[sheet: Cover & General Info]
Field | Value
Document Title | Exhibit C to EPC Agreement — Construction Schedule and Milestone Dates
Project Name | Stonebridge Data Center Campus
Project Location | NE corner of Belmont Ridge Road and Stonebridge Boulevard, Loudoun County, Virginia 20148
Owner | Stonebridge Campus Holdings LLC (a Virginia LLC, wholly owned by Ironhaven Data Centers LLC)
Contractor | Titan-McAllister Construction Group, LLC
Contractor Address | 7900 Harkins Road, Suite 100, Lanham, MD 20706
Contractor President | Raymond Okafor
Contractor SVP, Data Center Programs | Michelle Tran
EPC Agreement GMP | $412,000,000
Contract Type | Guaranteed Maximum Price (GMP)
Total Gross Floor Area | 480,000 sq ft (4 buildings × 120,000 sq ft each)
Total Critical IT Load Capacity | 96 MW (4 buildings × 24 MW each)
Total Construction Duration | 24 months from Notice to Proceed (NTP)
Notice to Proceed (NTP) Target Date | November 1, 2025
Substantial Completion — Building A | August 1, 2027
Substantial Completion — Buildings B, C, D | November 1, 2027
Liquidated Damages (Delay) | $125,000 per calendar day per building
LD Cap Per Building | $10,300,000 (10% of per-building GMP allocation of $103,000,000)
Owner's Representative | Kestrel Infrastructure Advisors, LLC (Diane Prescott, Engagement Lead)
Civil / Site Engineer | Lumen Ridge Engineering, PLLC (Carlos Esteban, PE, Project Principal)
Exhibit Effective Date | To be dated as of EPC Agreement Execution (target: October 20, 2025)
Draft Status | DRAFT — Subject to revision pending final NTP date confirmation
[sheet: Master Milestone Schedule]
Milestone ID | Milestone Description | Target Start Date | Target Completion Date | Duration (days or months) | Predecessor Milestone ID | Responsible Party | Notes / Conditions
M-001 | Notice to Proceed (NTP) Issued | November 1, 2025 | November 1, 2025 | 0 days | N/A | Owner / Stonebridge Campus Holdings LLC | Requires EPC Agreement execution (target Oct 20, 2025), construction loan closing (target Oct 15, 2025), and minimum equity contribution of $52,500,000
M-002 | Construction Mobilization & Site Preparation | November 1, 2025 | December 15, 2025 | 45 days | M-001 | Titan-McAllister Construction Group, LLC | Includes contractor mobilization, temporary facilities, erosion & sediment control installation
M-003 | Mass Grading and Earthwork — Full Campus | December 1, 2025 | March 15, 2026 | 105 days | M-002 | Titan-McAllister Construction Group, LLC | Geotechnical recommendations per Brannigan Geotechnical Engineering, LLC (Neil Brannigan, PE); civil design per Lumen Ridge Engineering, PLLC
M-004 | Underground Utilities — Stormwater, Water, Sewer, Ductbanks | January 15, 2026 | May 31, 2026 | 137 days | M-003 (partial) | Titan-McAllister Construction Group, LLC | Coordinates with Loudoun County stormwater management requirements and cross-access utility easements across Stonebridge Parcel (62.0 acres) and Meridian Parcel (19.4 acres)
M-005 | Foundations — Building A | March 1, 2026 | June 15, 2026 | 107 days | M-003 | Titan-McAllister Construction Group, LLC | Building A: ~120,000 sq ft shell, 24 MW critical IT load
M-006 | Foundations — Building B | April 1, 2026 | July 15, 2026 | 106 days | M-003 | Titan-McAllister Construction Group, LLC | Building B: ~120,000 sq ft shell, 24 MW critical IT load
