Extract to table / permitting-strategy-memo.docx
permitting-strategy-memo.docx · 1030-00003

Parties

Harkness LLP
Harborstone Capital Markets LLC
Environmental Consulting Inc
Land Services LLC
Army Corp
Veldkamp Family Holdings LLC
Dunlap Creek Ranch Inc
Pratt LLP

Dates

April 14, 2025
December 15, 2025
November 30, 2025
June 30, 2027
April 21, 2025
March 14, 2025
August 15, 2025
February 10, 2025
January 22, 2025
May 15, 2025

Amounts

$48,000,000
$31,200,000
$16,800,000
$677,000
$615,000
$62,000
$347,000
$1,024,000
$930,000
$94,000

Obligations

Through the analysis set forth below, this memorandum identifies nine distinct permit and approval tracks across three levels of government — federal, state, and local — that must be coordinated and completed to authorize construction
In order to meet this target, the technical sections prepared by Pinnacle must be finalized and delivered to C&H by May 1, 2025, allowing two weeks for legal review, integration, and finalization of the complete checklist
While the MDNS need not be issued before the SSDP application is filed, the checklist must have been submitted and the comment period should be underway
The SEPA MDNS must be issued, or at a minimum, the SEPA Environmental Checklist must have been submitted and the public comment period initiated, before the County will complete processing of the SSDP application
The SSDP must be obtained before grading permits can be issued for sites within the shoreline jurisdiction (PS-1, PS-2, and PS-3)
The HMP must be finalized and submitted with the Critical Areas application by June 1, 2025