MEMORANDUM

PRIVILEGED & CONFIDENTIAL — ATTORNEY WORK PRODUCT This memorandum is protected by the attorney-client privilege and the work product doctrine. It was prepared in anticipation of litigation and reflects the mental impressions, conclusions, opinions, and legal theories of counsel. It is not to be disclosed to any person or entity outside of the attorney-client relationship without the prior written consent of counsel.

TO: Linda Osei, Responsible Partner

FROM: Jeffrey Park, Lead Associate

DATE: January 15, 2025

RE: Cure Notice and Termination Timeline — Compliance with MCA § 14.1

MATTER: Meridian Infrastructure Partners LLC v. Northgate Fiber Americas Inc., Supreme Court of the State of New York, New York County, Commercial Division, Index No. 654321/2024

C&H MATTER NO.: 1022-00005

Right-click to update Table of Contents

I. Executive Summary

This memorandum presents a detailed chronology of the cure notice and termination-for-cause sequence from January 18, 2024, through April 8, 2024, and demonstrates that Northgate Fiber Americas Inc. ("NFA" or the "Owner") strictly complied with the procedural requirements of Section 14.1 of the Master Construction Agreement dated March 15, 2020 (the "MCA") when it terminated Meridian Infrastructure Partners LLC ("Meridian" or the "Contractor") for material breach. The memorandum also addresses the broader factual context—including the pattern of escalating delays and pervasive quality deficiencies that preceded the cure notice process—so as to demonstrate that the termination was not only procedurally proper but substantively justified.

The core conclusion of this memorandum is as follows: NFA provided Meridian with two separate written cure notices, afforded cure periods totaling well over 30 calendar days (73 days from the first cure notice to termination), invited and gave full and fair consideration to Meridian's Corrective Action Plan, and issued a notice of termination only after Meridian had demonstrably failed to cure any of the material breaches identified in the cure notices. At every stage, NFA exceeded the procedural minimum required by MCA § 14.1. The termination was procedurally and substantively proper.

This memorandum is intended to serve several practical purposes in the litigation. First, it will form the factual and analytical foundation for the defense of Meridian's Count I, which alleges wrongful termination of the MCA and seeks recharacterization of the for-cause termination as a termination for convenience, thereby triggering Meridian's claimed entitlement to a termination fee and lost profits totaling approximately $92.4 million. Second, the chronology will support NFA's affirmative defense that the termination was justified by Meridian's material breach. Third, this memorandum will inform the expert reports being prepared by Dr. Elinor Chazen of Lakeview Consulting Group LLC (retained as NFA's delay and scheduling expert) and Professor Gordon Whitfield of Pinnacle Economics LLC (retained as NFA's damages expert). Fourth, and perhaps most critically, this memorandum is intended to provide the factual platform for summary judgment briefing anticipated for filing in August 2025, with the objective of obtaining a dispositive ruling on the validity of the termination before trial.

II. Contractual Framework — MCA § 14.1 and Related Provisions

Before turning to the chronology itself, it is necessary to set forth the contractual provisions governing the termination-for-cause process. The MCA is a comprehensive construction agreement for the design and construction of a fiber optic network spanning multiple states along the eastern seaboard of the United States. The MCA was executed on March 15, 2020, between NFA, as Owner, and Meridian, as Contractor, with a total Contract Price of approximately $1.2 billion. The Notice to Proceed was issued on April 1, 2020. The MCA is governed by the laws of the State of New York (MCA § 22.1).

A. MCA § 14.1 — Termination for Cause by Owner

Section 14.1 of the MCA sets forth the exclusive mechanism by which the Owner may terminate the MCA for cause. In relevant part, it provides that the Owner may terminate the MCA if the Contractor commits a "material breach" of the Agreement that remains uncured for thirty (30) calendar days after the Owner provides the Contractor with written notice specifying the breach.

The procedural requirements of Section 14.1 can be distilled into four elements, each of which must be satisfied before the Owner may exercise its right to terminate:

(1) Existence of a material breach. The Contractor must have committed a breach that is "material" — that is, a breach of sufficient gravity to justify termination of the contract, as distinguished from minor or inconsequential departures from the contract's requirements.

(2) Written notice specifying the breach. The Owner must provide the Contractor with a formal written notice that identifies the specific breach or breaches on which the termination for cause will be predicated. The notice must be sufficiently specific to apprise the Contractor of the nature and scope of the alleged breach so that the Contractor has a meaningful opportunity to cure.

(3) Expiration of the 30-calendar-day cure period without cure. The Contractor is afforded thirty (30) calendar days following receipt of the written notice within which to cure the identified breach. If the Contractor effects a cure within the 30-day period, the Owner's right to terminate is extinguished (with respect to that particular breach).

(4) Written notice of termination. If the Contractor fails to cure within the 30-day period, the Owner must issue a separate written notice of termination to effectuate the termination for cause.

As discussed in detail in Sections IV and V below, NFA satisfied each of these elements with substantial margin to spare.

B. MCA § 14.5 — Consequences of Termination for Cause

Section 14.5 of the MCA establishes the consequences that follow from a valid termination for cause under Section 14.1. These consequences are significant and include the following:

(a) Forfeiture of termination fee. The Contractor forfeits any right to a termination fee that would otherwise be payable under MCA § 14.3 (governing termination for convenience). Under Section 14.3, a Contractor that is terminated for convenience is entitled to a termination fee equal to 8% of the value of unperformed work. By contrast, a Contractor terminated for cause under Section 14.1 receives no such fee.

(b) Owner's right to complete work using substitute contractors. The Owner is entitled to engage one or more substitute contractors to complete the remaining work under the MCA, and to charge any excess completion costs (i.e., the amount by which the substitute contractor's charges exceed the remaining unperformed value under the MCA) to the Contractor.

