Extract to table / expert-report-work-plan.docx
expert-report-work-plan.docx · 1022-00005

Parties

Fenwick LLP
Meridian Infrastructure Partners LLC
Northgate Fiber Americas Inc
Lakeview Consulting Group LLC
Pinnacle Economics LLC
M. Ricci
Keystone Project Advisory LLC
Westbrook Valuation Services Inc

Dates

January 15, 2025
October 1, 2024
March 31, 2025
May 15, 2025
October 15, 2024
March 5, 2024
December 20, 2024
November 1, 2024
January 6, 2025
January 20, 2025

Amounts

$41.976
$34,133,333
$49
$9.1
$81.7
$712
$630.3
$18.3
$275,000
$11.825

Obligations

Key Vulnerabilities: The following weaknesses in Forster's anticipated damages analysis should be exploited: • Forster's model must survive scrutiny on Meridian's actual margin
The two experts' opinions must be carefully aligned on delay causation to avoid any inconsistency that opposing counsel could exploit at deposition or trial
Chazen must identify which NCRs caused rework delays, and Whitfield must quantify the cost of that rework
The two experts must use consistent NCR categorizations and cost data to ensure that their respective analyses are reconcilable
Whitfield's liquidated damages calculations must precisely match Chazen's delay attribution
Chazen must be prepared to opine on scope equivalence, and Whitfield must account for any legitimate scope differences in his cost differential analysis