Extract to table / verified-petition-icc-docket-23-0214.docx
verified-petition-icc-docket-23-0214.docx
Parties
Harkness LLP
Petitioner Metropolitan Transit Development Corp
REQUESTED Metropolitan Transit Development Corp
Metropolitan Transit Development Corp
M. Adler
Tillotson LLP
M. Quayle
Dates
March 1, 2023
February 15, 2023
January 9, 2023
October 15, 2021
Amounts
$12,300,000
$0.062
$98,125,000
$78,500,000
$19,625,000
$1,420,000,000
$71,800,000
$319,111
$26,325,000
$2,444,040
Obligations
First, depot charging is characterized by a significant overnight baseload component, as the majority of bus charging occurs during the late evening and overnight hours when buses return from revenue service and must be fully charged by the start of the next morning's service dispatch
MTDC agrees to participate in Prairie Shore's demand response programs to the extent feasible, consistent with MTDC's obligation to maintain its transit service schedules