Parties

Ironside Capital Management LP
Harkness LLP
Meridian Infrastructure GP IV LLC
Pinnacle Credit Partners LLC
M. Weir
Cascadia Acquisition Corp
Under LP
Associates LLP

Dates

July 18, 2023
June 30, 2023
July 10, 2023
April 1, 2023
July 29, 2022
January 9, 2023
October 31, 2023
April 30, 2023
June 28, 2023
December 31, 2023

Amounts

$64
$487
$1.95
$138
$975
$650
$325
$150
$1.125
$2.025

Obligations

05(c), which provides that costs arising from the GP's or Fund IV's discretionary decisions during a dormancy period shall not be allocated to the Vehicle absent the LP's prior written consent
The Side Letter provides that no management fee shall be charged by the GP to the Vehicle, either during the investment period or during dormancy