Parties

HARKNESS LLP
M. Palermino
Whitmore Aerospace LLC
M. Hargrove
Halcyon Defense Systems Inc
Dunaway LLP
Marlowe Asset Management Electro-Optics Corp
Protester Whitmore Aerospace LLC

Dates

October 17, 2023
October 16, 2023
September 26, 2023
September 22, 2023
September 27, 2023
September 15, 2023
October 2, 2023
October 6, 2023
October 12, 2023
October 30, 2023

Amounts

$387.5
$214.6
$14,200,000
$343,800,000
$17.4
$361,200,000

Obligations

§ 3554(a)(1), GAO is required to issue its decision on a protest "not later than 100 days after the date the protest is filed
This 100-day clock is not merely advisory — it reflects a congressional determination that bid protests must be resolved expeditiously to minimize disruption to the procurement process and to protect the interests of both protesters and the government
26, 2004, 2004 CPD ¶ 186 (GAO must manage its docket to ensure compliance with the 100-day deadline absent express statutory exceptions)