(c) Owner's right to draw on the performance bond. The Owner may draw upon the Contractor's performance bond to secure reimbursement for losses arising from the Contractor's breach. In this case, the performance bond was issued by Ironclad Surety Group Inc. under Bond No. ISG-2020-NE-04417 in the penal sum of $120 million.

Each of these consequences was expressly invoked by NFA in the Notice of Termination dated April 1, 2024, as discussed below.

C. MCA § 14.3 — Termination for Convenience (Contrast)

Section 14.3 of the MCA provides an alternative termination mechanism: termination for convenience. Under this provision, the Owner may terminate the MCA at any time for any reason (or no reason) upon sixty (60) days' prior written notice to the Contractor. If the Owner exercises this right, the Contractor is entitled to (i) payment for all work properly completed and accepted as of the termination date, and (ii) a termination fee equal to 8% of the remaining unperformed contract value.

The distinction between Section 14.1 (termination for cause) and Section 14.3 (termination for convenience) lies at the heart of this case. Meridian's central claim in Count I of the Verified Complaint is that NFA's purported termination for cause was, in fact, pretextual and should be recharacterized by the Court as a termination for convenience. Under Meridian's theory, such recharacterization would entitle Meridian to the termination fee that Section 14.3 provides. Meridian quantifies this fee at $50,424,000 (calculated as 8% of $630.3 million in remaining unperformed contract value). In addition, Meridian claims lost profits of $41,976,000, bringing Meridian's total claimed damages under Count I to approximately $92.4 million.

The analysis set forth in this memorandum directly refutes Meridian's recharacterization argument by demonstrating that the for-cause termination was neither procedurally deficient nor substantively pretextual.

D. MCA § 8.2 — Milestone Schedule

Section 8.2 of the MCA establishes a detailed milestone schedule consisting of fourteen (14) defined milestones, organized across three phases of construction. The milestones serve as intermediate benchmarks for measuring the Contractor's progress, and the MCA requires the issuance of interim completion certificates for each phase. The three phases and their associated milestones are as follows:

Phase 1: NY Metro & Northern NJ — Milestones 1 through 4; approximately 3,200 route miles of fiber optic cable installation; contract value of approximately $208 million.

Phase 2: CT, Western MA, Southern PA — Milestones 5 through 8; approximately 5,600 route miles; contract value of approximately $363 million.

Phase 3: MD, VA, Eastern PA — Milestones 9 through 14; approximately 9,700 route miles; contract value of approximately $629 million.

Meridian's failure to achieve milestones on schedule — and the escalating pattern of those failures — was a central basis for the material breach determination set forth in Cure Notice No. 1.

E. MCA § 9.1 — Liquidated Damages for Delay

Section 9.1 of the MCA provides for liquidated damages for delay. Specifically, for each day of unexcused delay beyond a milestone's scheduled completion date, the Contractor is required to pay the Owner liquidated damages of $175,000 per day per milestone. These liquidated damages are subject to a cap of 10% of the applicable milestone value per milestone, and an aggregate cap of 5% of the total Contract Price, which equates to approximately $60 million.

The liquidated damages mechanism is distinct from the termination-for-cause mechanism of Section 14.1. The assessment of liquidated damages for delay on a particular milestone does not, by itself, trigger the cure notice process. However, the persistent accumulation of delays across multiple milestones — and the escalating severity of those delays — contributed to the determination that Meridian was in material breach, which in turn triggered the Section 14.1 process.

F. MCA § 12.4 — Quality Standards

Section 12.4 of the MCA requires that all work performed by the Contractor conform to the quality standards set forth in Northgate Technical Specification NS-FIBER-2020, as well as applicable industry standards including ANSI/TIA-568 (cabling standards) and BICSI guidelines for telecommunications distribution design. The MCA imposes an affirmative obligation on the Contractor to maintain quality assurance processes and to correct any work that does not conform to the specified quality standards.

Meridian's persistent quality deficiencies — documented in 287 non-conformance reports ("NCRs"), of which 43 were classified as "critical" — constituted an independent basis for the material breach determination, in addition to the schedule delays.

G. MCA § 16.1 — Change Orders

Section 16.1 of the MCA governs changes to the scope of work or the construction schedule. It requires that any change to the scope or schedule be formalized through a written Change Order signed by both parties. No change is effective or binding unless memorialized in a properly executed Change Order.

This provision is relevant to the present analysis because, in its February 2, 2024 response to Cure Notice No. 1, Meridian asserted that fourteen (14) Owner-directed scope changes were never formalized as Change Orders, and that the additional scope arising from these alleged changes contributed to Meridian's delays. Meridian's constructive change order defense is addressed in a separate memorandum (see memo re Meridian's Constructive Change Order Defense), but the argument is referenced here as part of the analysis of Meridian's response to the cure notices. It bears noting that Meridian's February 2, 2024 letter did not identify specific Change Order numbers, dates, or corresponding scope descriptions, a deficiency that is relevant both to the adequacy of Meridian's response to Cure Notice No. 1 and to the viability of the constructive change order defense.

III. Background — Pattern of Delays and Quality Deficiencies Pre-Dating Cure Notices

The cure notice and termination sequence described in Section IV did not arise in a vacuum. Rather, it was the culmination of a years-long pattern of escalating schedule delays and persistent quality deficiencies that began during Phase 1 of the project and worsened markedly during Phase 2 and into Phase 3. This section sets forth the factual background necessary to understand why NFA determined, in January 2024, that Meridian's performance failures had risen to the level of material breach warranting invocation of Section 14.1.

A. Phase 1 Delays (2020–2021)

Phase 1 of the project encompassed Milestones 1 through 4 and involved the construction of approximately 3,200 route miles of fiber optic infrastructure across the New York metropolitan area and Northern New Jersey, with a total contract value of approximately $208 million.

