Extract to table / itc-ptc-analysis-memo.docx
itc-ptc-analysis-memo.docx
Parties
HARKNESS LLP
Calloway-Briggs Renewables Inc
Associates LLP
Pemberton LLP
Solaris West Solar LLC
Veltara Basin Financial LLC
Painted Rock Solar LLC
Dates
April 25, 2022
January 1, 2022
December 31, 2021
December 31, 2024
December 31, 2026
December 31, 2025
December 31, 2022
Amounts
$600,000,000
$280,000,000
$0.0275
$165,000,000
$143,000,000
$100,000,000
Obligations
Begin-construction documentation is under review, and continuity-of-construction requirements must be carefully managed
Placed-in-Service Requirement To claim the ITC, the energy property must be "placed in service" within the meaning of Treasury Regulation Section 1
Second, the project must satisfy continuity-of-construction requirements between the begin-construction date and the placed-in-service date, as discussed in Section IV
A project that begins construction in a qualifying year but is not placed in service within the applicable Continuity Safe Harbor period must demonstrate continuous construction or continuous efforts under a facts-and-circumstances test to preserve its credit eligibility
The placed-in-service requirements must be maintained throughout the ten-year PTC Period
Continuity of Construction: The expected COD of Q4 2024 must fall within the applicable Continuity Safe Harbor window measured from the begin-construction date