Parties

PROTEST OF WHITMORE AEROSPACE LLC
Harkness LLP
Whitmore Aerospace LLC
Halcyon Defense Systems Inc
Ashbury Partners LLC
Marlowe Asset Management Electro-Optics Corp
THE PROTESTER Whitmore Aerospace LLC
Pinnacle Precision Manufacturing Inc

Dates

September 26, 2023
September 15, 2023
September 18, 2023
September 22, 2023
September 19, 2023
June 2, 2023
August 3, 2023
September 1, 2023
March 14, 2023
May 12, 2023

Amounts

$387,500,000
$14,200,000
$343,800,000
$17,400,000
$361,200,000
$17.4
$398,600,000
$92,400,000
$214,600,000
$1,870,000,000

Obligations

2(a)(2), a protest based on other than alleged improprieties in a solicitation must be filed not later than ten calendar days after the basis of protest is known or should have been known, whichever is earlier
A properly documented tradeoff analysis must articulate, in specific terms, what the government is getting for the additional cost
These concerns are particularly acute for a procurement of aircraft survivability equipment, which must be available and supportable under the most demanding operational conditions
308, the source selection authority must base the source selection decision on a comparative assessment of proposals against all source selection criteria in the solicitation
The SSA's decision must document the rationale for any tradeoffs made, including the benefits associated with additional costs
When the SSA selects a higher-priced proposal over a lower-priced proposal, the SSA must specifically identify the technical advantages of the higher-priced proposal and explain why those advantages are worth the additional cost to the government