Meridian achieved Milestones 1, 2, and 4 on or before their scheduled completion dates. However, Milestone 3, which had a target completion date of August 28, 2021, was not achieved until October 14, 2021 — a delay of 47 days. NFA assessed liquidated damages of $8,225,000 (calculated as 47 days × $175,000 per day) by letter dated November 5, 2021. These liquidated damages were deducted from Meridian's subsequent payment application, and Meridian did not dispute the assessment at the time.

While the Milestone 3 delay was a single data point, it is significant as the first documented indication of the systemic scheduling problems that would become more pronounced during Phase 2. In retrospect, the 47-day delay on Milestone 3 was a harbinger of the far more severe delays that followed.

B. Phase 2 Delays (2021–2024)

Phase 2 of the project encompassed Milestones 5 through 8 and involved the construction of approximately 5,600 route miles of fiber optic infrastructure across Connecticut, Western Massachusetts, and Southern Pennsylvania, with a total contract value of approximately $363 million. It was during Phase 2 that Meridian's performance deteriorated dramatically, with delays escalating from milestone to milestone in a pattern that demonstrated worsening — not improving — performance.

The Phase 2 delay history is as follows:

Milestone 5: 22 days late. Liquidated damages assessed: 22 × $175,000 = $3,850,000.

Milestone 6: 68 days late. Liquidated damages assessed: 68 × $175,000 = $11,900,000.

Milestone 7: 91 days late. Liquidated damages assessed: 91 × $175,000 = $15,925,000.

Milestone 8: Never completed before termination. As of the April 1, 2024 termination date, Meridian had accrued 134 days of delay on Milestone 8. The uncapped calculation of liquidated damages would be 134 × $175,000 = $23,450,000, but under the 10% per-milestone cap (MCA § 9.1), the Milestone 8 liquidated damages are capped at 10% of the Milestone 8 value ($91 million × 10% = $9,100,000).

The total Phase 2 liquidated damages amount to $40,775,000. When combined with the $8,225,000 in Phase 1 liquidated damages (Milestone 3), the total assessed liquidated damages across the project are $49,000,000 — below the $60 million aggregate cap provided by MCA § 9.1.

The significance of the Phase 2 delay history lies not only in the magnitude of the delays but in the unmistakable pattern of escalation: 22 days late, then 68 days late, then 91 days late, and then 134+ days late with no completion in sight. This pattern of worsening performance — rather than improvement — was a critical factor in NFA's determination that Meridian's delays constituted a material breach of the MCA, rather than isolated schedule slippages that might be addressed through the liquidated damages mechanism alone.

C. Quality Deficiencies (Phase 2)

In addition to the escalating schedule delays, Meridian exhibited persistent and serious quality deficiencies during Phase 2 construction. NFA's internal quality assurance team, led by Sean Calloway, Director of Construction Management, documented these deficiencies in monthly QA reports and in formal non-conformance reports ("NCRs").

During Phase 2, a total of 287 NCRs were issued documenting instances in which Meridian's work failed to conform to the quality standards required by MCA § 12.4 and Northgate Technical Specification NS-FIBER-2020. Of these 287 NCRs:

• 43 NCRs were classified as "critical" — indicating defects of sufficient severity to compromise the performance, reliability, or safety of the fiber optic infrastructure. Critical NCRs included, among other things, instances of (i) splice loss exceeding specification tolerances, resulting in signal degradation; (ii) improper conduit burial depth, failing to meet the minimum depth requirements of NS-FIBER-2020 and creating vulnerability to third-party damage; and (iii) unauthorized route deviations from the approved construction drawings, resulting in non-compliant fiber paths.

• 244 NCRs were classified as "non-critical" — indicating deviations from the specifications that, while requiring corrective action, did not individually compromise the integrity of the network.

The volume and severity of these quality deficiencies formed a key basis for the material breach determination set forth in Cure Notice No. 1. Notably, the 43 critical NCRs represented failures of basic construction quality — not edge cases or minor deviations — and many of them required costly remediation or reconstruction of completed work segments. The quality deficiencies were pervasive across the Phase 2 geography and were not limited to isolated work crews or subcontractors.

D. Phase 3 Minimal Progress

Phase 3 of the project encompassed Milestones 9 through 14 and was the largest phase by scope, involving the construction of approximately 9,700 route miles of fiber optic infrastructure across Maryland, Virginia, and Eastern Pennsylvania, with a contract value of approximately $629 million. The planned construction window for Phase 3 was July 2023 through March 2025.

Meridian mobilized construction crews in Maryland in July 2023, but made minimal progress thereafter. By the April 1, 2024 termination date — approximately nine months into the planned Phase 3 construction window — Meridian had completed only approximately 340 of the 9,700 planned route miles, representing just 3.5% of the Phase 3 scope. At this rate of progress, Phase 3 would have taken approximately 21 years to complete — an obviously unacceptable pace that further confirmed Meridian's inability to perform the remaining work.

With respect to payments during Phase 3, Meridian submitted payment applications totaling $48.2 million. NFA approved and paid $31.7 million of this amount. The remaining $16.5 million was disputed on the grounds of defective work (work that did not meet quality specifications) and inflated unit counts (payment applications claiming payment for work that had not actually been completed or that was measured using improper unit quantities). The disputed payment applications are the subject of Meridian's Count III in the Verified Complaint and are addressed in a separate memorandum.

The inadequacy of Meridian's Phase 3 mobilization and progress was cited in Cure Notice No. 1 as further evidence of material breach.

IV. Detailed Chronology of Cure Notice and Termination Sequence

This section sets forth the detailed chronology of the cure notice and termination sequence, beginning with Cure Notice No. 1 on January 18, 2024, and concluding with Meridian's demand on the Ironclad performance bond on April 15, 2024. Each event is presented with its full context, including the authorship, delivery, content, and legal significance of each communication.