M-007 | Foundations — Building C | May 1, 2026 | August 15, 2026 | 107 days | M-003 | Titan-McAllister Construction Group, LLC | Building C: ~120,000 sq ft shell, 24 MW critical IT load
M-008 | Foundations — Building D | June 1, 2026 | September 15, 2026 | 107 days | M-003 | Titan-McAllister Construction Group, LLC | Building D: ~120,000 sq ft shell, 24 MW critical IT load
M-009 | Central Utility Plant (CUP) — Foundations & Structural | April 1, 2026 | September 30, 2026 | 183 days | M-003 | Titan-McAllister Construction Group, LLC | Serves all four data center buildings
M-010 | Structural Steel & Building Envelope — Building A | June 15, 2026 | December 15, 2026 | 184 days | M-005 | Titan-McAllister Construction Group, LLC
M-011 | Structural Steel & Building Envelope — Building B | July 15, 2026 | January 15, 2027 | 184 days | M-006 | Titan-McAllister Construction Group, LLC
M-012 | Structural Steel & Building Envelope — Building C | August 15, 2026 | February 15, 2027 | 184 days | M-007 | Titan-McAllister Construction Group, LLC
M-013 | Structural Steel & Building Envelope — Building D | September 15, 2026 | March 15, 2027 | 182 days | M-008 | Titan-McAllister Construction Group, LLC
M-014 | Substation Construction — 230kV/34.5kV Dedicated Substation (VPC) | March 1, 2026 | June 1, 2027 | 15 months | M-003 | Vantage Power Cooperative (contractor) / IHDC funding ($18,500,000 line extension contribution) | Located on Meridian Parcel; substation owned by VPC post-construction; energization target June 1, 2027. Coordinates with VPC Service Application No. LSA-2025-0091
M-015 | Primary Electrical Distribution — Switchgear & MV Cabling | January 1, 2027 | May 31, 2027 | 151 days | M-014 (partial), M-010 | Titan-McAllister Construction Group, LLC | Part of $61,000,000 power infrastructure budget
M-016 | MEP Rough-In — Building A | December 15, 2026 | April 30, 2027 | 137 days | M-010 | Titan-McAllister Construction Group, LLC | Mechanical, electrical, plumbing systems
M-017 | MEP Rough-In — Building B | January 15, 2027 | May 31, 2027 | 136 days | M-011 | Titan-McAllister Construction Group, LLC
M-018 | MEP Rough-In — Building C | February 15, 2027 | June 30, 2027 | 135 days | M-012 | Titan-McAllister Construction Group, LLC
M-019 | MEP Rough-In — Building D | March 15, 2027 | July 31, 2027 | 139 days | M-013 | Titan-McAllister Construction Group, LLC
M-020 | Backup Generator Installation — Building A (2N Configuration) | February 1, 2027 | May 15, 2027 | 104 days | M-010 | Titan-McAllister Construction Group, LLC | 2N diesel generator configuration; procurement included in EPC GMP
M-021 | Backup Generator Installation — Building B (2N Configuration) | March 1, 2027 | June 15, 2027 | 107 days | M-011 | Titan-McAllister Construction Group, LLC | 2N diesel generator configuration
M-022 | Backup Generator Installation — Building C (2N Configuration) | April 1, 2027 | July 15, 2027 | 106 days | M-012 | Titan-McAllister Construction Group, LLC | 2N diesel generator configuration
M-023 | Backup Generator Installation — Building D (2N Configuration) | May 1, 2027 | August 15, 2027 | 107 days | M-013 | Titan-McAllister Construction Group, LLC | 2N diesel generator configuration
M-024 | CUP — MEP Fit-Out and Equipment Installation | October 1, 2026 | April 30, 2027 | 212 days | M-009 | Titan-McAllister Construction Group, LLC | Cooling plant, chiller systems, pumps
