Extract to table
Pull the structured facts out of a document: parties, dates, amounts, obligations.
Extract to table / state-co-plaintiff-signature-pages-joinder.docx
state-co-plaintiff-signature-pages-joinder.docx
Parties
Torchlight Mining Corp
Weiss LLP
Harkness LLP
General Counsel Torchlight Mining Corp
Dates
February 14, 2025
February 19, 2025
July 30, 2024
February 3, 2025
December 31, 2019
September 15, 2022
December 14, 2025
June 14, 2026
June 14, 2027
June 14, 2055
Amounts
$198,600,000
$134,900,000
$42,800,000
$34,100,000
$14,200,000
$5,800,000
$20,000,000
$5,500,000
$245,000,000
$165,000,000
Obligations
Montana hereby joins as a co-plaintiff to the Consent Decree and agrees to be bound by the terms and conditions thereof as they pertain to the Ridgecrest Facility and the Gallatin Facility
Commencement of Ridgecrest remedy construction shall occur no later than June 14, 2027
The Ridgecrest thirty (30)-year remediation obligation shall conclude no later than June 14, 2055, subject to any extensions or modifications approved by the EPA in consultation with MT DEQ
Nevada hereby joins as a co-plaintiff to the Consent Decree and agrees to be bound by the terms and conditions thereof as they pertain to the Bonanza Creek Facility
West Virginia hereby joins as a co-plaintiff to the Consent Decree and agrees to be bound by the terms and conditions thereof as they pertain to the Kanawha Bend Facility
The state environmental agencies — MT DEQ, NV DEP, and WV DEP — exercise concurrent authority over state-specific permit and regulatory obligations at their respective facilities and shall coordinate with the EPA in the exercise of such authority, consistent with the terms of the Consent Decree and applicable federal-state cooperative agreements