A. Cure Notice No. 1 — January 18, 2024

1. Author and Recipient. Cure Notice No. 1 was sent by Renata Voss, Vice President of US Network Infrastructure at Northgate Fiber Americas Inc., to Victor Sandoval, Managing Member and Chief Executive Officer of Meridian Infrastructure Partners LLC. Ms. Voss was the senior NFA executive with direct operational responsibility for the fiber network construction program and was the designated representative for purposes of contract administration under the MCA.

2. Form and Delivery. Cure Notice No. 1 was issued as a formal written notice, as required by MCA § 14.1. The notice was transmitted via two independent delivery methods: (i) overnight courier service (Severin Partners LLC), addressed to Meridian's registered office, and (ii) electronic mail to Mr. Sandoval and Meridian's general counsel. Severin Partners LLC delivery was confirmed on January 19, 2024, establishing the date of receipt for purposes of the 30-day cure period.

Cross-reference: Supporting documents — Cure Notice No. 1 letter, Bates Nos. [to be assigned upon completion of Bates-stamping]; Severin Partners LLC delivery confirmation, Bates Nos. [to be assigned].

3. Content of Cure Notice No. 1. Cure Notice No. 1 identified the following as constituting a material breach of the MCA, thereby triggering the cure process under Section 14.1:

(a) Failure to achieve Milestone 8 (Phase 2). The notice identified Meridian's failure to achieve Milestone 8 — the final milestone of Phase 2 — as a material breach of MCA § 8.2 (Milestone Schedule). As of the date of the notice, Milestone 8 was 134 days past its scheduled completion date, with no completion date in sight. The notice characterized this as the most severe in a pattern of escalating milestone delays.

(b) Inadequate mobilization for Phase 3. The notice cited Meridian's failure to adequately mobilize for Phase 3 construction, noting that only approximately 340 of the 9,700 planned route miles (3.5%) had been completed in the approximately six months since Meridian's initial Phase 3 mobilization in July 2023. The notice characterized this progress as wholly insufficient to achieve the Phase 3 milestones within the contractually required timeframe.

(c) Persistent substandard workmanship — 43 critical NCRs. The notice referenced the 43 critical non-conformance reports issued during Phase 2 as evidence of persistent substandard workmanship in violation of MCA § 12.4 and Northgate Technical Specification NS-FIBER-2020. The notice specifically identified categories of critical defects, including splice loss exceedances, improper conduit depth, and unauthorized route deviations.

(d) Aggregate pattern of delays across all phases. The notice stated that the aggregate pattern of delays across the project — Milestone 3 (47 days late), Milestone 5 (22 days late), Milestone 6 (68 days late), Milestone 7 (91 days late), and Milestone 8 (134+ days late and ongoing) — constituted a material breach of the MCA. The notice emphasized that the escalating nature of these delays demonstrated a systemic failure of project management and execution, rather than isolated incidents.

The notice demanded that Meridian cure the identified breaches within 30 calendar days, as required by MCA § 14.1. Based on the January 19, 2024 delivery date, the cure period was set to expire on February 17, 2024 (the thirtieth calendar day following delivery).

4. Significance. Cure Notice No. 1 was the first formal invocation of MCA § 14.1's termination-for-cause mechanism. It is important to distinguish this from the prior liquidated damages assessments. NFA had previously assessed liquidated damages for milestone delays under MCA § 9.1 — beginning with the LD assessment letter of November 5, 2021, for Milestone 3, and continuing with subsequent assessments for Milestones 5, 6, and 7. Those LD assessments, however, were handled through the liquidated damages mechanism of Section 9.1 without triggering the Section 14.1 cure process. The issuance of Cure Notice No. 1 represented a qualitative escalation: NFA determined that the cumulative pattern of delays and quality deficiencies had progressed beyond the scope of what the LD mechanism was designed to address, and that the Contractor's overall performance had deteriorated to the point of material breach warranting potential termination.

B. Meridian's Response to Cure Notice No. 1 — February 2, 2024

1. Author and Recipient. Meridian's response was transmitted by letter from Victor Sandoval, Managing Member and Chief Executive Officer of Meridian, to Renata Voss, Vice President of US Network Infrastructure at NFA.

2. Timing. The response was dated February 2, 2024 — fifteen (15) days after the issuance of Cure Notice No. 1 and within the 30-calendar-day cure period. The response was timely in the sense that it was submitted during the cure period; however, timeliness of response is distinct from the question of whether the response constituted an actual cure of the identified breaches.

Cross-reference: Supporting document — Meridian Response Letter dated February 2, 2024, Bates Nos. [to be assigned].

3. Content of Meridian's Response. Meridian's February 2, 2024 response disputed NFA's characterization of Meridian's performance as constituting material breach. The letter did not acknowledge any breach or undertake to cure any of the identified deficiencies. Instead, Meridian asserted three defenses:

(a) Permitting Delays (MCA § 5.3). Meridian claimed that NFA failed to timely obtain municipal permits for certain construction activities, which Meridian contended were the Owner's responsibility under MCA § 5.3. Specifically, Meridian alleged that permitting delays in municipalities in Connecticut, Massachusetts, and Pennsylvania had caused cascading schedule impacts that were responsible for a substantial portion of the milestone delays. Meridian asserted that NFA was therefore not entitled to rely on those delays as a basis for a material breach determination.

(b) Unformalized Scope Changes (MCA § 16.1). Meridian claimed that NFA had directed fourteen (14) scope changes during the course of the project that were never formalized as written Change Orders under MCA § 16.1. Meridian asserted that the additional scope arising from these alleged changes contributed to the delays, and that NFA could not terminate Meridian for breach of a schedule that had been rendered unachievable by Owner-directed scope additions. Notably, Meridian's February 2, 2024 letter did not identify specific Change Order numbers, dates, scope descriptions, or the individual schedule impact of any of the 14 alleged changes.