M-025 | Substation Energization | June 1, 2027 | June 1, 2027 | 0 days | M-014 | Vantage Power Cooperative | Triggers commencement of 10-year LLSA term; contracted demand: 120 MVA
M-026 | Structured Parking — Construction | June 1, 2026 | February 28, 2027 | 273 days | M-003 | Titan-McAllister Construction Group, LLC | Included in GMP scope
M-027 | Commissioning & Testing — Building A | May 1, 2027 | July 15, 2027 | 76 days | M-016, M-020, M-025 | Titan-McAllister Construction Group, LLC / Kestrel Infrastructure Advisors, LLC | Integrated systems testing including power, cooling, fire suppression, BMS
M-028 | Commissioning & Testing — Building B | June 1, 2027 | August 31, 2027 | 92 days | M-017, M-021, M-025 | Titan-McAllister Construction Group, LLC / Kestrel Infrastructure Advisors, LLC
M-029 | Commissioning & Testing — Building C | July 1, 2027 | September 30, 2027 | 92 days | M-018, M-022, M-025 | Titan-McAllister Construction Group, LLC / Kestrel Infrastructure Advisors, LLC
M-030 | Commissioning & Testing — Building D | August 1, 2027 | October 15, 2027 | 76 days | M-019, M-023, M-025 | Titan-McAllister Construction Group, LLC / Kestrel Infrastructure Advisors, LLC
M-031 | Substantial Completion — Building A | August 1, 2027 | August 1, 2027 | 0 days (milestone) | M-027 | Titan-McAllister Construction Group, LLC | Contractual Substantial Completion date; LDs of $125,000/calendar day accrue after this date if not achieved; LD cap: $10,300,000
M-032 | Substantial Completion — Building B | November 1, 2027 | November 1, 2027 | 0 days (milestone) | M-028 | Titan-McAllister Construction Group, LLC | Contractual Substantial Completion date; LDs of $125,000/calendar day; LD cap: $10,300,000
M-033 | Substantial Completion — Building C | November 1, 2027 | November 1, 2027 | 0 days (milestone) | M-029 | Titan-McAllister Construction Group, LLC | Contractual Substantial Completion date; LDs of $125,000/calendar day; LD cap: $10,300,000
M-034 | Substantial Completion — Building D | November 1, 2027 | November 1, 2027 | 0 days (milestone) | M-030 | Titan-McAllister Construction Group, LLC | Contractual Substantial Completion date; LDs of $125,000/calendar day; LD cap: $10,300,000
M-035 | Site Work Final Completion (Landscaping, Screening, Hardscape) | September 1, 2027 | November 15, 2027 | 76 days | M-003, M-026 | Titan-McAllister Construction Group, LLC | Includes visual screening commitments per ZMOD proffer statement
M-036 | Punchlist Completion — All Buildings | November 1, 2027 | January 31, 2028 | 92 days | M-031 through M-034 | Titan-McAllister Construction Group, LLC | Final retainage release conditioned on punchlist completion; retainage at 5% after 50% completion
M-037 | Final Completion — Full Campus | January 31, 2028 | January 31, 2028 | 0 days (milestone) | M-036 | Titan-McAllister Construction Group, LLC | All punchlist items resolved; final lien waivers obtained; as-built drawings delivered
M-038 | Stabilization Target (85% Leased) | Q2 2028 | Q2 2028 | N/A | M-034 | Ironhaven Data Centers LLC | Post-construction leasing milestone; relevant to DSCR covenant (≥ 1.25x) under construction loan
[sheet: Building-Level Schedule Summary]
