Extract to table / declaration-park-motion-to-stay.docx
declaration-park-motion-to-stay.docx
Parties
Whitmore Aerospace LLC
M. Vickers
Reeves LLP
Plaintiff Whitmore Aerospace LLC
Compliance Whitmore Aerospace LLC
Kendall LLP
Harkness LLP
M. Brannigan
Dates
February 10, 2023
September 1, 2019
August 31, 2024
August 31, 2026
June 12, 2019
August 1, 2022
October 15, 2022
Amounts
$200
$412,000,000
$32,960,000
$470,000,000
$74,160,000
$14,726,583
$12,817,441
$1,909,142
$4,200,000
$5,100,000
Obligations
Under the Contract Disputes Act, once a contractor submits a claim to the contracting officer, the contracting officer is required to issue a decision on that claim
Second, the multi-work-package cost structure of the ATAP program complicates the allocation analysis, as the ACO must evaluate and apportion cost overruns among the various work packages with specificity
Third, the CPIF contract type itself adds analytical complexity, as the ACO must consider the cost-sharing implications of any overrun determination for both the government and the contractor
4(b) provides, in relevant part, that: "Team Member shall indemnify and hold harmless Team Lead against any claim by the U