FR EA

Extract to table

Pull the structured facts out of a document: parties, dates, amounts, obligations.

Extract to table / analysis-of-second-data-request.docx
analysis-of-second-data-request.docx · 1016-00004

Parties

Dunmore Energy Holdings Ltd
Dunmore Power Trading LLC
Through Dunmore Midstream Partners LP
Harkness LLP
Crestline Document Solutions LLC
Dunmore Midstream GP LLC
Westmark Services Inc
Beane LLP

Dates

August 10, 2023
August 7, 2023
June 26, 2023
January 3, 2022
March 17, 2023
August 28, 2023
August 21, 2023
August 18, 2023
May 22, 2023
May 24, 2023

Amounts

$250,000
$47.3

Obligations

This process is inherently operational in nature — gas must be nominated and scheduled in advance to ensure that generation units have adequate fuel supply when they are dispatched by MISO
Our response must be crafted with particular care