Parties

HARKNESS LLP
Dunmore Energy Holdings Ltd
Dunmore Power Trading LLC
Beane LLP
Dunmore Midstream Partners LP
Capitol Registered Agents Inc

Dates

July 17, 2023
June 26, 2023
January 3, 2022
March 17, 2023
June 12, 2023
June 5, 2023
February 6, 2023
September 15, 2021
August 12, 2005

Amounts

$15
$40
$614
$47.3

Obligations

To the extent that any response includes information falling outside the Relevant Period, such inclusion is voluntary, does not expand the scope of Respondents' obligations, and shall not be deemed a waiver of Respondents' objection to the temporal scope of the request
9, which provides that information and documents obtained during the course of an investigation shall not be made public without the consent of the person providing such information, except as required by law or as the Commission may authorize
Respondents note that the profitability of individual FTR positions varies based on actual congestion outcomes relative to expected congestion at the time of acquisition, and that FTR profitability data must be considered in the context of DPT's overall hedging strategy