(c) Force Majeure. Meridian asserted that the aftereffects of the COVID-19 pandemic on labor supply, as well as supply chain disruptions affecting the procurement of fiber cable from Meridian's suppliers, constituted force majeure events excusing Meridian's delays. Meridian did not identify specific subcontractors, specific labor shortages, or specific supply chain disruptions with dates and durations.

Critically, Meridian's response did not present a specific remediation plan or commit to a revised schedule for the completion of Milestone 8, the acceleration of Phase 3 construction, or the remediation of quality deficiencies. Equally critically, the response did not address the 43 critical NCRs cited in Cure Notice No. 1 or propose any corrective action with respect to the quality deficiencies documented therein. The quality issues were simply ignored.

4. Analysis of Response. Meridian's February 2, 2024 response was defensive in nature but did not constitute a "cure" of the identified breaches in any sense of the term. A cure requires affirmative corrective action — the actual remediation of the breach — not merely a letter disputing the characterization of the breach. Even assuming arguendo that some of Meridian's defenses had merit (an assumption this memorandum does not concede), the letter itself accomplished no curative action. Milestone 8 remained unachieved. Phase 3 remained at 3.5% completion. The 43 critical NCRs remained unaddressed.

The failure to address the quality issues at all was a particularly significant omission. Cure Notice No. 1 had specifically identified the 43 critical NCRs as a basis for the material breach determination, and Meridian's response was entirely silent on this point. This silence is notable both because it left a critical component of the identified breach wholly uncured and because it suggests that Meridian had no answer to the quality deficiency allegations.

With respect to Meridian's three stated defenses, each is addressed in separate legal analyses being prepared concurrently. The permitting responsibility defense is addressed in the memo re Permitting Responsibilities Under MCA § 5.3. The constructive change order defense is addressed in the memo re Meridian's Constructive Change Order Defense (MCA § 16.1). The force majeure defense is addressed in the memo re Force Majeure. For purposes of this chronology memorandum, however, several observations are warranted:

First, even accepting arguendo that some delays were contributed to by Owner-caused permitting delays or scope changes, Meridian did not demonstrate — in its February 2, 2024 letter or at any subsequent point during the cure period — that Owner-caused delays accounted for the full scope of the schedule slippage across all milestones. The delay data shows an escalating pattern (22 → 68 → 91 → 134+ days) that is inconsistent with the premise that Owner-caused events were the sole or even predominant driver.

Second, the force majeure defense raises serious timeliness issues. Meridian's February 2, 2024 letter was the first time Meridian invoked force majeure — approximately three to four years after the alleged COVID-related disruptions occurred. The MCA's force majeure clause almost certainly imposes contemporaneous notice requirements that Meridian failed to satisfy. This issue is analyzed in detail in the Force Majeure memorandum.

C. Cure Notice No. 2 — February 19, 2024

1. Author and Recipient. Cure Notice No. 2 was sent by Renata Voss, VP of US Network Infrastructure at NFA, to Victor Sandoval, Managing Member and CEO of Meridian.

2. Timing. Cure Notice No. 2 was sent on February 19, 2024 — two days after the expiration of the 30-calendar-day cure period from Cure Notice No. 1 (which expired on February 17, 2024). This timing is significant: as of February 17, 2024, NFA had the contractual right to issue a notice of termination, because the 30-day cure period had expired without cure. NFA chose not to exercise that right immediately. Instead, NFA issued a second cure notice, providing Meridian with an additional opportunity to remedy its performance failures.

This second notice was not strictly required by MCA § 14.1, which provides for termination after one 30-day cure period. NFA elected to provide the additional notice as a matter of good faith and to strengthen the documentary record by demonstrating that NFA gave Meridian every reasonable opportunity to cure before resorting to termination.

3. Form and Delivery. Cure Notice No. 2 was issued as a formal written notice, consistent with Cure Notice No. 1. It was sent via overnight courier (Severin Partners LLC) and electronic mail. Delivery was confirmed.

Cross-reference: Supporting document — Cure Notice No. 2 letter, Bates Nos. [to be assigned].

4. Content of Cure Notice No. 2. The content of Cure Notice No. 2 included the following:

(a) A statement that Meridian had failed to cure the material breach identified in Cure Notice No. 1 within the 30-calendar-day cure period, which expired on February 17, 2024.

(b) A rejection of Meridian's defenses (permitting delays, scope changes, and force majeure) as set forth in Meridian's February 2, 2024 response, characterizing those defenses as insufficient to excuse Meridian's performance failures.

(c) A determination that Meridian remained in continuing material breach of the MCA.

(d) An additional opportunity: Cure Notice No. 2 demanded that Meridian present a detailed remediation plan within fifteen (15) calendar days — that is, by March 6, 2024. The notice specified that the remediation plan should address both schedule recovery and quality corrective measures, and that it should set forth a realistic and achievable timeline for bringing the project back into compliance with the MCA's requirements.

5. Significance. By issuing Cure Notice No. 2 with an additional 15-day window for a remediation plan, NFA went substantially beyond the contractual minimum required by MCA § 14.1. NFA could have terminated the MCA on or after February 17, 2024, when the initial 30-day cure period expired. Instead, NFA extended the process by issuing a second cure notice, inviting a remediation plan, and affording additional time for Meridian to demonstrate a path to cure. This approach demonstrates NFA's good-faith effort to resolve the situation through means short of termination before ultimately concluding that termination was the only available recourse.