Facility | Gross Floor Area (sq ft) | IT Load Capacity (MW) | Per-Building GMP Allocation ($) | Foundation Start | Foundation Complete | Structural / Envelope Start | Structural / Envelope Complete | MEP Rough-In Start | MEP Rough-In Complete | Generator Install Start | Generator Install Complete | Commissioning Start | Commissioning Complete | Substantial Completion Date | LD Rate ($/calendar day) | LD Cap ($)
Building A | 120000 | 24 | 103000000 | March 1, 2026 | June 15, 2026 | June 15, 2026 | December 15, 2026 | December 15, 2026 | April 30, 2027 | February 1, 2027 | May 15, 2027 | May 1, 2027 | July 15, 2027 | August 1, 2027 | 125000 | 10300000
Building B | 120000 | 24 | 103000000 | April 1, 2026 | July 15, 2026 | July 15, 2026 | January 15, 2027 | January 15, 2027 | May 31, 2027 | March 1, 2027 | June 15, 2027 | June 1, 2027 | August 31, 2027 | November 1, 2027 | 125000 | 10300000
Building C | 120000 | 24 | 103000000 | May 1, 2026 | August 15, 2026 | August 15, 2026 | February 15, 2027 | February 15, 2027 | June 30, 2027 | April 1, 2027 | July 15, 2027 | July 1, 2027 | September 30, 2027 | November 1, 2027 | 125000 | 10300000
Building D | 120000 | 24 | 103000000 | June 1, 2026 | September 15, 2026 | September 15, 2026 | March 15, 2027 | March 15, 2027 | July 31, 2027 | May 1, 2027 | August 15, 2027 | August 1, 2027 | October 15, 2027 | November 1, 2027 | 125000 | 10300000
Central Utility Plant | N/A | N/A | Included in GMP | April 1, 2026 | September 30, 2026 | N/A | N/A | October 1, 2026 | April 30, 2027 | N/A | N/A | May 1, 2027 | July 31, 2027 | N/A (tied to Bldg A SC) | N/A | N/A
TOTAL | 480000 | 96 | 412000000 | 41200000
[sheet: Critical Path & Dependencies]
Item ID | Critical Path Item / Dependency | Related Milestone ID | Required By Date | Responsible Party | Status / Risk Level | Notes
CP-001 | EPC Agreement Execution | M-001 | October 20, 2025 | Owner (Stonebridge Campus Holdings LLC) / Contractor (Titan-McAllister Construction Group, LLC) | Prerequisite to NTP | Target execution date: October 20, 2025; GMP of $412,000,000
CP-002 | Construction Loan Closing — $390,000,000 Facility | M-001 | October 15, 2025 | Owner / Summit National Bank, N.A. (Admin Agent), Cascade Commercial Lending Corp., Harborview Trust Company | Prerequisite to NTP | Loan Commitment Ref: CL-2025-VA-04418; LTC ≤ 65%
CP-003 | Minimum Equity Contribution Funded ($52,500,000) | M-001 | Before first loan draw | Ironhaven Data Centers LLC / Ridgeline Capital Partners Fund IV, LP | Prerequisite to first draw | 25% of $210,000,000 total equity commitment
CP-004 | ZMOD Approval — Loudoun County Board of Supervisors | M-001, M-002 | October 2025 | Owner / Ashcroft & Wynn, P.C. (Thomas Ashcroft) / Cornerstone Land Use Consulting, LLC (Alan Mercer) | Critical for construction permits | ZMOD-2025-0038; proffer estimate $2,400,000 ($5.00/sq ft × 480,000 sq ft)
CP-005 | Land Closings — Stonebridge Parcel (62.0 acres) and Meridian Parcel (19.4 acres) | M-001 | September 15, 2025 | Owner / Fidelitas Title & Escrow, Inc. | Prerequisite to construction loan and NTP | Stonebridge: $58,500,000 (Blackthorn Realty Group, Inc.); Meridian: $19,400,000 (Meridian Acres LLC)
CP-006 | Building Permits Issued — All Buildings | M-002 | Prior to NTP or concurrent with mobilization | Loudoun County / Owner | Schedule-critical | Dependent on ZMOD approval and site plan approval
