye); Verdant Analytics quarterly audit
22028-06-142029-06-14Phase 1 — Construction & Active RemediationContinue AMD treatment plant construction; commence tailings impoundment cap installation (Phase 1 — 106 acres); initiate Flint Creek diversion channel engineering§ VI.A.3AMD treatment plant 50% completion certificate; tailings cap Phase 1 design submittalTMC / Pinnacle Creek2240.5Quarterly progress reports; Verdant Analytics quarterly audit
32029-06-142030-06-14Phase 1 — Construction & Active RemediationComplete AMD treatment plant construction and commissioning; continue tailings cap Phase 1 installation; begin Flint Creek diversion channel construction§ VI.A.4AMD treatment plant commissioning report; performance testing (target: dissolved copper < 0.0087 mg/L in effluent)TMC / Pinnacle Creek2464.5Quarterly progress reports; Verdant Analytics quarterly audit; first annual Verdant public report
42030-06-142031-06-14Phase 1 — Construction & Active RemediationOperate AMD treatment plant at full capacity; complete tailings cap Phase 1 (106 acres); continue Flint Creek diversion channel; begin tailings cap Phase 2 design (106 acres)§ VI.A.4Tailings cap Phase 1 completion certification; Flint Creek diversion 50% completion reportTMC / Pinnacle Creek19.584Quarterly progress reports; Verdant Analytics quarterly audit
52031-06-142032-06-14Phase 1 — Construction & Active RemediationComplete Flint Creek diversion channel; commence tailings cap Phase 2 installation; AMD treatment plant operations and optimization; 5-Year Benchmark 1 compliance assessment§ VI.A.55-Year Performance Report; Flint Creek diversion completion certification; Benchmark 1 compliance documentation submitted to EPA and CourtTMC / Pinnacle Creek / Verdant Analytics16100BENCHMARK 1 ASSESSMENT: AMD treatment plant operational; tailings cap Phase 1 complete (106 acres); Flint Creek water quality — dissolved copper trending toward chronic aquatic life standard5-Year Benchmark Report to Court; Verdant Analytics annual public report; EPA review and determination
62032-06-142033-06-14Phase 2 — Extended Remediation & MonitoringContinue tailings cap Phase 2 (106 acres); AMD treatment plant O&M; begin design for tailings cap Phase 3 (106 acres); enhanced groundwater monitoring§ VI.A.6Tailings cap Phase 2 progress report; annual groundwater monitoring reportTMC / Pinnacle Creek12.5112.55-Year Benchmark 2 (Years 6–10): Complete tailings cap Phases 2 & 3, achieve Flint Creek interim water quality targets, groundwater containment verificationQuarterly progress reports; Verdant Analytics quarterly audit
72033-06-142034-06-14Phase 2 — Extended Remediation & MonitoringComplete tailings cap Phase 2; commence tailings cap Phase 3 installation; continue AMD treatment; Flint Creek in-stream monitoring§ VI.A.6Tailings cap Phase 2 completion certification; Phase 3 construction mobilizationTMC / Pinnacle Creek11123.5Quarterly reports; Verdant audit
82034-06-142035-06-14Phase 2 — Extended Remediation & MonitoringContinue tailings cap Phase 3; AMD treatment plant O&M; begin evaluation of long-term AMD treatment optimization§ VI.A.6Phase 3 progress report; AMD treatment optimization studyTMC / Pinnacle Creek9.5133Quarterly reports; Verdant audit
92035-06-142036-06-14Phase 2 — Extended Remediation & MonitoringComplete tailings cap Phase 3 (total 318 acres capped of 425-acre impoundment); begin tailings cap Phase 4 design (107 acres — final phase)§ VI.A.7Phase 3 completion certification; Phase 4 design submittal; groundwater trend analysisTMC / Pinnacle Creek8.5141.5Quarterly reports; Verdant audit
