Extract to table / cure-notice-timeline-memo.docx
cure-notice-timeline-memo.docx · 1022-00005

Parties

Meridian Infrastructure Partners LLC
Northgate Fiber Americas Inc
Lakeview Consulting Group LLC
Pinnacle Economics LLC
Ironclad Surety Group Inc
Severin Partners LLC

Dates

January 15, 2025
January 18, 2024
April 8, 2024
March 15, 2020
April 1, 2020
April 1, 2024
February 2, 2024
August 28, 2021
October 14, 2021
November 5, 2021

Amounts

$92.4
$1.2
$120
$50,424,000
$630.3
$41,976,000
$208
$363
$629
$175,000

Obligations

1 can be distilled into four elements, each of which must be satisfied before the Owner may exercise its right to terminate: (1) Existence of a material breach
The Owner must provide the Contractor with a formal written notice that identifies the specific breach or breaches on which the termination for cause will be predicated
The notice must be sufficiently specific to apprise the Contractor of the nature and scope of the alleged breach so that the Contractor has a meaningful opportunity to cure
If the Contractor fails to cure within the 30-day period, the Owner must issue a separate written notice of termination to effectuate the termination for cause
Specifically, for each day of unexcused delay beyond a milestone's scheduled completion date, the Contractor is required to pay the Owner liquidated damages of $175,000 per day per milestone
Under the MCA, changes to scope or schedule must be formalized through a written Change Order signed by both parties