D. Meridian's Corrective Action Plan — March 5, 2024

1. Author and Recipient. The Corrective Action Plan was submitted by Bridget Yeung, Chief Operating Officer of Meridian, to Renata Voss (VP of US Network Infrastructure, NFA) and Sean Calloway (Director of Construction Management, NFA). The fact that the plan was submitted by Meridian's COO, rather than its CEO, is of some significance — it suggests that Meridian recognized the operational nature of the issues and assigned responsibility for the response to its senior operations executive.

2. Timing. The Corrective Action Plan was submitted on March 5, 2024 — one day before the 15-calendar-day deadline set in Cure Notice No. 2 (which ran from February 19, 2024, and expired on March 6, 2024). The plan was therefore timely submitted within the additional window provided by NFA.

Cross-reference: Supporting document — Meridian Corrective Action Plan dated March 5, 2024, Bates Nos. [to be assigned].

3. Content of the Corrective Action Plan. Meridian's Corrective Action Plan contained the following principal elements:

(a) Proposed accelerated construction schedule. The plan proposed an accelerated construction schedule, stating that Meridian would deploy additional construction crews to increase the pace of Phase 3 construction. The plan did not, however, specify the number of additional crews, their geographic deployment, or the timeline for mobilization.

(b) Request for 9-month schedule extension. The plan requested a nine-month extension to the overall contract duration, which would have extended the original completion date of March 31, 2025 to approximately December 31, 2025.

(c) Request for $87 million in additional compensation. The plan requested $87 million in additional compensation, which Meridian characterized as compensation for alleged Owner-caused delays (permitting delays and unformalized scope changes). The $87 million figure was not supported by a detailed breakdown or calculation methodology in the Corrective Action Plan itself.

(d) Absence of milestone-by-milestone remediation schedule. The plan did not include a milestone-by-milestone remediation schedule setting forth revised target dates for each of the remaining milestones (Milestones 8 through 14). The plan spoke in general terms about "acceleration" but provided no specifics about when particular milestones would be achieved.

(e) Absence of quality corrective measures. The plan did not address corrective action for the 43 critical NCRs identified in Cure Notice No. 1, nor did it address the broader population of 287 NCRs. Quality remediation was not mentioned at all — a remarkable omission given that quality deficiencies were specifically cited as a basis for the material breach determination.

(f) No explanation of quality-crew nexus. The plan did not explain how the deployment of additional construction crews would address quality deficiencies, as opposed to solely accelerating the pace of construction. Additional crews, without corresponding quality improvement measures, could in fact exacerbate quality problems by introducing new workers unfamiliar with the project's quality requirements.

4. Analysis. The Corrective Action Plan was materially deficient in several respects. Most fundamentally, it transformed Meridian's cure obligation into a demand for contract renegotiation. Rather than committing to cure the identified breaches within the existing contractual framework — by achieving delinquent milestones, accelerating Phase 3 construction, and remediating quality deficiencies — the plan conditioned its proposed "cure" on NFA's agreement to (i) extend the contract by nine months and (ii) pay Meridian an additional $87 million. This was not a cure; it was a counteroffer.

The $87 million demand is particularly noteworthy. Even if Meridian had legitimate claims for additional compensation arising from Owner-directed changes or permitting delays (claims that are disputed and analyzed in separate memoranda), the assertion of such claims is not a substitute for the performance of the cure obligation. A contractor that is in material breach of a construction contract cannot condition its cure on the owner's agreement to pay additional money, particularly where the contractor has failed to follow the contractual procedures (Change Orders under MCA § 16.1) for securing additional compensation for changed conditions.

The failure to address quality issues was a critical gap. Cure Notice No. 1 had specifically identified 43 critical NCRs as a basis for the material breach determination. Cure Notice No. 2 had expressly requested that the remediation plan address quality corrective measures. The Corrective Action Plan was entirely silent on quality. This silence is inexplicable if Meridian genuinely intended to cure the identified breaches and strongly suggests that Meridian either could not or would not address the quality deficiencies that had plagued the project.

E. Northgate Rejects Corrective Action Plan — March 12, 2024

1. Author and Recipient. NFA's rejection of the Corrective Action Plan was communicated by letter from Renata Voss (VP of US Network Infrastructure, NFA) to Victor Sandoval (Managing Member and CEO, Meridian) and Bridget Yeung (COO, Meridian).

Cross-reference: Supporting document — NFA Rejection Letter dated March 12, 2024, Bates Nos. [to be assigned].

2. Content. The rejection letter contained the following key points:

(a) NFA rejected the Corrective Action Plan as inadequate and non-responsive to the breaches identified in Cure Notices No. 1 and No. 2.

(b) NFA cited 12 additional critical NCRs that had been issued during February 2024 — that is, during the cure period and after the issuance of Cure Notice No. 2. These 12 new critical NCRs demonstrated that Meridian's quality deficiencies were not only continuing but worsening during the very period in which Meridian was supposed to be curing its breaches. This brought the total number of critical NCRs to 55 (43 cited in Cure Notice No. 1, plus 12 issued in February 2024).

(c) NFA noted that Meridian's Corrective Action Plan failed to address quality corrective measures at all, despite the fact that both cure notices had specifically identified quality deficiencies as a basis for the material breach determination.

(d) NFA stated that Meridian's request for $87 million in additional compensation and a nine-month schedule extension was not consistent with a cure of the Contractor's material breach, but rather represented a demand for renegotiation of the contract.

(e) NFA reserved all rights under MCA § 14.1 (termination for cause) and MCA § 14.5 (consequences of termination for cause).

3. Significance. This letter is important to the litigation record for two reasons. First, it establishes that NFA gave full and fair consideration to Meridian's proposed cure before concluding that it was inadequate. NFA did not summarily reject the Corrective Action Plan; the rejection came seven days after its receipt and was accompanied by a detailed explanation of the plan's deficiencies. Second, the citation of 12 additional critical NCRs issued during February 2024 is powerful evidence that the breach was ongoing and uncured even after formal notice. The fact that quality deficiencies were worsening — not improving — during the cure period directly refutes any argument that Meridian was diligently pursuing cure.