102036-06-142037-06-14Phase 2 — Extended Remediation & MonitoringCommence tailings cap Phase 4; AMD treatment plant O&M; 5-Year Benchmark 2 compliance assessment§ VI.A.75-Year Performance Report; Benchmark 2 compliance documentation; tailings cap cumulative status reportTMC / Pinnacle Creek / Verdant Analytics8149.5BENCHMARK 2 ASSESSMENT: Tailings cap Phases 1–3 complete (318 acres); Phase 4 underway; Flint Creek interim targets met; groundwater plume contained5-Year Benchmark Report to Court; Verdant annual report; EPA determination
112037-06-142038-06-14Phase 3 — Long-Term O&M & MonitoringComplete tailings cap Phase 4 installation (107 acres); AMD treatment plant O&M; ongoing Flint Creek and groundwater monitoring§ VI.A.8Phase 4 progress report; annual monitoring reportTMC / Pinnacle Creek6.5156Quarterly reports; Verdant audit
122038-06-142039-06-14Phase 3 — Long-Term O&M & MonitoringComplete tailings cap Phase 4 (all 425 acres capped); AMD treatment O&M; site reclamation and revegetation monitoring§ VI.A.8Tailings cap Phase 4 completion certification; full cap integrity assessmentTMC / Pinnacle Creek5161Quarterly reports; Verdant audit
132039-06-142040-06-14Phase 3 — Long-Term O&M & MonitoringAMD treatment plant O&M; tailings cap maintenance; ecological restoration monitoring; groundwater trend verification§ VI.A.8Annual monitoring and maintenance report; ecological restoration progress reportTMC / Pinnacle Creek4.5165.5Quarterly reports; Verdant audit
142040-06-142041-06-14Phase 3 — Long-Term O&M & MonitoringContinued AMD treatment O&M; tailings cap inspections and repairs as needed; Flint Creek biological monitoring§ VI.A.8Annual monitoring report; biological assessment report for Flint CreekTMC / Pinnacle Creek3.5169Quarterly reports; Verdant audit
152041-06-142042-06-14Phase 3 — Long-Term O&M & MonitoringAMD treatment plant long-term O&M; tailings cap maintenance and inspections; Flint Creek and groundwater monitoring; 5-Year Benchmark 3 compliance assessment§ VI.A.85-Year Performance Report; Benchmark 3 compliance documentationTMC / Pinnacle Creek / Verdant Analytics2.5171.5BENCHMARK 3 ASSESSMENT: All tailings cap phases complete (425 acres); AMD treatment meeting effluent standards consistently; Flint Creek final water quality targets on track5-Year Benchmark Report to Court
162042-06-142043-06-14Phase 3 — Long-Term O&M & MonitoringAMD treatment O&M; routine tailings cap inspections; Flint Creek and groundwater monitoring; begin passive treatment feasibility evaluation§ VI.A.9Annual monitoring report; passive treatment feasibility study — Phase 1TMC / Pinnacle Creek3174.5Quarterly reports; Verdant audit
172043-06-142044-06-14Phase 3 — Long-Term O&M & MonitoringContinue AMD treatment O&M; passive treatment pilot study if warranted; tailings cap maintenance; environmental monitoring§ VI.A.9Annual monitoring report; passive treatment feasibility study — Phase 2TMC / Pinnacle Creek2.8177.3Quarterly reports; Verdant audit
182044-06-142045-06-14Phase 3 — Long-Term O&M & MonitoringAMD treatment O&M; tailings cap maintenance; Flint Creek biological and chemical monitoring; groundwater trend confirmation§ VI.A.9Annual monitoring report; groundwater trend analysis updateTMC / Pinnacle Creek2.7180Quarterly reports; Verdant audit
192045-06-142046-06-14Phase 3 — Long-Term O&M & MonitoringAMD treatment O&M; routine cap and infrastructure maintenance; monitoring well network assessment; comprehensive data review§ VI.A.9Annual monitoring report; monitoring well network optimization studyTMC / Pinnacle Creek2.5182.5Quarterly reports; Verdant audit
