Parties
HARKNESS LLP
Torchlight Mining Corp
Dates
February 5, 2025
February 3, 2025
January 18, 2024
March 5, 2024
April 22, 2024
December 31, 2025
April 25, 2024
May 15, 2024
July 30, 2024
October 21, 2024
Amounts
$63.2
$47.1
$31.5
$7.9
$12.0
$3.5
$5,500,000
$3,500,000
$3,000,000
$12,000,000 3.6
Obligations
BCM is required to install and operate enhanced treatment systems for cyanide destruction and mercury removal in process solution circulated through the heap-leach operation
BCM is required to develop and implement a pit-lake water management plan addressing selenium contamination and other water-quality concerns in the pit lake
Kamal Osei, Senior Managing Director; Portland, Oregon) shall serve as the independent monitor
The claiming party must provide written notice to EPA within 15 days of the event or circumstances giving rise to the force majeure claim
The consent decree establishes a three-tier dispute resolution mechanism: (i) Informal Negotiation: The parties shall first attempt to resolve any dispute through informal negotiation for a period of 30 days following written notice of the dispute
(ii) Formal EPA Decision: If the dispute is not resolved through informal negotiation, EPA shall issue a formal written decision within 30 days, setting forth its position on the dispute and the factual and legal basis therefor