Extract to table
Pull the structured facts out of a document: parties, dates, amounts, obligations.
Extract to table / schedule-ev-t-term-sheet.docx
schedule-ev-t-term-sheet.docx
Parties
Harkness LLP
Metropolitan Transit Development Corp
North American Electric Reliability Corp
Tillotson LLP
M. Adler
M. Quayle
Dietrich LLP
Dates
March 1, 2023
Amounts
$78,500,000
$98,125,000
$19,625,000
$12,300,000
$0.062
$7,380,000
$4,920,000
$2,444,040
$0.0785
$0.0495
Obligations
SECTION 1: DEFINITIONS The following terms, as used in this Term Sheet and in any definitive Schedule EV-T tariff or related agreements derived herefrom, shall have the meanings set forth below unless the context clearly requires otherwise
Capitalized terms used but not defined in this Section 1 shall have the meanings ascribed to them elsewhere in this Term Sheet
Billing Demand shall be determined separately for each Service Point
The method of measuring and calculating Billing Demand shall be consistent with ICC General Order requirements and applicable ANSI standards for revenue-grade metering
The first Contract Year at a Service Point shall begin on the Commencement Date for that Service Point and end on the day immediately preceding the first anniversary thereof; each subsequent Contract Year shall begin on each successive anniversary of the Commencement Date
The Depot Charging Facility at each Service Point shall include all customer-side equipment located beyond the point of delivery as defined by Prairie Shore's tariff