F. Notice of Termination for Cause — April 1, 2024

1. Author and Recipient. The Notice of Termination for Cause was issued by Renata Voss on behalf of Northgate Fiber Americas Inc. to Victor Sandoval on behalf of Meridian Infrastructure Partners LLC.

2. Timing. The following timeline illustrates the deliberate pace at which NFA proceeded:

• 73 calendar days after Cure Notice No. 1 (January 18, 2024 → April 1, 2024).

• 41 calendar days after Cure Notice No. 2 (February 19, 2024 → April 1, 2024).

• 27 calendar days after Meridian's Corrective Action Plan submission (March 5, 2024 → April 1, 2024).

• 20 calendar days after NFA's rejection of the Corrective Action Plan (March 12, 2024 → April 1, 2024).

To place these durations in context: MCA § 14.1 required only 30 calendar days from the initial cure notice before the Owner could terminate. The 30-day cure period expired on February 17, 2024. NFA waited an additional 43 days beyond the contractual minimum — providing a second cure notice, inviting a Corrective Action Plan, reviewing it, rejecting it with a detailed explanation, and then waiting an additional 20 days — before issuing the termination notice. This extended timeline demonstrates that NFA afforded Meridian every reasonable opportunity to cure before exercising its termination rights.

3. Form and Delivery. The Notice of Termination was issued as a formal written notice. To ensure conclusive proof of delivery, NFA transmitted the notice through three independent delivery methods: (i) overnight courier service (Severin Partners LLC); (ii) electronic mail; and (iii) certified mail, return receipt requested. Delivery was confirmed through all three channels.

Cross-reference: Supporting document — Notice of Termination letter dated April 1, 2024, Bates Nos. [to be assigned].

4. Content. The Notice of Termination was a comprehensive document that recited the full factual and contractual basis for the termination. Its key provisions included:

(a) Termination for cause under MCA § 14.1, effective immediately. The notice stated that the MCA was terminated for cause under Section 14.1, effective as of the date of the notice (April 1, 2024).

(b) Recitation of grounds for termination. The notice identified the following as the bases for the termination:

(i) Meridian's persistent schedule delays across multiple milestones, constituting a material breach of MCA § 8.2, including but not limited to Milestone 3 (47 days late), Milestone 5 (22 days late), Milestone 6 (68 days late), Milestone 7 (91 days late), and Milestone 8 (134+ days late and never completed);

(ii) Meridian's failure to achieve Milestone 8 — the final milestone of Phase 2 — which remained uncompleted as of the termination date;

(iii) Meridian's inadequate Phase 3 progress, with only 340 of 9,700 route miles (3.5%) completed approximately nine months into the Phase 3 construction window;

(iv) A total of 287 NCRs, including 55 critical NCRs (43 identified in Cure Notice No. 1 plus 12 additional critical NCRs issued during February 2024), documenting persistent substandard workmanship in violation of MCA § 12.4 and Northgate Technical Specification NS-FIBER-2020; and

(v) Meridian's failure to cure any of the identified breaches despite two cure notices, a combined cure period of 73 days, and NFA's consideration of Meridian's proposed Corrective Action Plan.

(c) Invocation of rights under MCA § 14.5. The notice invoked NFA's rights under Section 14.5 to complete the remaining work using substitute contractors and to charge excess completion costs to Meridian.

(d) Reservation of right to draw on performance bond. The notice reserved NFA's right to draw on the performance bond issued by Ironclad Surety Group Inc. (Bond No. ISG-2020-NE-04417, penal sum of $120 million) to secure reimbursement for losses arising from Meridian's breach.

(e) Forfeiture of termination fee. The notice stated that, as a consequence of the for-cause termination under Section 14.1, Meridian forfeited any right to a termination fee under MCA § 14.3.

5. Significance. The termination notice was comprehensive and well-documented. It cross-referenced both cure notices and the rejected Corrective Action Plan, creating a clear documentary chain linking the cure notice process to the termination decision. The notice left no ambiguity about the grounds for termination or the contractual provisions on which it was based.

Most significantly, NFA afforded Meridian 73 days from Cure Notice No. 1 to termination — more than 2.4 times the 30-day minimum required by MCA § 14.1. This substantially extended timeline, combined with the issuance of two cure notices and the invitation and review of a Corrective Action Plan, provides compelling evidence that NFA acted in good faith and gave Meridian every reasonable opportunity to cure before exercising its termination rights.

G. Meridian Contests Termination — April 8, 2024

1. Author and Recipient. Meridian's contestation was communicated by letter from Victor Sandoval (Managing Member and CEO, Meridian) to Renata Voss (VP of US Network Infrastructure, NFA).

2. Timing. The letter was dated April 8, 2024 — seven (7) days after the Notice of Termination. This was the last pre-litigation correspondence between the parties on the termination issue.

Cross-reference: Supporting document — Meridian Contestation Letter dated April 8, 2024, Bates Nos. [to be assigned].

3. Content. Meridian's April 8, 2024 letter contested the validity of the termination for cause and included the following:

(a) Repetition of prior defenses. The letter repeated the three defenses previously asserted in Meridian's February 2, 2024 response — permitting delays, unformalized scope changes, and force majeure — without providing additional factual support or documentary evidence for any of them.

(b) New pretext allegation. The letter introduced a new theory: that the termination was pretextual and that NFA's true motivation was to bring the fiber build in-house or to re-procure the construction work at lower cost, taking advantage of what Meridian alleged were favorable market shifts in construction pricing that had occurred since the MCA was executed in 2020. This was the first instance of Meridian's "pretext" theory, which subsequently became the central theory of Count I of the Verified Complaint filed on July 15, 2024.