202046-06-142047-06-14Phase 3 — Long-Term O&M & MonitoringContinued O&M; monitoring well network assessment; possible transition to passive AMD treatment evaluation; 5-Year Benchmark 4 compliance assessment§ VI.A.95-Year Performance Report; Benchmark 4 compliance documentation; passive treatment feasibility studyTMC / Pinnacle Creek2.5185BENCHMARK 4 ASSESSMENT: Sustained compliance with all surface water and groundwater standards; evaluate passive treatment transition5-Year Benchmark Report to Court
212047-06-142048-06-14Phase 4 — Transition & Pre-TerminationContinue AMD treatment (active or passive per feasibility outcome); tailings cap maintenance; routine monitoring; initiate long-term stewardship planning§ VI.A.10Annual monitoring report; long-term stewardship plan — draftTMC / Pinnacle Creek21875-Year Benchmark 5 (Years 21–25): Sustained compliance; termination planning initiatedQuarterly reports; Verdant audit
222048-06-142049-06-14Phase 4 — Transition & Pre-TerminationContinued O&M; monitoring; institutional controls verification; long-term stewardship plan finalization§ VI.A.10Annual monitoring report; long-term stewardship plan — finalTMC / Pinnacle Creek1.9188.9Quarterly reports; Verdant audit
232049-06-142050-06-14Phase 4 — Transition & Pre-TerminationO&M continuation; cap integrity assessment; comprehensive environmental monitoring; termination readiness data compilation§ VI.A.10Annual monitoring report; cap integrity assessment reportTMC / Pinnacle Creek1.8190.7Quarterly reports; Verdant audit
242050-06-142051-06-14Phase 4 — Transition & Pre-TerminationO&M continuation; monitoring; begin assembling Certification of Completion documentation; pre-termination site assessment§ VI.A.10Annual monitoring report; pre-termination site assessment — draftTMC / Pinnacle Creek1.8192.5Quarterly reports; Verdant audit
252051-06-142052-06-14Phase 4 — Transition & Pre-TerminationContinue O&M; maintain tailings cap; comprehensive site-wide monitoring; 5-Year Benchmark 5 compliance assessment; begin preparation of termination petition package§ VI.A.105-Year Performance Report; Benchmark 5 compliance documentation; preliminary termination readiness assessmentTMC / Pinnacle Creek1.5194BENCHMARK 5 ASSESSMENT: All performance standards sustained; site conditions stable; initiate termination planning5-Year Benchmark Report to Court
262052-06-142053-06-14Phase 4 — Termination EligibilityO&M continuation; monitoring; finalize termination petition documentation; coordinate with EPA on Certification of Completion requirements§ VI.A.11Annual monitoring report; termination petition — draft for EPA reviewTMC / Pinnacle Creek1.1195.15-Year Benchmark 6 (Years 26–30): Certification of Completion; termination petitionQuarterly reports; Verdant audit
272053-06-142054-06-14Phase 4 — Termination EligibilityO&M continuation; monitoring; EPA review of draft termination materials; address EPA comments and information requests§ VI.A.11Annual monitoring report; revised termination petition packageTMC / Pinnacle Creek1196.1Quarterly reports; Verdant audit
282054-06-142055-06-14Phase 4 — Termination EligibilityO&M continuation; final confirmation monitoring; Verdant Analytics comprehensive final compliance assessment; submit formal termination petition to Court§ VI.A.12Formal termination petition filed; Verdant final compliance report — draftTMC / Pinnacle Creek / Verdant Analytics0.9197Quarterly reports; Verdant final compliance audit
292055-06-142056-06-14Phase 4 — Termination EligibilityFinal O&M activities; confirmation monitoring; Court review of termination petition; respond to Court and EPA inquiries§ VI.A.12 / § XIIAnnual monitoring report; supplemental information as requested by Court/EPATMC / Pinnacle Creek0.6197.6Quarterly reports; Verdant audit