CP-007 | Phase II ESA Completion — Stonebridge Parcel Northwest Quadrant (~4.2 acres) | M-003 | July 1, 2025 | Pendleton Environmental Associates, Inc. (Dr. Renata Volkov) | Must clear before mass grading of NW quadrant | Former agricultural use; potential residual pesticide contamination
CP-008 | Geotechnical Report — Final Foundation Recommendations | M-005 | Prior to foundation design finalization | Brannigan Geotechnical Engineering, LLC (Neil Brannigan, PE) | Critical for foundation schedule | Campus-wide investigation
CP-009 | VPC Substation Construction & Energization | M-025 | June 1, 2027 | Vantage Power Cooperative | Critical for commissioning | IHDC funding $18,500,000 line extension contribution; 230kV/34.5kV substation on Meridian Parcel; VPC Application No. LSA-2025-0091
CP-010 | ALTA Survey Completion — Both Parcels | M-002 | June 15, 2025 | Lumen Ridge Engineering, PLLC (Carlos Esteban, PE) | Required for site design finalization | 81.4 total acres
CP-011 | Performance and Payment Bonds Delivered ($412M each) | M-001 | At EPC execution | Great Basin Surety & Insurance Corp. (for Titan-McAllister) | Condition to NTP | 100% of GMP; required by both EPC Agreement and construction loan
CP-012 | Builder's Risk Policy in Effect ($412M) | M-001 | At NTP | Great Basin Surety & Insurance Corp. / Northgate Insurance Brokerage, LLC (William Keane) | Condition to NTP | $250,000 deductible per occurrence
CP-013 | Owner's Insurance Program (OCIP or Traditional) Finalized | M-001 | Prior to NTP | Northgate Insurance Brokerage, LLC / Owner | Schedule-adjacent | OCIP under evaluation; estimated 12–15% savings vs. traditional
CP-014 | Lender Approval of EPC Contract and Construction Schedule | M-001 | At or prior to construction loan closing | Summit National Bank, N.A. / Redmond & Calloway LLP (Victor Redmond) | Condition precedent to loan closing | Collateral assignment of EPC contract to lenders required
[sheet: Retainage & Payment Schedule]
Month | Calendar Month | Cumulative % Complete (%) | Monthly Draw Amount — Estimated ($) | Cumulative Draws ($) | Retainage Rate (%) | Retainage Withheld — Monthly ($) | Cumulative Retainage Held ($) | Net Payment to Contractor ($) | Notes
Month 1 | November 2025 | 1.5 | 6180000 | 6180000 | 10 | 618000 | 618000 | 5562000 | Mobilization, temporary facilities, E&S controls
Month 2 | December 2025 | 3.5 | 8240000 | 14420000 | 10 | 824000 | 1442000 | 7416000 | Site prep continues; mass grading begins
Month 3 | January 2026 | 5.5 | 8240000 | 22660000 | 10 | 824000 | 2266000 | 7416000 | Mass grading; underground utilities commence
Month 4 | February 2026 | 8 | 10300000 | 32960000 | 10 | 1030000 | 3296000 | 9270000 | Earthwork continues; utility trenching
Month 5 | March 2026 | 11 | 12360000 | 45320000 | 10 | 1236000 | 4532000 | 11124000 | Foundations start — Bldg A; substation construction begins
Month 6 | April 2026 | 14 | 12360000 | 57680000 | 10 | 1236000 | 5768000 | 11124000 | Foundations in progress — Bldgs A & B; CUP foundations begin
Month 7 | May 2026 | 17.5 | 14420000 | 72100000 | 10 | 1442000 | 7210000 | 12978000 | Foundations — Bldgs A, B, C; underground utilities
Month 8 | June 2026 | 21 | 14420000 | 86520000 | 10 | 1442000 | 8652000 | 12978000 | Bldg A structural steel begins; foundations Bldgs B, C, D
Month 9 | July 2026 | 24.5 | 14420000 | 100940000 | 10 | 1442000 | 10094000 | 12978000 | Structural steel — Bldg A; foundations Bldgs B, C, D
