Extract to table
Pull the structured facts out of a document: parties, dates, amounts, obligations.
Extract to table / summary-dd-report-risk-matrix.docx
summary-dd-report-risk-matrix.docx
Parties
Harkness LLP
Ironside Capital Management LP
Cascadia Acquisition Corp
Greer LLP
Pinnacle Credit Partners LLC
M. Weir
Blackthorn Advisory Group LLC
Clearwater Environmental Consulting Inc
Dates
September 1, 2022
August 31, 2022
July 15, 2022
August 3, 2022
August 12, 2022
August 8, 2022
March 14, 2012
June 28, 2012
August 22, 2022
April 12, 2018
Amounts
$299,970,000
$1,950,000,000
$1,050,000,000
$900,000,000
$138,000,000
$487,000,000
$195,000,000
$4,875,000
$5,000,000
$64,000,000
Obligations
FERC §203 approvals are subject to an 18-month lapse provision: if the transaction does not close within 18 months of the date of the FERC order granting approval, the approval lapses and a new application must be filed