302056-06-142057-06-14Phase 4 — Termination EligibilityFinal year of 30-year obligation; complete final monitoring cycle; prepare and submit Certification of Completion to EPA and Court; Verdant Analytics final compliance report; 5-Year Benchmark 6 (final)§ VI.A.12 / § XII (Termination)Certification of Completion application; final 5-Year Performance Report; termination petition (termination no sooner than 5 years after completion of all remedial construction)TMC / Pinnacle Creek / Verdant Analytics / EPA1198.6BENCHMARK 6 (FINAL): All remediation objectives achieved; Certification of Completion sought from EPA; Court approval of terminationFinal Verdant report; EPA Certification of Completion review

[sheet: 5-Year Benchmark Summary]

Benchmark #PeriodCalendar YearsPhaseKey Performance CriteriaTarget Water Quality MetricsTailings Cap StatusCost for Period ($M)Cumulative Cost ($M)NPV of Period Cost ($M, 3%)Consent Decree SectionReporting Requirements
1Years 1–5June 2027 – June 2032Phase 1 — Construction & Active RemediationAMD treatment plant operational; tailings cap Phase 1 complete; Flint Creek diversion channel completeDissolved copper in AMD effluent < 0.0087 mg/L; molybdenum < 0.5 mg/L; selenium < 0.005 mg/L; sulfate trending below 2,000 mg/LPhase 1 complete: 106 of 425 acres capped (25%)10010086.3§ VI.A.3–55-Year Benchmark Report; Verdant Analytics annual public reports; quarterly EPA progress reports
2Years 6–10June 2032 – June 2037Phase 2 — Extended Remediation & MonitoringTailings cap Phases 2–3 complete; Phase 4 commenced; Flint Creek interim targets met; groundwater plume containedFlint Creek in-stream dissolved copper < 0.05 mg/L (interim); groundwater monitoring well copper < 1.0 mg/L at compliance boundaryPhases 1–3 complete: 318 of 425 acres capped (75%); Phase 4 underway49.5149.536.9§ VI.A.6–75-Year Benchmark Report; Verdant reports
3Years 11–15June 2037 – June 2042Phase 3 — Long-Term O&M & MonitoringAll tailings cap phases complete (425 acres); AMD treatment sustained; Flint Creek final targets on trackFlint Creek dissolved copper approaching chronic standard 0.0087 mg/L; groundwater stable/declining trendsAll phases complete: 425 of 425 acres capped (100%)22171.514.2§ VI.A.85-Year Benchmark Report
4Years 16–20June 2042 – June 2047Phase 3 — Long-Term O&M & MonitoringSustained compliance; passive treatment feasibility evaluationAll water quality standards met consistentlyMaintenance and inspections only13.51857.5§ VI.A.95-Year Benchmark Report
5Years 21–25June 2047 – June 2052Phase 4 — Transition & Pre-TerminationSustained compliance; termination planning initiatedAll standards met; trending data confirms long-term stabilityMaintenance and inspections only91944.3§ VI.A.105-Year Benchmark Report; preliminary termination readiness assessment
6Years 26–30June 2052 – June 2057Phase 4 — Termination EligibilityCertification of Completion; termination petitionFinal confirmation of all performance standardsFinal cap integrity verification4.6198.61.9§ VI.A.12 / § XIIFinal 5-Year Report; Certification of Completion application
TOTALYears 1–30June 2027 – June 2057All Phases———198.6198.6151.1——

[sheet: Cost Allocation by Remedy Compo]

Remedy ComponentDescriptionNominal Cost ($M)% of TotalConstruction PeriodO&M PeriodConstruction Cost ($M)O&M Cost ($M)
AMD Treatment SystemDesign, construction, commissioning, and 30-year operation of active acid mine drainage treatment plant to reduce dissolved copper (from avg. 47 mg/L to < 0.0087 mg/L), molybdenum (from 1.2 mg/L to < 0.5 mg/L), selenium (from 0.082 mg/L to < 0.005 mg/L), and sulfate (from 3,400 mg/L to < 2,000 mg/L)72.436.5Years 1–3Years 4–303834.4
Tailings Impoundment CapEngineering, installation, and maintenance of engineered cap over 425-acre tailings impoundment in four phases (Phase 1: 106 ac, Phase 2: 106 ac, Phase 3: 106 ac, Phase 4: 107 ac) to eliminate seepage to Flint Creek58.229.3Years 1–10Years 11–304810.2