Month 10 | August 2026 | 28.5 | 16480000 | 117420000 | 10 | 1648000 | 11742000 | 14832000 | Structural steel — Bldgs A, B; foundations Bldgs C, D
Month 11 | September 2026 | 33 | 18540000 | 135960000 | 10 | 1854000 | 13596000 | 16686000 | Structural steel — Bldgs A, B, C; CUP structural complete
Month 12 | October 2026 | 38 | 20600000 | 156560000 | 10 | 2060000 | 15656000 | 18540000 | Structural steel — Bldgs A–C; CUP MEP fit-out begins
Month 13 | November 2026 | 43 | 20600000 | 177160000 | 10 | 2060000 | 17716000 | 18540000 | Structural steel & envelope — all buildings; parking structure
Month 14 | December 2026 | 48.5 | 22660000 | 199820000 | 10 | 2266000 | 19982000 | 20394000 | Bldg A envelope complete; MEP rough-in Bldg A begins
Month 15 | January 2027 | 53 | 18540000 | 218360000 | 5 | 927000 | 20909000 | 17613000 | Retainage drops to 5% after 50% completion; MEP Bldgs A, B
Month 16 | February 2027 | 57 | 16480000 | 234840000 | 5 | 824000 | 21733000 | 15656000 | MEP rough-in Bldgs A, B, C; generator install Bldg A
Month 17 | March 2027 | 62 | 20600000 | 255440000 | 5 | 1030000 | 22763000 | 19570000 | MEP all buildings; generator installs Bldgs A, B
Month 18 | April 2027 | 67 | 20600000 | 276040000 | 5 | 1030000 | 23793000 | 19570000 | MEP rough-in all buildings; CUP fit-out nearing completion
Month 19 | May 2027 | 72 | 20600000 | 296640000 | 5 | 1030000 | 24823000 | 19570000 | Commissioning Bldg A begins; MEP completion Bldg A; generators Bldgs B, C
Month 20 | June 2027 | 77 | 20600000 | 317240000 | 5 | 1030000 | 25853000 | 19570000 | Substation energized; commissioning Bldgs A, B; generators Bldgs C, D
Month 21 | July 2027 | 83 | 24720000 | 341960000 | 5 | 1236000 | 27089000 | 23484000 | Commissioning Bldgs A, B, C; Bldg A commissioning complete
Month 22 | August 2027 | 88 | 20600000 | 362560000 | 5 | 1030000 | 28119000 | 19570000 | Substantial Completion — Bldg A achieved; commissioning Bldgs B, C, D
Month 23 | September 2027 | 92 | 16480000 | 379040000 | 5 | 824000 | 28943000 | 15656000 | Commissioning Bldgs B, C, D; site work finalization
Month 24 | October 2027 | 95.5 | 14420000 | 393460000 | 5 | 721000 | 29664000 | 13699000 | Commissioning completion Bldgs B, C, D; punchlist preparation
Month 25 | November 2027 | 97.5 | 8240000 | 401700000 | 5 | 412000 | 30076000 | 7828000 | Substantial Completion — Bldgs B, C, D achieved; punchlist begins
Month 26 | December 2027 | 99 | 6180000 | 407880000 | 5 | 309000 | 30385000 | 5871000 | Punchlist work; site work final completion
Month 27 | January 2028 | 100 | 4120000 | 412000000 | 0 | 0 | 0 | 34505000 | Final Completion; all retainage released upon punchlist sign-off and final lien waivers
[sheet: Liquidated Damages Schedule]
Building | Contractual Substantial Completion Date | Per-Building GMP Allocation ($) | LD Rate — Per Calendar Day ($) | LD Cap — % of Building GMP (%) | LD Cap Amount ($) | Maximum LD Days Before Cap (days) | Notes
Building A | August 1, 2027 | 103000000 | 125000 | 10 | 10300000 | 82 | LD cap reached after 82.4 calendar days of delay ($10,300,000 ÷ $125,000)
Building B | November 1, 2027 | 103000000 | 125000 | 10 | 10300000 | 82
Building C | November 1, 2027 | 103000000 | 125000 | 10 | 10300000 | 82
Building D | November 1, 2027 | 103000000 | 125000 | 10 | 10300000 | 82
TOTAL | 412000000 | 41200000 | Aggregate LD cap across all buildings = $41,200,000