Parties
Harkness LLP
Petitioner Metropolitan Transit Development Corp
STATEMENT Metropolitan Transit Development Corp
Tillotson LLP
Dietrich LLP
M. Quayle
Dates
April 12, 2023
March 29, 2023
March 30, 2023
April 5, 2023
October 15, 2022
September 22, 2022
December 31, 2022
March 15, 2023
March 1, 2023
January 9, 2023
Amounts
$98,125,000
$78,500,000
$19,625,000
$12,000,000
$5,500,000
$2,125,000
$1,420,000,000
$12,300,000
$7,380,000
$4,920,000
Obligations
Nothing in these responses shall be construed as a waiver of any objection, right, or privilege not specifically asserted herein
MTDC must demonstrate the availability and commitment of the required local match at the time of each drawdown request
The FTA Grant Agreement specifies certain conditions that must be satisfied before MTDC may draw down grant funds
MTDC is required to submit quarterly progress reports to FTA documenting its progress toward these milestones
MTDC is required to obtain FTA concurrence before making significant modifications to the project; (e) Any finding by FTA or the U