Flint Creek Water Quality RestorationDiversion channel construction, bank stabilization, and long-term in-stream monitoring along Flint Creek (note: separate from the $5.5M Flint Creek Watershed Restoration SEP)24.812.5Years 1–5Years 6–30168.8
Groundwater Monitoring & ContainmentMonitoring well network (existing + new wells), groundwater sampling (quarterly/semi-annual), plume delineation updates, and potential extraction/treatment if containment not achieved passively18.69.4Years 1–5 (installation)Years 1–30 (monitoring)513.6
RCRA Corrective Action (SX-EW Circuit)Investigation, closure, and remediation of hazardous waste from the solvent-extraction/electrowinning circuit, including soil removal and disposal126Years 1–4Years 5–109.52.5
Site Reclamation & Ecological RestorationGrading, topsoil placement, revegetation, habitat restoration of open-pit area and disturbed lands within the 3,200-acre mine footprint8.64.3Years 3–10Years 11–205.53.1
Project Management, Reporting & Regulatory ComplianceOverall project management by Pinnacle Creek Environmental, regulatory reporting, permit compliance, coordination with EPA Project Coordinator (Dr. Samuel Tesfaye) and independent monitor (Verdant Analytics)42Years 1–30Years 1–301.52.5
TOTALAll remedy components — Ridgecrest Copper-Molybdenum Mine198.6100——123.575.1

[sheet: Contaminant Targets]

ContaminantMediumBaseline ConcentrationApplicable Standard / TargetRegulatory BasisInterim Target (Year 5)Interim Target (Year 10)Final Target (Year 30)Monitoring Frequency
Dissolved CopperSurface Water (AMD discharge / Flint Creek)Avg. 47 mg/L0.0087 mg/L (Montana chronic aquatic life standard)CWA § 301 / Montana WQS< 0.0087 mg/L in AMD treatment effluent; < 0.05 mg/L in Flint Creek (interim)< 0.0087 mg/L in Flint Creek at downstream compliance pointSustained compliance with 0.0087 mg/L at all compliance pointsMonthly (AMD effluent); Quarterly (Flint Creek stations)
MolybdenumSurface WaterAvg. 1.2 mg/L0.5 mg/L (site-specific target per consent decree)Consent Decree § VI.A< 0.5 mg/L in AMD effluent< 0.5 mg/L sustained< 0.5 mg/L sustainedMonthly (AMD effluent)
SeleniumSurface WaterAvg. 0.082 mg/L0.005 mg/L (Montana WQS)CWA / Montana WQS< 0.02 mg/L (interim)< 0.005 mg/L< 0.005 mg/L sustainedMonthly (AMD effluent); Quarterly (Flint Creek)
SulfateSurface WaterAvg. 3,400 mg/L2,000 mg/L (interim); site-specific per consent decreeConsent Decree § VI.A< 2,500 mg/L (interim)< 2,000 mg/L< 2,000 mg/L sustainedMonthly
Dissolved CopperGroundwater (monitoring wells)Varies (up to 85 mg/L at source area wells)Site-specific groundwater cleanup levels per consent decreeRCRA / CERCLAPlume contained; no expansion beyond current boundaryDeclining trends at all compliance wellsMeet groundwater cleanup levels at compliance boundaryQuarterly
ArsenicGroundwater (monitoring wells)Varies (up to 0.15 mg/L at source area wells)0.010 mg/L (MCL)SDWA / CERCLAPlume contained; concentrations declining at source< 0.050 mg/L at compliance boundary wells< 0.010 mg/L at compliance boundary wellsQuarterly
Hazardous Waste Residuals (SX-EW)Soil / WasteCharacterization per RCRA § 3004RCRA closure standards; land disposal restrictions metRCRA §§ 3004, 3005Waste removal 50% completeClosure certification obtainedPost-closure monitoring completeSemi-annual during closure; annual post-closure
Total Suspended Solids (TSS)Surface Water (Flint Creek)Avg. 120 mg/L during high-flow events30 mg/L (Montana WQS — 30-day average)CWA / Montana WQS< 80 mg/L (interim, post-diversion channel)< 30 mg/L at downstream compliance point< 30 mg/L sustainedQuarterly; event-based during high flow