FR EA

Extract to table

Pull the structured facts out of a document: parties, dates, amounts, obligations.

Extract to table / regulatory-environmental-overview.docx
regulatory-environmental-overview.docx · 1015-00001

Parties

Calloway-Briggs Renewables Inc
North American Electric Reliability Corp
Army Corp
Solaris West Solar LLC
Red Mesa Wind Energy LLC
Painted Rock Solar LLC
Pronghorn Wind LLC
Brazos Energy Storage LLC

Dates

July 28, 2023
December 31, 2022

Amounts

$1,000,000
$0.026
$280,000,000

Obligations

To qualify for the ITC, a project must satisfy the applicable "begin construction" requirements established by the IRS
In addition, the IRS has established a continuity-of-construction requirement, under which a taxpayer must demonstrate continuous efforts to advance the project toward completion after satisfying the begin-construction requirement
Under Section 50(a) of the Code, if a project for which the ITC has been claimed is disposed of, or otherwise ceases to be eligible property, within five years of being placed in service, a portion of the ITC previously claimed must be recaptured (i
When NEPA is triggered, the responsible federal agency must prepare an environmental review document, the scope and depth of which depends on the significance of the potential environmental impacts