(c) Demand for termination-for-convenience fee. Meridian demanded payment of the termination-for-convenience fee under MCA § 14.3, which Meridian calculated as 8% of $630.3 million in remaining unperformed contract value, totaling $50,424,000. This demand was predicated on Meridian's theory that the for-cause termination should be recharacterized as a termination for convenience.

(d) Reservation of rights. Meridian reserved all rights, including claims for lost profits, unpaid invoices, and retainage.

4. Significance. This letter is significant for several reasons. First, it marks the first articulation of the pretext theory that has become central to Meridian's case. The timing of the allegation — raised for the first time after the termination had already occurred — is relevant to evaluating its credibility; the pretext theory was not mentioned in Meridian's February 2, 2024 response to Cure Notice No. 1 or in the March 5, 2024 Corrective Action Plan.

Second, the letter offered no new factual evidence in support of the pretext theory. The allegation that NFA intended to "bring the fiber build in-house or re-procure at lower cost" was conclusory and unsupported by any documentary evidence or factual specifics.

Third, and perhaps most telling, Meridian did not claim in this letter that it had in fact cured the identified breaches. At no point in the April 8, 2024 letter did Meridian assert that Milestone 8 had been achieved, that Phase 3 construction had accelerated, or that the NCRs had been addressed. Instead, Meridian attacked the legitimacy of the termination decision itself — an approach that implicitly concedes the factual premise of NFA's cure notices (that Meridian's performance was deficient) while disputing the legal conclusion drawn from those facts.

H. Meridian's Demand on Performance Bond — April 15, 2024

On April 15, 2024, Meridian filed a demand on Ironclad Surety Group Inc. for $120 million under Bond No. ISG-2020-NE-04417, claiming that it was the obligee under a separate subcontractor protection endorsement to the performance bond.

This demand is disputed by both NFA and Ironclad. NFA, as the Owner, is the named obligee on the performance bond. Meridian's claim of a subcontractor protection endorsement is inconsistent with the express terms of the bond instrument. The bond demand is the subject of a separate analysis and coordination effort with Ironclad Surety Group.

Cross-reference: Supporting documents — Meridian's bond demand letter dated April 15, 2024, Bates Nos. [to be assigned]; memo re Ironclad Surety Group coordination.

V. Summary of Compliance with MCA § 14.1 Procedural Requirements

This section provides a consolidated summary of NFA's compliance with each of the procedural requirements of MCA § 14.1 for termination for cause.

A. Written Notice Requirement — Satisfied

MCA § 14.1 requires the Owner to provide the Contractor with written notice specifying the breach. NFA provided not one but two written cure notices:

• Cure Notice No. 1 (January 18, 2024) was a formal written notice specifying the breaches: Milestone 8 delay, Phase 3 inadequate mobilization, and 43 critical NCRs.

• Cure Notice No. 2 (February 19, 2024) reiterated and supplemented the specified breaches, noting the failure to cure within the initial 30-day period and providing an additional opportunity for Meridian to present a remediation plan.

Both notices were transmitted via overnight courier and email, and delivery was confirmed. The written notice requirement was satisfied with margin.

B. Specificity of Breach Identification — Satisfied

MCA § 14.1 requires the written notice to specify the breach. Both cure notices met this requirement with a high degree of specificity. The notices identified:

(i) Failure to achieve defined milestones, specifically Milestone 8, in violation of MCA § 8.2;

(ii) Persistent schedule delays across Phases 1 through 3, with specific day counts for each milestone (47, 22, 68, 91, and 134+ days);

(iii) Quality deficiencies documented in 43 critical NCRs, in violation of MCA § 12.4 and Northgate Technical Specification NS-FIBER-2020; and

(iv) Inadequate Phase 3 mobilization (340 of 9,700 route miles completed, or 3.5%).

The notices were not vague or general — they pointed to specific contractual provisions, specific milestones, specific day counts, and specific quality documentation. Meridian would have difficulty arguing that it was not adequately apprised of the nature and scope of the alleged breaches.

C. 30-Calendar-Day Cure Period — Exceeded

MCA § 14.1 requires 30 calendar days. Cure Notice No. 1 was issued January 18, 2024. Delivery was confirmed January 19, 2024. The 30-day cure period expired on February 17, 2024.

NFA did not terminate on February 17 or 18. Instead, NFA issued Cure Notice No. 2 on February 19, 2024, extending the process and providing Meridian with a further 15-day window to present a detailed remediation plan. NFA then reviewed Meridian's Corrective Action Plan (received March 5, 2024), rejected it with a detailed explanation (March 12, 2024), and waited an additional 20 days before issuing the termination notice on April 1, 2024.

The total elapsed time from Cure Notice No. 1 to termination was 73 days — 2.4 times the 30-day contractual minimum. This is not a case in which the Owner rushed to terminate at the earliest possible moment; to the contrary, NFA provided more than double the required cure period before exercising its termination rights.

D. Failure to Cure — Established

The record demonstrates beyond any reasonable dispute that Meridian failed to cure the identified breaches at any point during the 73-day period from Cure Notice No. 1 to termination:

• Meridian's February 2, 2024 response disputed the breach characterization but did not take any corrective action or present a remediation plan. It did not address the quality deficiencies at all.

• Meridian's March 5, 2024 Corrective Action Plan requested a nine-month schedule extension and $87 million in additional compensation rather than committing to cure deficiencies within the existing contractual framework. It did not address quality issues. It did not include a milestone-by-milestone schedule.

• Twelve (12) additional critical NCRs were issued in February 2024 — during the cure period — demonstrating that quality deficiencies were continuing and worsening, not being cured.

• No milestone was achieved by Meridian during the January 18 – April 1, 2024 period. Milestone 8 remained uncompleted. Phase 3 progress did not meaningfully advance.